An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.
During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?
A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.
What should the project manager do?
A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to
take action in advance to ensure the project succeeds.
What should the project manager do?
A project manager became aware of misunderstandings between a key stakeholder
and a team member with regard to some of the features defined in the project scope. What
should the project manager do?
A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload
What should the project manager do to optimize the time of the resource who produces the progress reports?
A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.
What technique is the project manager applying?
A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?
A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.
What should the project manager do?
A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.
How should the project manager handle this situation?
A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.
What should the project lead have done initially to avoid this situation?
A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs
to be delivered to the customer as a ready-to-use product .
Based on this scenario, what should the project manager focus on throughout the project life cycle?
A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.
What should the project manager do next?
A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit
Which two rules are appropriate tor the project manager to instill in the team? (Choose two)
During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.
How should the project manager handle this situation''
During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead
handle this situation?
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?
A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.
What should the project manager do given the urgency?
A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.
What should the project manager do next?
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager
What should the project manager do first in this situation'?
An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?
A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water
What caused this situation to occur?
A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?
After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?
A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.
A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor
What should the project manager have created to prevent this situation1?
A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs
How should the project manager ensure the work continues smoothly?
A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need
What should the project manager do'?
A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools
In order to deliver the project successfully, what should the project manager focus on as part of the plan?
A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.
What should the project manager do?
project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?
A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.
What should the project manager do?
A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in
one of the project teams.
What should the project manager do?
A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.
How should the project manager proceed?
A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.
What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?
A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important
milestone in a week.
What should the project manager do next?
A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.
What should the project manager do?
A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.
What should the project manager do next?
A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.
How will the project manager be able to complete this task?
In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?
A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented
What should the project manager do?
A project manager needs the team to define the steps and identify the risks of migrating data to a new system.
What type of leadership should the project manager use to accomplish this?
A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?
How should the project manager reply to the product owner?
A project is approaching its project closure phase, and the project manager receives
an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.
Which three actions should the project manager ask the project specialist to take? (Choose
three)
A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?
A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer's standards
in order to ensure this, what should the project manager define and document?
A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,
What should the project manager do?
A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.
What should the project manager have done*?
During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.
What should the project manager do to reduce exposure?
A project team is implementing a new solution that will be distributed worldwide. Due to a new issue that has a global impact, several government agencies are implementing new regulations that will affect the solution. The project manager must assess and prioritize the impact of these changes on the project scope/backlog.
Which analytical tool can be used by the project manager to define this scenario?
A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?
A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,
What should the project manager do first?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,
yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?
A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members
Which three actions should the project manager take? (Choose three)
A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules
Which two actions should the project manager take with regard to schedule analysis? (Choose two)
A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.
How should the project manager resolve this conflict?
A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.
What should the project manager do to communicate with the stakeholders?
we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.
What should the project manager do?
A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team
What should the project manager do to resolve this?
A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.
What should the project manager do?
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a
requirement for a user experience design approach.
Which project management approach should the project manager use?
A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?
A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.
How should the project manager have handled the situation?
A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value
What should the new project manager do next?
A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?
An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but
the agile coach and technical writer feel that is an inconvenient time for them.
How does the project lead ensure adherence to agile practices?
Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.
What should the project manager do to engage the stakeholders?
A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required
What should the project manager do?
A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?
A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution
What should the project manager do?
A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.
What should the project manager do?
A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.
What should the project manager do?
A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.
What is the appropriate course of action for the project manager to pursue?
One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority
What should the project manager do to mitigate the risk of not having the materials printed on time?
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.
In order to help the team, what should the project leader do?
A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team
What should the project manager do?
A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has
doubts about the feasibility of the project.
What should the project manager do in this situation?
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay
What should the project manager do next?
After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.
What should the project manager do next?
A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team
members and stakeholders who have contradictory opinions.
What should the project manager do?
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.
What tool should the project manager use to conduct meetings with the project team and clients?
A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.
What should the agile leader do?
A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team
What should the project manager do?
A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.
Knowing that there are no additional funds available, how should the project manager proceed?
Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?
The project team is planning a schedule with limited information. The team |s having
issues identifying the detailed tasks and estimating task durations.
Which three techniques should the project manager use? (Choose three)
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix
What should the project manager do with regard to community engagement in this situation''
A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be
enough to add business value.
With the project on a fixed budget, what should the project manager do next?
During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.
How should the team share tacit knowledge?
A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.
What should the project manager do?
A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.
What should the project manager do moving forward?
A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward
What should the project manager do first at this pomp
A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.
What should the project manager do to address this concern?
A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff
What should the project manager do first?
An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.
What should the project manager do?
A project team is executing a project to replace an existing system with a new one.
A new project manager has been hired and observes that the team consist of professionals
who have worked with the older system, and others who have little previous experience.
What should the project manager do to ensure project success?
A customer calls the project manager to express concern about a project team
member who has been making changes within the live environment without approval. The
team member mentioned that the customer called and asked them to make the changes.
What should the project manager do next?
A project manager is assigned to a new water treatment plant project that has been
delayed for many years. It is revealed in the project charter that the sponsors of this project
are from three different business units. This is the first time the sponsors have ever
implemented such a project.
What should the project manager do?
A project with multiple teams recently transitioned from a predictive approach to agile
as requested by the product owner. Midway through implementation, a team member noticed
there was no technical capability to support the current business requirement; therefore, the
project will need to be reworked and the issue needs to be communicated to all stakeholders.
What should the agile project lead have done to avoid this situation?
One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.
What should the project manager do?
A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.
What should the project manager do next?
A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.
A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity
How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?
A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days
What should the project manager do first to maintain the project team's performance level?
A project team delivered a critical deliverable to the customer. The customer
complained that the maintenance manual was not included.
What should the project manager do next?
A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.
What should the project manager do?
An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project
How should the agile leader ensure successful delivery?
A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met
How should the project manager approach the stakeholder?
A project sponsor has requested a trend analysis of all risks that the project has
monitored over the past 12 months. What should the agile project manager do?
A project manager is leading a project at a contracting company, and the project
team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.
What should the project manager do to avoid this situation in the future?
A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.
What should the project manager do in this situation?
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.
A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities
What should the team do differently during planning for the next iteration"?
A new project manager has been assigned to an environmental project. After
reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.
Why is this situation problematic?
Two learn members are consistently having misunderstandings and find it difficult to work together. How should the project manager handle this situation?
During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer's request will affect the sales department's budget and forecast.
In order to reach a consensus and have a successful project completion, what should the
project manager do first?
During the project planning phase, a project manager called a meeting to discuss the
product backlog with multiple stakeholders who represent the end users in various capacities.
Only one executive manager attended the meeting.
What should the project manager do?
A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.
How should the project manager address this?
A hybrid project is experiencing several issues with both the agile delivery of the
product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?
A project manager is managing a government project that targets the development of
small businesses in remote towns. The project team is having difficulty conducting
entrepreneurship training in some of the targeted towns because the local municipal
governments will not authorize the training. As a result of the delay, project implementation is at risk.
What is a probable reason for this?
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
A project manager has been assigned to a new project. There is one team member
who never says anything during meetings. After meetings, however, the team member sends
detailed emails with very good suggestions that help with project execution.
How should the project manager guide the team members?
A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback
What should the project manager do to resolve the issue?
A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?
During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?
A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team
What should the project manager do first to solve the situation?
A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.
What should the project manager do to address this issue?
Vendor A submitted a bid for US$500,000. There is a 65% probability that the
vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come
in ahead of schedule for a savings of US$50,000.
What should the project manager determine as the value of the vendor's bid?
A project manager is working on a highly complex project. During the execution of
the project, the local government changed certain environmental regulations, which could
potentially delay the project.
What immediate action should the project manager take?
A project manager has been assigned with initiating a large project to deliver complex equipment Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.
Which approach should the project manager choose for this project?
A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.
What should the project manager do to avoid these challenges?
A project manager is leading the first agile project for the organization. During the
kick-off meeting, the project manager notices that the team does not have the same
understanding about agile approaches. The project manager is concerned about the impact of that confusion.
What should the project manager do to address this situation?
A project manager is assigned to a project related to taxes, which will be managed
using an agile approach. By reviewing lessons learned from a previous project, the project
manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?
A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?
During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?
A project manager is developing a project baseline schedule and has started to
assign team members to the project activities according to their function. What should the
project manager do in this phase?
In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan
What should the project manager do?
During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?
A project requires testing of the final product to be done at another department's
testing facility, which is known for having low availability. This situation could potentially
impact the project schedule.
What should the project manager do next?
A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project
How should the project manager report this cost?
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.
What should the project manager do?
A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person
What should the project manager do first?
A project manager has noticed that a critical team member is consistently arguing
with a client. This has started to have a negative effect on the meetings.
How should the project manager address this?
A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?
A customer interacts directly with a Scrum team and continually requests changes in
priorities. This causes confusion among the team members and they complain to the project
manager.
What should the project manager do?
During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.
What should the project manager do to address the issue?
Eight people have been working on a project for an extended period of time. The
scope has changed significantly and the product owner has been replaced multiple times. The
team members are feeling disassociated from the project.
What should the project manager do to ensure team alignment with the goals?
A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.
What should the previous project manager have done to prevent this issue?
The change control board (CCB) has approved a change request to add a new
component within a product. The operations manager discovers the change after its approval
and complains that the implementation of the change will cause significant disruption to the
production line.
What should the project manager do first?
A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some
reserves needed
What should the project manager do to successfully complete the next phase?
During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements
Which technique should the project manager use to resolve this issue?
A project has been running for 2 months and now requires approval for a supplier to
begin some execution tasks. The project team has evaluated several suppliers and selected
their top two preferred suppliers. The project sponsor requested that another supplier who has
lower costs be added to the list. However, the project manager is aware that this supplier
does not always fulfill the project requirements.
What should the project manager do?
A project manager is leading an electrical project that spans five towns. The project
manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?
A new privacy law will go into effect at the beginning of the next calendar year. The project manager realizes the project needs to be compliant with the new law. What should the project manager do next?
A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract
What should the project manager do?
During the planning for a long project, the project manager recognized that several
members of the team are new to their roles. How should the project manager incorporate this
into planning?
During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?
A project manager is assigned to lead a design for a new version of an existing
product with the technology and operations teams. The project manager organizes a joint
requirements session to determine the most practical ideas. The project manager was advised
that the session may become chaotic.
What should the project manager do to ensure the session is interactive, productive, and
efficient?
In an ongoing project, stakeholders have been approaching team members for status
reports and changes without consulting the project manager. What should the project
manager do to ensure a successful project?
A project team that is very experienced in enterprise resource planning (ERP)
systems implementation is currently planning the delivery of a new ERP project. There is a
requirement to reuse the client's security subsystem developed by a third party. The client
states that integration with the security subsystem must be done by the client's team. The
project manager does not want to have such an external dependency.
What should the project manager do first?
During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?
A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.
What should the project manager do?
A subcontractor informs the project manager that they are unable to supply a key
component to the project. What should the project manager do?
A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?
An issue reoccurs six months after a project's go-live date despite being resolved
during the project life cycle. What should the project manager have done in the previous
phase to avoid this issue?
An international client contacted a software development company to build out a
software product, and an agile project manager was assigned. At one of the review meetings,
the client complains that a feature mentioned at the initial debriefing was not implemented.
What should the project manager do?
In an agile product development environment, work is distributed to Cities A, B, and
C, which are geographically dispersed. The small teams work and collaborate to deliver the
sprints.
• City A's team focuses on the features of data capture.
• City B's team focuses on the user experience and development pieces.
• City C's team coordinates testing.
What should the project manager do to ensure a successful rollout of sprints?
The sponsor approaches the project manager with new features they want added to
the project. The project is 95% complete, but the sponsor insists that continued support for the
project relies on the addition of the new features.
What should the project manager do?
An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.
What tools should the agile project manager use to do these estimates?
A project manager working on a large-scale network implementation is frustrated
with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.
What should the project manager do first to proceed with this change?
On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.
How should the project manager set up communications?
A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.
What should the project manager do?
Toward the end of a protect the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?
A team member is openly criticized by others during a standup meeting for failing to
complete yesterday's tasks. What should the agile coach do first to address the situation?
An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed
What action should the project manager take?
A project manager is leading a hybrid project. The self-organizing teams are
continually late in delivering their demos, resulting in low morale. The steering committee is
familiar with the reporting and planning associated with a predictive approach and is
concerned about the project because it is unclear if the expected value will be delivered.
What should the project manager do?
A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?
A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items
What should the project manager do as a servant leader?
On a project with multiple international locations, a trend for delays has been
flagged. When looking into the issue, the project manager realized that some of the key
activities were scheduled over the holiday periods in the overseas offices.
What should the project manager do next?
During the execution of a construction project, the project sponsor asks to make
changes to the floor plan by adding a minimal storage room. The sponsor insists on making
this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.
Which two things should the project manager do? (Choose two)
During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts
What should the project manager do?
During a meeting with a customer, it was determined that participants of the meeting
had different draft versions of an important design document. What should the project
manager do first to ensure that this does not happen again?
An organization started the process of a digital transformation and is trying to change
its culture from a predictive to a more agile approach. The project manager leading the
change management process identified some knowledge gaps of key team members, which
could prevent the transformation from happening as planned.
What should the project manager do?
The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?
us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?
During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?
A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.
What should be me project manager's response?
The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?
A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to
ensure the community members are up to date on project progress?
A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of
risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk
mitigation plan.
What should the project manager do?
A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.
What should the project manager do?
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.
What should the project manager do next?
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because
of that, each feature is taking longer than initially estimated.
What should the project manager do to address the issue?
A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change
requests issued due to the nature of the project.
What should the project manager do?
A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do?
A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.
Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three)
A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.
How should the project manager address the employee's request?
After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?
A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to
reduce conflicts in the company’s internal tracking system. With over 1,000 people in the company who will benefit from the software, the project
manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide
upon the most effective way to communicate progress.
What should the project manager do?
A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does
not have a requirement for it.
What should the project manager do?
During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.
How should the project manager help guide the lead developer?
A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.
How should the project manager respond to this request?
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience
performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.
What should the project manager recommend?
A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?
The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:
• The marketing director is the key stakeholder. as the project will create a new product for the company.
• The finance director is providing funding and does not have much time to follow the tracking of the project.
• The sales representatives assigned to the team provided some negative feedback on the requirements
• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.
A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.
What should the project manager do?
A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project
manager for mentoring.
Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)
In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project
manager do?
The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?
A project manager is managing a complex project with a high number of artifacts. Some of the stakeholders are having issues accessing the artifacts. How should the project manager address this situation?
A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.
Match the roles for the team on the left to their corresponding responsibilities on the right.
A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the
project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’
experience as an agile practitioner working as a scrum master.
What should the project manager do at the start of the project?
An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is
informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.
What should the project manager do first?
A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall
progress.
What should the project manager do next?
In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.
What should the project manager do?
During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project
manager is not sure if some of the project deliverables will be fully compliant with the new requirements.
What should the project manager do?
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.
What should the project manager do in this situation?
A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of
the team. What should the project manager do?
A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.
What should the project manager do?
A project manager is reviewing the status of a large project with team members in different countries. Through the status review, the project
manager notices that one team is consistently behind schedule and their work often needs to be corrected.
What should the project manager do to improve the quality of this team's work?
A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as
something that will work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?
A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety
approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.
What is the appropriate flow for product development?
A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project.
What should the project manager do?
A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.
How should the project manager proceed?
A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.
What should the project manager have done to avoid this situation?
A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and
delay new feature development.
Which action should the project manager take to resolve the quality issues?
A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project
stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.
What should the project manager do?
A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly.
This uncertainty from the junior engineers is now slowing progress.
‘What should the project manager do?
During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much
experience in development.
What should the project manager do?
A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically
last 45 minutes with many misunderstandings due to language barriers.
How should the project manager resolve this issue for the next iteration?
A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager
has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management
competencies. The project manager explains that the exiting team members were lazy.
What should the project manager do to prevent this high turnover rate from continuing?
A project team needs to follow regulatory compliance guidelines that are mandatory for the project. What should the project manager do to ensure compliance adherence?
A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?
During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific
component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality
management plan and there is no reference to this component.
What should the project manager do next?
In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in
conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
An experienced project team member always points out the issues of other team members during meetings. The other team members feel that
the experienced team member is deflecting their own issues in meetings.
What should the project manager do?
An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.
What should the project manager, who is responsible for this project, do to mitigate this risk?
A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,
What should the project manager, as a servant leader, do to address this situation?
A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?
A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?
A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide
any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.
What should the project manager do to ease the situation?
During the implementation phase of a project, functional managers are adding new requirements, which may impact cost and schedule baselines. The project manager
notices that some of the team members are communicating with their managers directly to fulfill their requests. This will lead the project to go beyond the agreed baselines.
How should the project manager handle this situation?
A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one
member reported an impediment that requires collaboration from an expert who is assigned to another project.
What should the project manager do first in this situation?
During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager
react to ensure the project remains successful?
A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.
What should the project manager do In this scenario?
When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a
result, the team ground rules favor these two team members.
What should the project manager have done to avoid this situation?
A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.
What should the project manager do?
A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.
What should the project manager do?
After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?
After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.
Which phase of the Tuckman ladder of team formation is occurring?
A project manager is working on a software development project. The project manager and the project team identified the project risks. As the
project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.
At what point did the project manager move the risk from the risk register to the issue log?
An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.
What should the project manager do to avoid this situation in the future?
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.
What should the project manager do?
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.
Which stakeholders should the project manager consult with first to manage interdependencies?
A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.
What should have been done to avoid this problem?
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.
What should the project manager do to manage business concerns and expectations before starting the project?
A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.
Which action should the project manager take to address the sponsor's request?
A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for
the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.
Which stakeholders should the project manager include in the stakeholder engagement plan?
A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.
What should the project manager do?
A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.
How should the project manager approach this situation?
A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a
dependency missing between:
+ Test the product
+ Release to customer
According to the quality management plan, the product must be tested before being released.
How should the project manager enter this dependency?
During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the
required IT system. What should the project manager do?
A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the
project manager ensure that the needs of stakeholders are consistently met?
One of the team members is always late to the daily standup meeting. What should the project manager do?
A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.
How should the project manager ensure the acceptance criteria are ret?
Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.
What should the project manager do?
In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.
What should the project manager do next?
A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.
What should the project manager do first?
The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could
resolve the bottleneck, and the project manager has been informed.
What should the project manager do next?
A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.
What should the project manager do?
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the
quality standards required by regulations.
What should the project manager have done to avoid this?
A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.
What should the project manager do?
A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.
What should the project manager do to keep the team performing as effectively as possible?
An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile
practices, which are relevant to the project.
What should the project manager do in order to gain buy-in from the different stakeholders?
A functional manager is concerned that the project's quality management techniques have advanced beyond the department's capabilities and wants the project team to review all quality management activities in two full-day workshops the following week. What should the project manager do next?
A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The
engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to
complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete
items with associated regulatory components as they are essential items.
How should the project manager prioritize the work items?
A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.
What should the project manager do?
A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became
concerned that the product quality will be sacrificed.
What should the project manager do?
A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway
through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.
What should the project manager have done to prevent this situation?
An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.
Which release strategy should the project manager recommend?
A project management team received news that a competitor has released the
latest version of a program. What should the team do next?
A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.
What should the project manager do?
The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.
What should the project manager do to resolve and prevent additional arguments?
A project needs to purchase a specific piece of equipment, as stated in the
project documents and approved by the project sponsor. The procurement division is
questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.
What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?
The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.
What strategy should the project manager use in order to keep delivering value in a restricted environment?
An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager
do with many tasks still open on the Kanban board?
A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team. What should the project leader do to improve the situation?
A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?
An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.
Which evaluation practice should the project lead use to obtain accurate usage data?
During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.
The customer is asking the project manager for guidance.
What should the project manager do?
During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?
A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.
Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.
The company asked the project manager to explain the value gained by using an agile process.
How should the project manager respond?
Match the project situation on the left to the meeting on the right where the situation could occur.
A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project
How should the project manager proceed?
A company is transitioning from a predictive to agile delivery of projects. Based on
the requirements, the project team estimates the budget and decides to use a fixed-price
contract with its vendor. However, during the execution of the project, the requirements
evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.
What should the project manager do next?
A team is assembled for a new project that will be using a predictive approach through requirements gathering and an agile approach for development and testing Not everyone on the team has experience working in agile. The schedule has started slipping due to the unclear structure of the agile development approach.
What should the project manager have done to avoid this situation?
A junior team member escalates an issue to the project manager about another
member's interpersonal skills causing the team to be less effective.
What should the project manager do first?
The operations director complains to the CEO about the outcome of a project's first sprint The operations department will not be able to support a new product due to poor performance indicators The project team facilitator asks for feedback from the project team and is informed that performance information is available in the application server log
How should this complaint be addressed?
A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?
An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.
What should the project manager do to address this concern?
During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?
Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.
What should the project manager do next?
A project manager has been asked to participate in the procurement process for a
software application that allows customers to buy online e-learning courses. The project
manager will take over the project once the supplier has been sourced.
What should the project manager do before the project starts?
local company is developing a new product and. for the first time, using a remote
team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's
outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.
How should the project manager address this situation?
In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement
How should the project manager respond to the suggestion?
A company has hired a vendor to deliver a scope of work and assigned a project
manager to oversee the project. The vendor advised that they completed the scope
successfully and is asking for approval.
What should the project manager do in response to this request?
A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.
What should the project manager have done to prevent this conflict?
A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.
What should the project manager do first?
A contractor delivering construction services to a company is using agile principles
to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design
changes or performing rework.
What should the project manager do to minimize the cost?
When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?
A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?
A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?
A project manager is working on a large project with a very difficult client. During
the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.
How should the project manager approach this?
According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.
What should the project manager do?
A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?
An agile project team is building a new product. The stakeholders require ongoing
illustration of project business value.
How should the project manager proceed?
A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)
Due to a recent budget reduction, two team members were released from an agile
team. The customer is still expecting early results for the project.
Which two actions should the project manager take to align customer expectations? (Choose
two)
In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.
What should the project manager do?
Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.
How should the agile project leader resolve this situation?
A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.
What should the project manager do to address this situation?
A project manager is working on a major construction project. Part of the
agreed-upon plan was to use a cloud-based system with a server that runs on high-speed
internet service since most of the team members work virtually. The company needs to
reduce operating costs as much as possible and management insists that the project will
now use a system running on a conventional dial-up service.
What should the project manager do next?
During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?
A project manager is using a hybrid approach for project delivery. The
development team was sized, but is not yet fully resourced. The project manager is working
on defining the project schedule.
What should the project manager do to address the issue of developer availability?
A project using a hybrid approach to migrate from a current system to a new and
enhanced system is underway. The plan is to migrate the system in stages. However, the
operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.
What else does the project manager need to do before determining the budget baseline?
An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.
What should the project manager do to help move the project forward?
An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings
How should the project manager handle this'?
In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.
Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.
What should the project manager do next?
After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.
What should the project manager do to prevent this frustration going forward?
While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:
Approved Work Package Cost Estimates: US$9,500
Contingency reserves: $500 %
Management reserves: 10% of contingency reserves
Percent complete of the project: 50%
Planned percent of the project: 40%
Actual costs of the project: US$4,500
What is accurate about the project status?
A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings
What should the project manager do?
A project team is conducting a retrospective. The team wants to identify what had
a positive impact on the velocity and keep doing it.
Click on the area that the team should focus on to identify good practices.
A large company has agreed on a business case for an environmental project. The
project will cause some major changes in their operations, such as reduction in paper use,
which will obviously affect all of the users.
What is the first thing the appointed project manager should do?
During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.
What should the project manager do first?
A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.
How should the project manager address this issue?
A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.
What should the team member do?
A project manager prepared the base budget model to deliver a highly
customizable software solution. The solution will be delivered in multiple countries with
significantly different cultures and will be staged over phases.
What should the project manager do next?
A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.
What is the first thing the project manager should do"?
A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?
The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.
What should the project manager do first in this situation?
A company is planning a digitization project. Which action should the project
manager take first when defining the project scope?
A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.
What should the project manager do?
A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member's agile experience with the existing team members.
What should the project manager do to integrate the new team member effectively?
An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.
Which ceremony should be used in developing this register?
A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?
A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?
A labor union contract negotiation is delaying the completion of a project to build
a new manufacturing plant. Because the labor contract was due for renewal this year, the
project manager documented the negotiation process as a risk to the project. The project
was about to start the first phase of equipment installation at the plant when the negotiation began.
How should the project manager address the situation?
A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?
A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?
Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)
A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.
An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance
team is requesting a project budget for the new product.
What should the team do to address this request?
A newly hired team member just joined the project team and reports directly to the
project manager. In the first week, this new member tells the project manager that there is a
task priority conflict with hard, dependent tasks on the critical path.
What should the project manager do to handle the conflict?
A project manager for a building construction project is planning to go on vacation
midway through the project execution phase. What should the project manager do first to
ensure the team is empowered and deadlines are met?
A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.
What strategy should the project manager implement to deal with this situation?
A project manager is working with an agile team. A key stakeholder who does not
join the sprint planning session is very unhappy, as the delivery date for the final product has
been pushed back three times. What should the project manager do?
The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.
What should the project manager have done?
A project is being initiated, and almost every resource available on the project team is a recent university graduate. What should the project manager do to ensure their engagement with the project?
An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.
What should the project manager do to avoid this situation in the future?
Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.
What should the project manager have done earlier to change the product owner's behavior''
In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?
The team architect resigned from the company. The new architect points out a
design flaw during a planning meeting that may potentially impact the final quality.
What should the project manager do first?
After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.
How should the project manager handle this situation?
A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule
Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)
A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation
What should the project manager do?
A stakeholder is requesting that the project manager share project status updates
on a regular basis. This stakeholder is not included in the regular distribution list.
What should the project manager do?
For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.
A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.
How should the project manager communicate the organizational culture and project goal to these stakeholders?
An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.
What should the project manager do?
On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements.
Who is responsible for analyzing the new requirement and making the final decision?
A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.
What is the next step for the project manager?
A project manager recently joined the company. At the interview, the project manager demonstrated experience with agile delivery, and the project management office (PMO) manager asked for assistance in implementing agile.
What should the project manager do to initiate the adoption of agile within the company?
A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.
What should the project manager do to address the growing resistance?
A supplier was supposed to mobilize a government-issued, licensed piece of
equipment two days ago, but did not. The procurement manager was informed that the
supplier failed to check the validity of the license, which expired last week. The supplier had
already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.
Which action should the project manager take?
During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?
A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested
in the product design.
How should the project manager deal with this situation?
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.
What should the project manager do to address the issue?
A team has been working for some time on a project with incremental deliveries. The project manager noticed that one of the team members is less engaged in team meetings, yet delivers promptly. While discussing the source of demotivation, the team member informed the project manager that this is due to a feeling of lack of skills in dealing with new tasks.
How should the project manager address the issue?
A project team member who has the expert knowledge necessary for the project is often absent from meetings. The team member sends a message to the project manager questioning them about the rationale behind some decisions made on the project.
How should the project manager handle the situation?
A project manager is leading a project team that consists of five team members. One of the team members, a senior technical staff member, always criticizes the ideas of other members during team meetings. However, this senior technical member is not performing well on their own daily tasks. Other team members are frustrated and have become silent in meetings.
What should the project manager do?
A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.
What should the project manager do next?
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be
required 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.
What should project manager do?
An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?
A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.
What two things should the project manager do? (Choose two)
A development team is struggling to find design documentation for the upcoming sprint. Prior to leaving for vacation, the product owner
communicated that the documentation had been uploaded to the project file repository.
What should the project manager do to address this issue?
A project manager leads a project that implements a new process throughout the organization. The rollout is done in stages and the project manager planned a demonstration for the pilot business units. A manager from a business unit that is scheduled for a later date asks to be invited to the sprint review.
What should the project manager do?
A company has started developing a new product. During execution the project team notices that another competitor has launched a product with
very similar functionalities and a cheaper market price.
What should have been done differently to avoid this scenario?
A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.
One particular pain point is the transition to operations, where the issues usually arise.
What should the project manager do to improve this scenario?
A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.
What should the project manager do?
A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.
What should the project manager do next?
An organization with a new project management office (PMO) team is now undergoing a restructuring. Additionally, there is a lack of communication from the PMO to the team members.
How should the project manager handle this situation?
A project manager is assigned to a global project with dispersed team members. Previously, when working with remote teams, the project manager observed that team members do not tend to produce quality work.
What should the project manager do to ensure the project is completed on time with quality?
During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.
What should the project manager do?
A project manager has been assigned to lead a project with limited funding and resources. During the requirements brainstorming session, several stakeholders request a long list of requirements for a new project, which exceeds the budget.
What should the project manager do first?
An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.
How can the project manager ensure that the appropriate acceptance criteria are applied to the features?
Anew major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings. Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.
What should the project manager do first?
A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.
Which action should the project manager take to address this situation?
A project team is defining the ground rules during their first meeting as a team. During this session, only a few of the team members suggested and approved the ground rules while most remained silent. As a result, the team's ground rules favor those few team members.
What should the project manager do?
After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.
What should the project manager do?
The key stakeholders of a project would like to be actively involved in the review of product increments.
What should the project manager do?
A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers
arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.
What does the project manager need to do now?
A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?
A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.
What should the project manager do to avoid these situations?
A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.
What should the project manager have done to avoid this issue?
Developers spend most of the sprint writing code for user stories, leaving little time for testing. As a result, user stories cannot be tested in time and the stories remain unfinished by the end of the iteration, resulting in poor metrics.
What should the scrum master do first in this situation?
A project manager is in the process of authoring the communications management plan for a new project. One of the project's stakeholders has a habit of posting work updates on social media, which may include confidential project status updates.
What should the project manager do?
A project team is working on a critical release and the customer wants this feature to be made available as early as possible. The business owner suggests an enhancement during the product demo.
How should the project manager address this request?
A project is starting its second iteration out of six. During the daily meeting, a team member asks for help. In order to finish a deliverable, an
approval from the design department will be needed.
What should the project manager do?
Drag the communication event on the left to the main subject discussed during the event on the right.
A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project
and the customer.
What should the project manager do?
A project manager is leading a project team composed of members with varying levels of knowledge and
experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.
What should the project manager do?
A project team is struggling to meet the project deadline due to a recurring conflict between two team members. What should the project manager do?
Two project team members are updating the schedule but cannot reach an agreement on when two milestones are due. Each team member believes they are correct based on the documents they have available.
What should the project manager do first to finalize the schedule?
A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time.
What should the project manager do?
A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.
What should the project manager do next?
A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the
equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.
What should the project manager have done to prevent this situation from happening?
A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be
engaged in how the project will be executed.
How should the project manager proceed?
A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not
be able to provide assistance for 1 week.
How should the project manager address this situation?
During the lessons learned workshop, one stakeholder mentioned that the project was unsuccessful as it did not deliver the expected business value. What should the
project manager do to address this concern?
A project manager is newly appointed to lead a project team that will be working remotely. The project manager decided to use a set of tools that
worked well for previous projects. However, a few team members are not happy with this plan.
What should the project manager have done to avoid this?
In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.
What should the project manager do?
A flagship project is sponsored by the CEO and has a critical go-live date. The project's product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.
What should the project manager do?
A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government
official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include
aspects that the previous project sponsor did not support.
What should the project manager do next?
A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting all together. What should the project manager do?
Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.
What should the project manager do to obtain approval of the project budget?
A project is in the execution phase and there are disagreements between two key stakeholders about the project's scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.
What should the project manager do?
A large, multinational organization is reevaluating its policy on project management approaches. Team members are complaining about having different processes for each project they are on. Currently, predictive, agile, and hybrid methodologies are being used. A project manager is now part of a team working on standard criteria for approach selection for new projects.
What should the project manager recommend?
A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office
(PMO) recommends the project manager to lead the next similar project.
What should the project manager do next?
During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?
A Scrum team has information radiators but must also keep stakeholders aware of their progress. In addition, the project management office (PMO) has specific templates for status reporting to management. The project lead realizes that a variety of reporting will be needed to satisfy enterprise and stakeholder needs.
What should the project lead do?
The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.
What should the project manager do first?
A project manager assigned to an agile project realizes that after iteration demos, new user stories to fix issues reported by the product owner are not included in prioritization of the following sprint. This has led to a high number of unprioritized stories in the backlog and will lead to delay of the product release.
What should the project manager do?
A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.
What should the project manager do next?
A project team consisting of 13 people was set up three months ago. As part of the transition to agile, a scrum master was assigned to the project. The scrum master wants to know the status of the team's development stage. The project manager believes that the team has passed the "storming" stage.
Which indicators should be used to determine the team's development stage?
A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.
What should be used to prioritize the backlog items?
A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.
What should the new project manager first discuss, review, and clarify during the transition meetings?
During planning, a virtual project team agreed to the project reporting structure and established a meeting cadence that fits multiple time zones. One month into execution, the project manager notices that certain members are disengaged during project meetings.
What should the project manager do to resolve this issue?
A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.
What is the first step the project manager should take?
A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.
What should the project manager do to integrate the diverse stakeholder groups?
A project manager has just been designated to lead an approved project with a virtual team. The team members are from several countries and have never met before.
In order to promote team engagement and introduce the project team, what should the project manager do?
In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.
Which action should the project manager avoid?
The velocity of the team is decreasing at every iteration. The project team members are complaining that the user stories are being rejected by the quality assurance team.
Which three actions should the project manager take? (Choose three)
A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.
Which three actions should the project manager take? (Choose 3)
Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?
A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule, with a heavy contractual penalty. The former project manager had numerous conflicts with the project team members and a few stakeholders.
What should the project manager do first?
A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team
member's deliverables do not meet the requirements.
What should the project manager do first?
A project manager is in the process of closing out a project and has been asked by the project management office (PMO) to confirm that the transfer of knowledge to the operations team for support operations has been successfully completed. Which technique should the project manager apply to verify the knowledge transfer?
A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.
Which estimation technique should the project manager recommend?
A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.
What should the new project manager do next?
During project execution, a key stakeholder approaches the project manager and questions the business value of the project. What should the project manager do?
A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.
Which tool should the project manager use?
A project with a hard timeline is starting its first iteration out of six. The project team is lacking the necessary skills to execute.
What should the project manager do?
A new file vault system vendor is being considered by a protect sponsor who has supported several projects over the previous year What should the project manager review to assist the sponsor on the decision?
An enthusiastic, newly hired vice-president has been assigned as the product owner for a digital transformation project. The project manager
advises the product owner that some of the functional requirements are not aligned with the chief information technology officer's (CTO) strategy.
The product owner tells the project manager that the CTO is not part of the project and should not be engaged at this moment.
What should the project manager do?
A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.
What should the project manager do next?
A project manager agreed to a team member's request to have an alternative working schedule whereby they begin working at 12:00 p.m. each
day. This arrangement has worked well for the project, but has recently been scrutinized by members from other project teams because the
company's core working hours begin at 9:00 a.m.
What should the project manager have done to prevent this situation?
A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?
A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.
What should the project manager have done to avoid this situation?
A project manager in a matrix organization has been assigned to a system solution project with tight time lines. There are two resources assigned as part of the solution
team: one who is experienced and one who is new. During development, the project manager notices that the resources disagree on the solution approach.
What should the project manager do next to deliver a reliable solution?
A project team is performing a post-release evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have promptly provided feedback. One of them has not provided any feedback despite numerous requests from the team.
What should the project manager do in this situation?
A project manager leads a development project for a mobile chatting application. One of the experienced developers constantly creates conflicts
with the other team members. As a result, the other team members are refusing to work with the developer. Since the developer is a high
performer, the project goals may be negatively impacted if they leave the team.
What should the project manager do in this situation?
An information technology project manager works at an insurance company and is assigned to an infrastructure upgrade project. During the execution phase, a stakeholder approaches the project manager and informs them that a deliverable is not meeting the quality requirements.
What should the project manager do first?
A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to
analyze team performance? (Choose two)
A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB).
What should the project manager do now?
A project team has two members with conflicting personalities. This is affecting the rest of the team's performance.
What should the project manager do?
A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.
What should the project lead do?
During a weekly status update meeting with the project management office (PMO), the assigned project manager notices some stakeholders raise concerns about the implementation plan even though the status was regularly communicated to all stakeholders.
What should the project manager do?
Early on during a sprint in an agile project, the project team begins deliberating two different approaches to implement a feature. The project manager is concerned that the team is spending too much time discussing this feature, because the team needs to cover other features in the sprint as well.
How should the project manager approach the situation?
A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.
What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
During a meeting with the customer, it was observed that the features delivered during the last few iterations were not meeting the planned expectations.
What should the project manager do?
A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.
What should the project manager do?
A project manager is leading a project with strict time constraints. In team meetings, one of the team members is always silent. The project manager determines that this team member is not knowledgeable about the technology solution. The project manager is concerned that this problem will impact productivity.
What should the project manager do?
During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?
In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.
What should the project manager do next1?
After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session
What should the project manager do first?
During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.
What should the project manager do next in this situation?
In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict
How should the project manager resolve the problem?
During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics
1,600 rpm (rate-per-minute) -> stops working and crashes the system
1.500 rpm (rate-per-minute) -> warns of max rate allowed
1.400pm (rate-per-minute) -> reduces the power and brakes the engine
Which of the following statements is correct?
A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.
How should the project manager prepare for the next steps of the project?
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.
What should the project manager do?
In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?
A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.
Which two documents should the project manager update as soon as possible? (Choose two)
After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features
What should the project manager do to avoid this in the future?
A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint
What should the project manager have done to avoid this situation?
An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.
What should the project manager do first to ensure team adherence to the ground rules?
The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively
What key activity is needed to ensure the project's success?
In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control
How should the project manager report the project status to key stakeholders?
A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members
What is the cause for this communication gap?
After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch
What should the project manager do to realize benefits?
An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right
A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch
On what should the project manager focus?
A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?
During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level
What should the project manager do next with this opportunity?
Drag the organizational characteristics on the left to the correct scenario on the right
A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase
How should the business increase the value of the project?
A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company
What should the project manager have the Scrum team do to recover from these issues?
A company is changing their current business model The change requires implementing a complex project using multiple agile teams.
What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)
The project manager just started leading a project team from which the previous project manager resigned After a quick evaluation of the project it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule
What should the project manager do?
In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed
Which two actions should the project manager take? (Choose two)
During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version
How can the project manager prevent this outcome in the new project?
A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?
During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of authority during meetings
How should the project manager handle this moving forward?
During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.
What should the project manager pay special attention to in order to achieve this goal?
A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.
Which two actions should the team take to engage this new team member? (Choose two)
A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project
What should the project manager do first to determine a governance approach for the project?
The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>
What should the project manager do?
An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project
Drag the mitigation strategy on the left to the project manager's actions on the right
A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships
Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)
A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?
A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register
What should the project manager do?
From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.
How can the project manager promote empowerment and accountability among the team?
A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline
What two actions should the project manager take'? (Choose two)
Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.
How should the project manager address this situation?
A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?
A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required
How should the project manager assist the product owner?
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points
Which team is performing better?
One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization
How should the project manager acknowledge this team member’s commitment?
A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams
What should the project manager do?
A company's project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company
What should the project manager do first?
The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders
What should the project manager do first?
During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.
What should the project manager do?
A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.
Which activity should be considered as a priority?
The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?
A few months into a project, several schedule issues have emerged Drag the schedule problems on the left to the specific tools on the right that if implemented during schedule development could have prevented the issues.
A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email
What should the project manager do?
An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.
What should the project manager do to resolve this issue?
During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.
What two actions should the project manager take to prevent the team from being unqualified? (Choose two)
During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications
The team is confused by the product owner's statement
What should the project manager do when using a hybrid approach?
After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.
Which technique will help the project manager to accelerate the deliverable?
A project team has recently finished a sprint for developing two features for a fleet management system Although the team delivered the required features, they encountered several issues and conflicts during the sprint. Team members were upset about this experience and are now showing a lack of motivation due to what has occurred.
What can the project manager do to help increase the team's motivation and engagement with the project?
A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project
What should the project manager have the project team update to ensure proper communications to stakeholders?
A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.
What should the project manager have done to avoid this?
A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished
How should the project manager approach this situation?
A project manager has received an updated earned value analysis report The following are the key findings from the report
•Budget at completion = USS1 million
•Earned value = US$0 7 million
•Actual cost = US$0 75 million
•Cost performance index = 0 933
Based on this information, what should the project manager conclude about project performance'?
A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer
What should the project manager do?
During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?
A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time
How should the project manager address this situation?
The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.
What does that project manager need to do to make the team work in a collaborative way?
A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget
What should the project manager do?
A newly formed team has become accustomed to agile practices The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.
What should the project lead do in this situation?
A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project
What should the project manager do?
A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information
What should the project manager do first to resolve this situation?
A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented
What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?
A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.
What training should the project manager choose for their team to help with this situation?
The product team is progressing with a prototyping approach to deliver a multiyear business initiative A few user stones are taking longer to be delivered.
What should the project manager do?
A project manager is appointed for the deployment of a new solution The solution will be integrated into the environment by a third-party vendor This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?
A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right
The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress What should the project lead do?
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)
A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer The SMEs captured various process deviations without sharing with the project team
How can the project manager ensure knowledge transfer across the team?
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.
How should the project manager plan the delivery of the project?
During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team
How should the project manager handle this situation?
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.
What should the project manager do?
During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.
What should the project manager do?
A project just kicked off and management’s expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?
for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.
What should the project manager do next?
During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path
What should the project manager do to avoid future delays?
The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.
What does the project manager need to do first?
A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing
What should the project manager review?