Question 1

How should a minor quality control failure during the creation of a product be addressed initially?

Options:

A.

By escalating the issue to the project manager

B.

By performing an independent review of the product

C.

By revisiting the development and test activities

D.

By discussing with the chief product owner

Question 2

Which of the following uses a flow-based approach to control work in progress?

Options:

A.

Agilometer

B.

Lean

C.

Kanban

D.

Scrum

Question 3

Which of the following integrated elements defines who is working on the project and who is affected by the project?

Options:

A.

The project context

B.

The PRINCE2 practices

C.

The PRINCE2 processes

D.

The “people” element

Question 4

Which statement about timeboxes is CORRECT?

Options:

A.

Flow based working partitions work into timeboxes

B.

A project cannot be referred to as a timebox

C.

A timebox can contain another timebox

D.

Timeboxes should be avoided in business as usual environments

Question 5

How should product-based planning be used as part of PRINCE2 Agile?

Options:

A.

To track progress against the team plan

B.

To create the project plan using empiricism

C.

To enable team planning to be predictive

D.

To plan by focusing on the features required

Question 6

What is a role of personas in the 'business case' practice?

Options:

A.

To group users based on demographic data

B.

To ensure project timelines are met

C.

To identify and articulate specific user benefits

D.

To differentiate between product versions

Question 7

What is an epic?

Options:

A.

A detailed user story with high business value

B.

The set of products handed over to the users

C.

A high-level user story that is quite broad or vague

D.

A prioritized list of requirements to be delivered in a sprint

Question 8

Which workshop is used to assess the project’s status and address any challenges?

Options:

A.

Team planning workshop

B.

Project retrospective workshop

C.

Team retrospective workshop

D.

Progress review workshop

Question 9

Which practice has the purpose of controlling uncertainties that would affect the project’s objectives?

Options:

A.

Plans

B.

Issues

C.

Quality

D.

Risk

Question 10

What is the MOST important when blending PRINCE2 Project Management with agile?

Options:

A.

Adopting agile mindset

B.

Fostering psychological safety

C.

Using agile techniques

D.

Following agile processes

Question 11

Which is a typical characteristic of ‘business as usual’ work?

Options:

A.

It requires a specific dedicated project manager

B.

It is executed by program management

C.

It is delivered by a temporary team

D.

It is delivered by an established team

Question 12

Which statement about the PRINCE2 Agile behaviour ‘collaboration’ is CORRECT?

Options:

A.

It allows many small learnings to accumulate over time

B.

It allows the delivery team to decide how best to get the job done

C.

It creates a shared ownership of goals

D.

It uses the most effective channel to communicate

Question 13

Which should be an objective of a retrospective?

Options:

A.

To identify many process improvements and implement them

B.

To identify key process improvements to implement in the next sprint

C.

To encourage the team to bond by allowing social activities to take place

D.

To focus on objective learning rather than subjective feelings and emotions

Question 14

Which workshop enables participants to collaboratively define the Definition of Ready?

Options:

A.

Starting up workshop

B.

Project kickoff workshop

C.

Project initiation workshop

D.

Agile enablement workshop

Question 15

How does the change theme regard change in PRINCE2 Agile?

Options:

A.

As disruptive

B.

As something to be avoided

C.

As a necessity

D.

As inevitable

Question 16

What is a responsibility of the team coach?

Options:

A.

To liaise with the agile coach

B.

To liaise with the project manager

C.

To liaise with the chief product owner

D.

To liaise with project assurance

Question 17

What challenge does PRINCE2 Agile address in Agile adoption?

Options:

A.

Agile frameworks are too rigid for product delivery

B.

Agile frameworks struggle to scale for large, complex initiatives

C.

Agile frameworks struggle with role definitions

D.

Agile frameworks cannot be combined with other methods

Question 18

Which practice supports identification and assessment of uncertainties?

Options:

A.

Risk

B.

Plans

C.

Quality

D.

Business case

Question 19

Whose interests are specifically represented by the senior supplier?

1. Those ensuring the project is value for money.

2. Those who will use the project’s products.

3. Those who will be developing the project’s products.

4. Those responsible for the project’s technical integrity.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 20

Why are team working agreement produced?

Options:

A.

To create structure so that the team manager can assess individual performance

B.

To evolve the effectiveness and behaviors of the self-organizing team by agreeing values

C.

To make the team rules visible to the project manager for monitoring purposes

D.

To ensure that the delivery team members comply with company policy

Question 21

Which statement about the ‘embrace change’ target is CORRECT?

Options:

A.

It minimizes the time needed to train a new team member

B.

It reduces the planning of dependencies between projects

C.

It reduces testing in order to meet deadlines

D.

It encourages the customer to raise new ideas

Question 22

Which organizational level is responsible for day-to-day management and decision making within the constraints established by the project manager?

Options:

A.

Commissioning

B.

Directing

C.

Managing

D.

Delivering

Question 23

Which is a benefit of the Lean Startup approach to releasing a product?

Options:

A.

It provide a technique to reduce the testing of a product before release

B.

It enables the release plans to be synchronized with the PRINCE2 plans

C.

It reduces the number of people needed to manage a release of a product

D.

It provides quick feedback that can be responded to at the earliest opportunity

Question 24

Which statement defines a PRINCE2 principle?

Options:

A.

A PRINCE2 project defines its quality management approach

B.

A PRINCE2 project is monitored and controlled on a stage-by-stage basis

C.

A PRINCE2 project ensures a consistent approach to risk management

D.

A PRINCE2 project is tailored to suit the competitor’s environment

Question 25

Which artifact is used to describe the project's major products in the form of epic user stories?

Options:

A.

Project dashboard

B.

Release map

C.

Product backlog

D.

Project backlog

Question 26

What is typically displayed on a board to show progress to people working on a project?

Options:

A.

Agilometer assessment

B.

Product backlog

C.

Information radiator

D.

User story

Question 27

Which statement about quality tolerances for a product is CORRECT in an agile context?

Options:

A.

All quality criteria tolerance must be fixed

B.

Quality tolerances should be the same for all quality criteria

C.

Setting quality tolerance relies on prioritising quality criteria

D.

All quality criteria should have zero tolerance

Question 28

Which statement describes how the “risk” practice should be applied?

Options:

A.

Agile adoption issues should be identified by using the Agilometer

B.

Trading should be used to handle emerging changes

C.

An objectives and key results framework should be used

D.

A set of criteria in the Definition of Done should be identified

Question 29

In which workshop are the project role descriptions created?

Options:

A.

Starting-up workshop

B.

Project kickoff workshop

C.

Project initiation workshop

D.

Project canvas workshop

Question 30

Which of the following is a benefit of 'being and doing agile'?

Options:

A.

Following processes

B.

Using agile techniques

C.

Increasing user satisfaction

D.

Focusing on completing tasks

Question 31

What is the purpose of the “agile enablement” workshop?

Options:

A.

To identify, assess, and plan for risks associated with project delivery

B.

To identify, assess, and plan for risks associated with team delivery

C.

To identify, assess, and plan for risks associated with Agile adoption

D.

To identify, assess, and plan for risks associated with enterprise agility

Question 32

Which technique is used in the ’Issues' practice?

Options:

A.

Trading/swapping

B.

Objectives and key results

C.

Refactoring

D.

Delegation poker

Question 33

What is a purpose of the 'team planning' workshop?

Options:

A.

To update the project dashboard

B.

To update the product backlog

C.

To update the release map

D.

To update the OKRs

Question 34

In which process is a workshop conducted to agree the Definition of Ready (DoR) and Definition of Done (DoD)?

Options:

A.

Initiating a project

B.

Directing a project

C.

Controlling a stage

D.

Managing product delivery

Question 35

When should PRINCE2 Agile be used?

Options:

A.

When a team is created to deliver a specific product

B.

When delivering an ongoing service to a customer

C.

When an established team performs product maintenance

D.

When simple requests to update a product are implemented

Question 36

Which tool is used to assess risks associated with Agile adoption?

Options:

A.

Enterprise agility assessment

B.

Project dashboard

C.

Agilometer assessment

D.

Cumulative risk burn-down chart

Question 37

Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?

1) It should be replaced by the project manager attending a daily stand-up.

2) It should be displayed in the form of an information radiator in a team room.

3) It should be produced when the amount to be delivered will result in tolerance being exceeded.

4) It should be produced in a product backlog in the form of prioritized user stories.

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 38

How does PRINCE2 Agile describe Scrum?

Options:

A.

Scrum is an IT method

B.

Scrum is agile and agile is Scrum

C.

Scrum is the most well-known agile framework

D.

Scrum is a project management framework

Question 39

Which is a key objective of running a workshop?

Options:

A.

To make daily progress visible to the delivery team and key stakeholders

B.

To encourage collaboration and create the defined outputs from the event

C.

To communicate decisions to the wider stakeholder community

D.

To make day-to-day decisions on behalf of the delivery team within a sprint

Question 40

Which statement about the ‘accept that the customer doesn’t need everything’ target is correct?

Options:

A.

It gives confidence on the progress of the project

B.

It can result in the early delivery of a minimum viable product

C.

It allows misunderstandings to be dealt with appropriately

D.

It is achieved by managing the culture of the team carefully

Question 41

Which statement about the ‘be on time and hit deadlines’ target is CORRECT?

Options:

A.

It allows change to be handled dynamically

B.

It is achieved by keeping the delivery teams stable

C.

It helps with planning dependencies within a project

D.

It ensures that the level of quality is protected

Question 42

What is the MOST LIKELY benefit from frequent releases into operational use?

Options:

A.

Feedback is obtained from real customers

B.

The need for customer involvement is increased

C.

The risks associated with agile ways of working are assessed

D.

The need for configuration management is reduced

Question 43

Which statement about the ‘keep teams stable’ target is CORRECT?

Options:

A.

It ensures that the level of quality is protected

B.

It will lead to a lower cost of ownership

C.

It is required in order to allow the team to self-organize

D.

It results in the earth delivery of a minimum viable product

Question 44

What role does AI play in addressing project complexity within PRINCE2 Agile?

Options:

A.

It helps reduce all sources of project complexity

B.

It adds layers of complexity through excessive automation

C.

It helps reduce uncertainty and ambiguity associated with change initiatives

D.

It ensures stakeholder involvement in all decision-making

Question 45

When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

Options:

A.

How to adapt the PRINCE2 management products

B.

How to select which Agile framework should be favoured

C.

How to decide whether PRINCE2 is appropriate

D.

How to calculate the project budget and cost tolerance

Question 46

Which of the following is a common challenge when merging project management and Agile?

Options:

A.

Lack of clear processes

B.

The use of different terminology

C.

Lack of guidance at project level

D.

The use of a flexible framework

Question 47

In which step of the approach to issue management are options to resolve an issue evaluated?

Options:

A.

Capture

B.

Implement

C.

Decide

D.

Recommend

Question 48

Which is a collaborative technique for defining decision-making within teams?

Options:

A.

Delegation poker

B.

Team skills matrix

C.

Personas

D.

Magic estimation