Pre-Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

APMG-International AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Exam Practice Test

Agile Project Management (AgilePM) Practitioner Exam Questions and Answers

Question 1

What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?

Options:

A.

The Project Manager should extend the timescale of Timebox B and shorten Timebox C.

B.

The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List.

C.

The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.

D.

The Project Manager should move a Must Have requirement from Timebox B into Timebox C.

Question 2

What action should the Project Manager take to plan the deployment activities?

Options:

A.

Prepare a Timebox Plan for the next Development Timebox.

B.

Check the Delivery Plan for deployment activities and update as required.

C.

Create a plan of activities to deploy the solution at the end of Timebox C.

D.

Update the Timebox Plan for Timebox C with the activities required to deploy the solution.

Question 3

Which 2 actions should the Workshop Facilitator take when preparing for the workshop?

Options:

A.

Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos.

B.

Invite the Marketing Director to create a summary of the content they believe the system should hold and why.

C.

Assign ownership of the workshop to the Software Developer.

D.

Ask the IT Operations Manager to prepare the agenda for the workshop.

E.

Research other hotel reservation systems to form an opinion on what the content should be.

Question 4

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

When specifying high-level prioritised requirements during Foundations, the Business Visionary has suggested that acceptance criteria for the requirement to " temporarily weatherproof the roof " should NOT be set until Solution Development Timebox A.

Is this an appropriate approach to setting high-level acceptance criteria?

Options:

A.

Yes, because the Local Planning Authority Officer will set the acceptance criteria.

B.

Yes, because acceptance criteria are NOT set before the Timeboxed work is started.

C.

No, because by the end of Foundations the quality expectations and overall acceptance criteria for at least the first increment should have been set, and high-level acceptance criteria set for later increments.

D.

No, because a Review Session should have been scheduled during Feasibility to enable the Solution Development Team to validate their understanding of the Local Planning Authority Officer ' s expectations.

Question 5

Which 2 statements explain why the Architecture Angels ' Chief Accountant would be an appropriate Business Ambassador?

Options:

A.

Has been authorised by the Architecture Angels ' Marketing Director to take decisions on behalf of the business areas.

B.

Has three Accounts Clerks as staff.

C.

Has been with the company for six months so is keen to make an impression.

D.

Understands the financial realities about what can be afforded and what is needed.

E.

Runs a personal refurbishment project in any spare time so will be able to interact with the technical staff.

Question 6

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because this will allow the Solution Development Team to focus on the quality of the Solution Development Timebox ' s deliverable as a whole, in order to keep focus on the business need.

B.

Yes, because it will be easier to set acceptance criteria for the Solution Development Timebox as a whole, rather than setting specific acceptance criteria for each individual requirement.

C.

No, because the acceptance criteria for the Solution Development Timebox are just the amalgamation of the individual requirements ' acceptance criteria, with nothing extra.

D.

No, because the Solution Development Timebox objective will change if any new requirements emerge or any lower priority requirements are de-scoped.

Question 7

The Timebox to deliver the online reservation system through the Hoy Hall website has experienced a major issue. During Timebox C a test was completed to

simulate an attack on the financial element of the online reservation system, with the intention of finding security weaknesses. It was found that it was

potentially possible to gain access to the system, its functionality and data. Further work is therefore needed to meet the information security elements of a

customer financial transaction.

Answer the following question about the actions to be taken by each role.

Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system. Column 2 lists the key roles. For each action in Column 1,

select from Column 2 the role that should carry out the action.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1

    Advise how the legislation on the transfer of data will affect the requirements

and the system.

    Agree the changes needed to the corporate technical architecture with the

Architecture Angels IT support team.

    Ensure the information security vulnerability is communicated to the AA Head

Office IT Director.

    Evaluate the impact of proposed security controls on the business and decide

on the most suitable solution.

    Reprioritise the requirements on the Prioritised Requirements List associated

with the security issue.

Column 2

    Project Manager

    Business Sponsor

    Business Visionary

    Technical Coordinator

    Business Analyst

    Team Leader

    Business Ambassador

    Solution Developer

Options:

Question 8

What action should the Project Manager take regarding the remaining windows?

Options:

A.

All requirements that have not been met are automatically carried over to the next increment.

B.

Extend the time allocated to Timebox C, to allow time to complete these.

C.

Insist that all available resources within the Solution Development Team are redirected to this work over the remaining two days.

D.

Decompose the individual elements of work to be completed on the windows and reprioritise them to meet the Minimum Usable Subset.

Question 9

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

Options:

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels ' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Question 10

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The requirement to ' install a heat reclamation system ' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because only Must Have requirements should be fully understood.

B.

Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.

C.

No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.

D.

No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.

Question 11

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?

Options:

A.

The Feasibility Assessment should contain a detailed description of costs and benefits associated with the refurbishment.

B.

Enough description of the required refurbishment work should be provided to enable the Architecture Angels ' Finance Director to decide whether the project should proceed.

C.

During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.

D.

The Outline Business Case should demonstrate the mitigation of all business risks associated with the refurbishment.

E.

The Outline Business Case should describe the full team structures to be engaged for the later phases of the project.

Question 12

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project

Management when developing the Feasibility Assessment?

Options:

A.

The new Project Manager should NOT be involved in finalising the

Feasibility Assessment.

B.

The Architecture Angels ' Finance Director should approve the final

Business Case as part of the Feasibility Assessment.

C.

The Earth Excavations ' Head Gardener should contribute to the outline

solutions considered for the gardens.

D.

The different options should be presented to the ' Hoy for Hoy Hall ' Action

Group for their feedback before the chosen outline solution is finalised.

E.

The Timber Tigers ' Site Manager should be the sole approver of the

finalised Feasibility Assessment before development commences.

Question 13

If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?

Options:

A.

Present own interpretation of what the system should include.

B.

Present the group with a predefined specification of what should be included.

C.

Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.

D.

Agree to disagree, and close the workshop acknowledging that all participants are entitled to their own view.

E.

Prepare a report describing the outcome of the workshop.

Question 14

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?

Options:

A.

Paper-based drawings are to be used for each option being considered for the building and gardens.

B.

The SAD must include a physically-built miniature model of the Hoy Hall building.

C.

The Architecture Angels ' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution.

D.

The views of the ' Hoy for Hoy Hall ' Action Group members are NOT relevant to the business decision made by Architecture Angels ' Finance Director when approving the final option.

E.

The SAD should contain high-level costs for all elements of each solution option.

Question 15

For cognitive learning, which is the BEST example of providing ' learning feedback ' ?

Options:

A.

Giving supervisor feedback on return to work.

B.

Testing before and after learning.

C.

Reviewing learners’ ideas in a group discussion.

D.

Discussion at the learners ' next annual performance reviews.

Question 16

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Are the measures and source data to be monitored by the Human Resources and Facilities Manager likely to have any of the limitations of data analytics?

Options:

A.

No, because reporting on staff data should only be carried out by Human Resources.

B.

No, because internal processes are likely to ensure a good data quality.

C.

Yes, because the volume of the source data is likely to be unmanageable.

D.

Yes, because the source data is unlikely to provide ‘real-time’ accuracy.

Question 17

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Do the measures to be monitored by the CEO represent appropriate ‘leading’, result-oriented measures for the effectiveness of the change interventions?

Options:

A.

No, because ‘leading’ metrics must be based on quantitative data.

B.

No, because these metrics are lagging, output-focused indicators.

C.

Yes, because these indicators will identify if UniCo sales continue to decline.

D.

Yes, because these metrics monitor benefits realization at senior management level.

Question 18

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Do the measures to be monitored by the Sales Director represent appropriate measures for assessing change readiness?

Options:

A.

No, because change readiness measures should consist of mostly quantitative measures.

B.

No, because change readiness should be monitored using the change programme plan.

C.

Yes, because the Sales Director has identified measures that require new data sources.

D.

Yes, because these metrics provide opinions collected via mostly qualitative methods.

Question 19

Two Sales staff members appear to have lost energy for the change process and did not attend recent change meetings. When questioned, they said they were so overwhelmed by the number of changes in systems, materials, technical knowledge, and processes that they couldn’t deal with any more.

Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance from staff?

Options:

A.

Find out which elements could remain unchanged so that future sales are unaffected.

B.

Add personal staff targets to ensure that the changes in the sales operations are continued.

C.

Assign the staff members to projects outside of this change, to prevent them undermining the changes needed.

D.

Consider limiting the changes to those that are related to each other during each iteration of change in sales.

E.

Ensure these staff members are rewarded for raising issues with the implementation.

Question 20

Which 2 actions demonstrate connectivity?

Options:

A.

Arrange a number of briefing sessions for Customer Services staff, over lunch times and in a comfortable setting.

B.

Make short videos available showing how customer service teams from other companies effectively provide services for these types of offerings.

C.

Create a central area on the UniCo internal shared work system for the Change Programme to collaborate and comment on the materials.

D.

Ask the senior leadership to provide examples of other companies undertaking, and successfully overcoming, similar challenges.

E.

Send the plans of the new office layout to the Selco staff showing them where each individual will be located.

Question 21

Which 2 actions demonstrate transparency?

Options:

A.

Ensure everyone is treated fairly by providing the same information, in the same format, to everyone impacted by this change.

B.

Send daily emails to everyone to remind them how important this change is and why they should support it.

C.

Distribute the key milestones and target dates for including Selco’s mobile technology and approaches into the UniCo operations.

D.

Ask Corporate Services to provide guidelines to ensure all written communications are easy to read and navigate.

E.

Publish how staff members can raise complaints and suggestions, formally and anonymously if needed.

Question 22

Which statement should be recorded under the High-level change approach heading?

Options:

A.

Existing UniCo staff only have skills in providing the installation of large-scale computer systems.

B.

Fast-track training of the Sales staff means taking a member of staff away from the sales operational work.

C.

The senior management will be asked to share examples of other companies undertaking, and successfully overcoming, similar challenges.

D.

All four Change Initiative elements will be required to produce a monthly formal report for the CEO.

Question 23

The Applications Manager agreed to the acquisition by UniCo because they knew that growing Selco needed more investment than they could raise and that they personally didn’t have the skill set to move from technical leader to business leader.

Which preference does this behavior BEST display?

Options:

A.

Extravert.

B.

Introvert.

C.

Thinking.

D.

Feeling.

Question 24

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions.

Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.

The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director ' s leadership team in the UniCo building. At the last Operations ' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.

Is this an appropriate approach to reward the brain in the need for ' status ' , and

why?

Options:

A.

No, because ' status ' should be rewarded by ensuring open, two-way

communication using rich channels.

B.

No, because the Application Manager ' s knowledge and skills are still

relevant and there no threat to ' status ' .

C.

Yes, because highlighting cooperation provides an opportunity for the

Applications Manager to learn and develop.

D.

Yes, because praising people publicly helps to improve a person ' s

informal importance in the organization.

Question 25

Which statement should be recorded under the High-level timing considerations heading?

Options:

A.

The traditional market has changed over the last year and UniCo can no longer rest on its previous success.

B.

UniCo lost significant market share in the last six months and faces ongoing increased competition in the next year.

C.

UniCo’s new finance system was delivered in the last quarter and training in the new system is almost complete.

D.

Completing the large contract with a Utilities company over the next nine months is a vital step to achieving the end vision.

Question 26

The Sales Manager is excited by the challenge to lead a pilot to upskill the sales team in the new capabilities. They will particularly enjoy coaching and spending time with team members.

Which preference does this behavior BEST display?

Options:

A.

Extravert.

B.

Introvert.

C.

Thinking.

D.

Feeling.

Question 27

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Within Sales, which 2 people would be the BEST candidates to use as change agents, based on the descriptions given?

Options:

A.

The Sales Director, who is keen to sell mobile applications to clients and manages the department.

B.

One of the existing long-standing members of the Sales staff, who is good at getting things done across the organization.

C.

One of the existing members of the Sales staff, who is resistant to the change but is diligent and responsible in all tasks.

D.

One of the new members of the Sales staff, who has previous experience selling mobile applications.

E.

The Sales Administrator, who ensures that the sales processes run smoothly and works with all levels of Sales staff.

Question 28

Answer the following questions about applying the principles for building

engagement to the Change Programme, defined by Hodges.

Which 2 actions demonstrate inclusivity?

Options:

A.

Consider providing everyone at the next staff event with pens and notebooks with the UniCo logo and an image representing this change programme.

B.

Define in early key messages how the inclusion of Selco links to the strategic repositioning of UniCo in the marketplace.

C.

Encourage the team from Selco to continue to use their old logo as a way of maintaining some familiar symbolism they can identify with.

D.

Provide opportunities for staff who had volunteered to act as mentors during the Change Programme to meet to resolve resistance issues.

E.

Invite those staff who are asking questions about the Change Programme proposals to suggest what might work for them.

Question 29

The Business Ambassador assigned to the project is only available 2 days a

week. The Project Manager has stated that the Investigation stage for each

Timebox should, where possible, be planned around the availability of the

Business Ambassador.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because this is where any final quality control checks should be

carried out to ensure all products meet the business need.

B.

Yes, because the Investigation stage of a Timebox requires intense

engagement with the Business Ambassador.

C.

No, because it is the Refinement stage of a Timebox that requires intense

engagement with the Business Ambassador.

D.

No, because Timeboxes are only used during Evolutionary Development

and at this point the Business Ambassador is NOT required.

Question 30

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification ' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Question 31

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following question

about assigning the Agile Project Management team roles within this

project.

Lines 1 to 5 in the table below consist of an assertion statement and a

reason statement. For each line identify the appropriate option, from options

A to E. that applies. Each option can be used once, more than once or not

at all.

Options:

Question 32

Which 2 actions should the Technical Coordinator take to implement the new

Must Have requirement?

Options:

A.

Ensure that the latest version of the website design in the Solution

Architecture Definition is provided to all members of the Solution

Development Team.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

D.

Consolidate and circulate an agenda for the workshop.

E.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

Question 33

The Marketing Director has insisted that detailed requirements for the new

coffee bar insurance web pages should be clearly defined in the early phases

of the project.

What action should the Project Manager take?

Options:

A.

Refuse to discuss any detailed requirements in the early phases.

B.

Agree to document the finite details of each requirement to ensure the

web developers can accurately estimate the effort required to fulfil them.

C.

Hold an early discussion to the level of detail necessary to establish a

shared understanding of what is required.

D.

Capture the Marketing Director ' s requirements in detail but leave the

input of others until later in the project.

Question 34

Which 2 statements represent appropriate entries for the Prioritised

Requirements List?

Options:

A.

Creation of a new coffee shop insurance product on the existing website

is expected to increase the insurance company ' s revenues by up to 10%

per week.

B.

All correspondence sent to coffee shop owners by the new system should

contain the XAN logo in the top left hand corner of the page.

C.

Further website developments to allow existing customers to access

services online are NOT to be included within the scope of this project.

D.

The Business Visionary will provide a formal acceptance of the coffee

shop insurance product.

E.

An assessment will be made of the effectiveness of the techniques used

on the project, in line with the principles of Agile Project Management.

Question 35

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Question 36

Time is running short and the Must Have requirements for the data entry screen

of the web page, as recorded in the Prioritised Requirements List, are not going

to be completed on time.

What action should the Project Manager take?

Options:

A.

Change the end date of the Timebox.

B.

Ensure that this issue is escalated to the project level roles.

C.

Amend the end date in the Delivery Plan.

D.

Accept that the Must Have requirements will not be delivered on time.

Question 37

Which 2 statements represent appropriate entries for the Development

Approach Definition?

Options:

A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.

B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.

C.

An easy to use web development tool called ' WebMatrix ' is to be used to

develop and maintain the website extension.

D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.

E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.

Question 38

Which 2 actions should the Project Manager take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

C.

Update the Delivery Plan to show the new financial transaction

functionality as a deliverable.

D.

Source and hire a web developer with experience in developing online

financial transaction functionality.

E.

Consolidate and circulate an agenda for the workshop.

Question 39

The Web Content Manager has provided the Web Developer with a mock up

of the ' Contact Us ' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads ' Delete ' instead of ' Cancel ' .

What action should the Web Content Manager take?

Options:

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Question 40

Answer the following questions about actions to be taken by different

roles.

The Business Sponsor has decided that the new coffee shop insurance

product website pages will include the financial transaction functionality to

support the end-to-end sales process. The Business Sponsor views this as a

valuable sales tool, enabling customers to pay for insurance policies online. If

successful, this new financial transaction functionality is to be made available

across all other insurance products. This is a new Must Have requirement.

All parties are to be invited to a workshop to discuss the additional work

required to deliver the required solution including the new Must Have

requirement. The areas to be discussed include specialist skills required and

possible legal, financial and technical standards to be adhered to.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 actions should the Business Sponsor take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Check the viability of the project, following the inclusion of the new Must

Have requirement.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

E.

Assess the impact of the new Must Have requirement on the original

Business Case.

Question 41

Which 2 actions should the Business Visionary take to implement the new

Must Have requirement?

Options:

A.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Ensure the marketing and sales teams are working together to deliver the

most effective outcome.

E.

Consolidate and circulate an agenda for the workshop.

Question 42

Which 2 statements represent appropriate entries for the plan for Post-Project

activities?

Options:

A.

The Sales Manager will create a company-wide email showing the

number of policies sold weekly by each of the sales assistants.

B.

Before the product is deployed, the Sales Manager will circulate a copy of

the revised sales procedure for processing coffee shop insurance sales.

C.

The Project Manager will attend Daily Stand-up meetings to observe

progress.

D.

A report showing the number of application forms completed online

through the website for coffee shop insurance policies will be produced

weekly.

E.

Once the new system has been deployed, the time it takes to process

sales online will be compared with the time it takes to process new

policies sold through telephone sales.

Question 43

Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(What should the Developers do to ensure their estimates align with AgilePM guidance?)

Options:

A.

Use a relative estimation approach to provide useful early estimates while allowing them to be refined as more information becomes available.

B.

Estimate all identified work in precise hours and days, giving the Delivery Teams the confidence to commit to fixed deadlines before development begins.

C.

Focus estimating on only the high-priority features, leaving lower-priority items, that are less likely to be addressed until later in the Project Increment.

D.

Remind Hira that it is not possible to provide accurate estimates given the influences of VUCA on both the project and the desired Eco-spa solution.

Question 44

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Which 2 of the following actions align with AgilePM practices for defining and estimating the work of Project Increment 4 during the Foundations phase?)

Options:

A.

Conduct a full analysis of Spa treatments to create a fixed guest service specification.

B.

Host a stakeholder workshop to prioritize integrating the Spa into the resort experience.

C.

Develop high-level estimates of effort and cost for Spa facilities and IT systems.

D.

Prepare a risk report on aligning Spa services with guest experience.

E.

Define work items in enough detail for Developers to start design work on treatments.

Question 45

(To keep Business Sponsor, Sarah, informed, Hira has set up a real-time dashboard displaying project progress, risks, and actions from planning events.

Will this meet Sarah ' s needs?)

Options:

A.

Yes, because she will have access to progress updates, removing all meeting dependency.

B.

Yes, because she can rely solely on the dashboard for all her updates.

C.

No, because dashboards lack the context and detail required for strategic decision-making.

D.

No, because she will need Hira to compile and present the data in a physical report for sharing.

Question 46

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

(Which one of the following statements does NOT align with AgilePM ' s MoSCoW prioritization?)

Options:

A.

' Must Have ' requirements are essential to success, without them the solution is unworkable, unsafe, illegal, or pointless.

B.

' Should Have ' requirements are important and must be delivered for the project be deemed successful.

C.

' Could Have ' requirements are valuable and desirable from a business perspective but will only be delivered if time and resources allow.

D.

' Won ' t Have this time ' requirements are explicitly out of scope of the current Solution Increment but should be reconsidered for inclusion later.

Question 47

Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(The Developers have used the Planning Poker technique to generate their estimates. Hira now needs to determine how many Sprints will be required for the Delivery Teams to deliver the Eco-spa.

What should the Developers do to help Hira make this decision?)

Options:

A.

They should use the commitment-based planning technique to estimate how many story points of work can be achieved in a Sprint.

B.

They should convert story points to person days, allowing Hira to establish how many Sprints will be needed based on development capacity.

C.

They should assign average time allocations for each backlog item, making it easy for Hira to ensure that every Sprint has an equal workload.

D.

They should re-estimate using a more appropriate technique because Story Point estimating intentionally avoids associating time with effort.

Question 48

Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.

Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Selling aromatherapy oils to guests was not previously in scope.

Which 2 of the following actions align with AgilePM ' s guidance for handling Mira Bachar ' s suggestion?)

Options:

A.

Hold a workshop to assess feasibility and document assumptions.

B.

Immediately add it to the scope, as it aligns with the project vision.

C.

Use MoSCoW prioritization to determine its importance against existing objectives.

D.

Develop a detailed business case and submit it for Project Board approval.

E.

Defer the decision until after the Eco-spa is delivered to avoid distractions.

Question 49

(Hira is considering splitting the Developers into two Delivery Teams: one focused on Spa infrastructure and the other on guest experience. Mira Bachar, the Guest Services Manager, will be the Product Owner for both teams.

Which one of the following statements support Hira ' s proposed Delivery Team structure?)

Options:

A.

The Guest Experience team can dictate the Infrastructure team priorities, ensuring guest satisfaction.

B.

Each Delivery Team can work independently, delivering valuable increments without needing to coordinate with the other.

C.

Each Delivery Team can refine their own practices without unnecessary distractions from other skill sets.

D.

Collaboration within specialized teams improves communication and commitment to goals.

Question 50

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

(Which one of the following actions will ensure that Product Backlog items for the Hydrotherapy infrastructure remain aligned with the planned treatment experience throughout development?)

Options:

A.

The Infrastructure Team should regularly review and refine Backlog items with Mira Bachar to maintain alignment.

B.

Lock all Backlog items after initial prioritization to prevent scope change and allow the Infrastructure Team to focus on delivering them.

C.

Frequently reassess the priority of Product Backlog items to ensure the Infrastructure Team remain focused on the highest value features.

D.

Encourage the Infrastructure Team to prioritize features for the hydrotherapy treatments since they understand what can be achieved within each Sprint.

Question 51

(New food hygiene laws take effect in six months. Sukra Aroon and Wanida Anong are assessing if kitchen remodeling is needed, which may divert Infrastructure Team resources.)

Options:

A.

Approach-based, because past Project Increment planning failed to account for regulatory change, causing lack of contingency and resource risks.

B.

Approach-based, because Sukra Aroon should have tracked evolving legislation from the start to mitigate the risk.

C.

VUCA-based, because new legislation is an external factor requiring adaptability to respond to unplanned demands.

D.

VUCA-based, because gaps in internal compliance cause uncertainty in responding to changing regulations.

Question 52

During the Foundations phase for Project Increment 4, Sukra Aroon held a meeting with Hira, Mira Bachar, andWanida Anong, to ensure alignment and compliance with EPR company policies, local regulations, and international standards. The meeting also clarified how financial and investment decisions would be made for Project Increment 4, ensuring alignment with EPR business priorities, and how this information will be tracked,

controlled and evidenced.

Wanida Anong, who works across multiple sites worldwide, attended the meeting in person but has limited availability throughout the Project Increment.

(During the meeting, Hira shared concern that the fixed end date for Project Increment 4, aligned with the start of next season, creates a risk as elements of the Eco-spa may not be ready in time. Based on AgilePM guidance, which of the following is an appropriate response to managing this risk?)

Options:

A.

Focus first on completing all compliance-related work to avoid late-stage regulatory issues, deferring guest experience features if necessary.

B.

Use MoSCoW prioritization to ensure that Must Have features are delivered first, while lower-priority features can be deferred or adjusted if time runs out.

C.

Increase Delivery Team capacity by hiring additional temporary resources to ensure all planned features are completed before the deadline.

D.

Extend the Project Increment deadline beyond the start of next season if necessary, ensuring that all planned deliverables meet the original quality expectations.

Question 53

Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(Sukra Aroon has noticed that the Developers are spending excessive time creating their estimates. He has also observed that the document capturing their assumptions behind these estimates is nearly 20 pages long.

Based on his observation, what advice should he offer to the Developers?)

Options:

A.

Ensure that your estimates are accurate enough to support planning but avoid excessive refinement that delays delivery.

B.

Continue refining your estimates as much as possible to eliminate uncertainty, ensuring that all potential risks and complexities are accounted for.

C.

Use broad, high-level estimates only, as attempting to refine estimates beyond this at any stage of the project is unnecessary.

D.

Document every possible assumption in detail, as extensive documentation ensures accuracy and prevents disputes later in the project.

Question 54

(During Sprint Planning, the Delivery Team identifies a potential risk in integrating Spa systems with the resort ' s client management system.

Which 2 statements describe how this risk should be handled within the AgilePM framework?)

Options:

A.

Escalate immediately to Hira who will devise and implement a mitigation plan.

B.

The Delivery Team should address technical challenges collaboratively while keeping project-level roles informed.

C.

Hira should instruct Sukra Aroon to resolve the issue independently to ensure there is no risk to the overall solution.

D.

The Delivery Team should escalate to project level roles and focus on other work until a resolution is found.

E.

Hira should coordinate with Sukra Aroon and Brinda Vyas to align team risk management activities with overall project priorities.

Question 55

(There were several responses to Brinda Vyas ' suggestion of a tranquil garden for guided meditation. While all valid and valuable, which opinion does NOT align with AgilePM responsibilities?)

Options:

A.

Brinda Vyas emphasized the garden ' s strategic importance in enhancing guest experience and meeting business goals.

B.

Brinda Vyas linked the garden to the resort ' s long-term objectives and the project ' s business case.

C.

Sukra Aroon considered technical feasibility and identified risks in infrastructure requirements.

D.

Sukra Aroon dismissed the garden rationale, saying guided meditation could happen in a treatment room.

E.

Mira Bachar prioritized the garden against other deliverables, ensuring alignment with stakeholder needs and project goals.

F.

Mira Bachar clarified the Product Goals for the Delivery Teams to deliver to contribute to the overall solution.

G.

A local expert shared how the garden ' s design could enhance meditation experiences for guest in line with well-being principles.