Pre-Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

Scrum PSPO-I Professional Scrum Product Owner (PSPO I) Exam Exam Practice Test

Demo: 51 questions
Total 173 questions

Professional Scrum Product Owner (PSPO I) Exam Questions and Answers

Question 1

Which statement best describes the Sprint Backlog as the output of the Sprint Planning?

(choose the best answer)

Options:

A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Developers plan for the Sprint.

E.

It is ordered by the Product Owner.

Question 2

What is the timebox for the Sprint Review?

(choose the best answer)

Options:

A.

2 hours for a one-month Sprint.

B.

1 day.

C.

4 hours for a one-month Sprint.

D.

As long as needed.

Question 3

A Scrum Master is working with a Scrum Team that has Developers in different physical

locations. The Developers meet in a variety of meeting rooms and have much to do logistically

(for example: reserve meeting rooms and set up conference calls) before the Daily Scrum.

What action should the Scrum Master take?

(choose the best answer)

Options:

A.

Allow the Developers to self-manage and determine for themselves what to do.

B.

Ask the Developers to alternate who is responsible for meeting setup.

C.

Set up the meeting and tell the Scrum Team that is how it will be done.

D.

Inform management and ask them to solve it.

Question 4

Who is on the Scrum Team?

(choose all that apply)

Options:

A.

Scrum Master.

B.

Product Owner.

C.

Developers.

D.

Project Manager.

E.

None of the above.

Question 5

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

Options:

A.

The Product Owner with input from the Developers.

B.

The Scrum Master.

C.

The Developers, alone.

D.

The Developers after clarifying requirements with the Product Owner.

E.

The most senior people in the organization, including architects and subject matterexperts.

Question 6

Which of the following are the Developers accountable for?

(choose the best two answers)

Options:

A.

Organizing the work required to meet the Sprint Goal.

B.

Selecting the Product Owner.

C.

Reporting productivity.

D.

Creating a plan for the Sprint, the Sprint Backlog.

Question 7

True or False: The Product Owner makes sure the correct stakeholders are invited to the Sprint Retrospective. They might have important instructions for team improvements.

Options:

A.

True

B.

False

Question 8

Which statement best describes the Sprint Review?

(choose the best answer)

Options:

A.

It is a mechanism to control the Developers activities during a Sprint.

B.

It is used to congratulate the Developers if they complete their forecast or to punishthe Developers if they fail to meet their forecast.

C.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint andfigure out what to do next.

D.

It is a demo at the end of the Sprint for everyone in the organization to check on thework done.

Question 9

True or False: A high-performance Scrum Team ensures that each Increment is complete by running a Release Sprint.

Options:

A.

True

B.

False

Question 10

Your management has asked you to take the lead in the development of a new product. Six teams new to Scrum will build this product.

You have gathered a number of requirements and ideas into an early form of a Product Backlog. How would you minimize dependencies between the Scrum Teams?

(choose the best answer)

Options:

A.

You create an independent Product Backlog per Scrum Team.

B.

You divide Product Backlog items among the six Product Owners.

C.

You identify the dependencies and re-order the Product Backlog for the other fiveProduct Owners.

D.

You work with the Developers on how to best analyze and break apart the work.

E.

You raise this as an impediment with the Scrum Master.

Question 11

When should the Product Owner update the project plan?

(choose the best answer)

Options:

A.

Before the Sprint Planning to know how much work will have to be done in the Sprint.

B.

The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.

C.

After the Daily Scrum to ensure an accurate daily overview of project progress.

D.

The project plan must be updated prior to the Sprint Retrospective.

Question 12

What is the Product Owner responsible for during the Sprint Retrospective?

(choose the best answer)

Options:

A.

Summarizing and reporting the discussions to the stakeholders that they represent inthe Scrum Team.

B.

The Product Owner should not take part in Sprint Retrospective.

C.

Participating as a Scrum Team member.

D.

Capturing requirements for the Product Backlog.

Question 13

A product ' s success is measured by:

(choose the best three answers)

Options:

A.

The impact on cost.

B.

The impact on my performance rating.

C.

The impact on revenue.

D.

The impact on my boss ' s mood.

E.

The delivery of upfront defined scope compared to the upfront planned time.

F.

The impact on customer satisfaction.

Question 14

A Product Backlog is:

(choose the best three answers)

Options:

A.

An exhaustive list of upfront approved requirements to be implemented.

B.

Managed by the Product Owner.

C.

An inventory of things to be done for the Product.

D.

Ordered based on priority, value, dependencies, and risk.

E.

Only visible to the Product Owner and stakeholders.

Question 15

What is a Product Owner typically responsible for during a Sprint?

(choose the best two answers)

Options:

A.

Attending every Daily Scrum to answer questions about the Sprint Backlogitems.

B.

Creating financial reporting upon the spent hours reported by the Developers.

C.

Nothing.

D.

Updating the work plan for the Developers on a daily basis.

E.

Collaborating with stakeholders, users, and customers.

F.

Working with the Scrum Team on Product Backlog refinement.

Question 16

Who owns the Sprint Backlog?

(choose the best answer)

Options:

A.

The Scrum Master.

B.

The Scrum Team.

C.

The Product Owner.

D.

The Developers.

Question 17

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the best answer)

Options:

A.

The Product Owner.

B.

The Quality Assurance Team.

C.

The Scrum Team.

D.

The Developers.

E.

The Scrum Master.

Question 18

Which statement best describes a Product Owner ' s responsibility?

(choose the best answer)

Options:

A.

Ensuring that the work meets the commitments to the stakeholders.

B.

Maximizing the value of the work the Scrum Team does.

C.

Keep stakeholders from distracting the Developers.

D.

Directing the Developers.

Question 19

You are the Scrum Master of a new, to be developed Product. Development is going to require

45 people. What is a good first question for you to suggest the group thinks about when forming into teams?

(choose the best answer)

Options:

A.

What is the right mixture of senior and junior people on each team?

B.

Who are the subject matter experts on each team?

C.

Who are going to be the team leads?

D.

How will we make sure all teams have the right amount of expertise?

Question 20

Who can cancel a Sprint?

(choose the best answer)

Options:

A.

The Scrum Team.

B.

The Scrum Master

C.

The Product Owner.

D.

The Stakeholders.

Question 21

A Scrum Team has been working on a product for 9 Sprints. A new Product Owner who is new to Scrum joins the team and understands she is accountable for the Product Backlog. However, she is unsure about the purpose of the Product Backlog. She has read that the Product Backlog

should be a list of all user features for the product. She goes to the Scrum Master asking where to put the other types of requirements that are going to be taken into account. Are all of the following types of requirements acceptable on a Product Backlog?

• Stability requirements

• Performance requirements

• Product Functionality

• Documentation

• Fixes

(choose the best answer)

Options:

A.

Yes, they all belong on the Product Backlog. The Product Backlog is supposed to be the " single source of truth " for all the work for the product.

B.

No. Product Backlog is a tool for the Product Owner. The Product Owner represents the users and stakeholders. Other types of requirements should be managedseparately by the Developers. They are not the Product Owner ' s concern.

Question 22

As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do?

(choose the best answer)

Options:

A.

Find another Scrum Team to give the excess work to.

B.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

C.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

D.

Reduce the Definition of Done and get all of the Product Backlog items done by the new definition.

Question 23

Why does the Product Owner want the Developers to adhere to its Definition of Done?

(choose the best answer)

Options:

A.

To predict the team ' s productivity over time.

B.

To have complete transparency into what has been done at the end of each Sprint.

C.

To know what the team will deliver over the next three Sprints.

D.

To be able to reprimand the team when they do not meet their velocity goal for the Sprint.

Question 24

When is the Sprint Backlog created?

(choose the best answer)

Options:

A.

Prior to Sprint Planning.

B.

During refinement.

C.

During the Sprint Retrospective.

D.

During Sprint Planning.

Question 25

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily

Scrum?

(choose the best two answers)

Options:

A.

An update of completed tasks and of the remaining work so the Scrum Mastercan plan the next day.

B.

An updated Scrum board to make Sprint progress transparent for thestakeholders.

C.

A status report for the upper management indicating what each individual hasdone, will be doing, and what is impeding him/her.

D.

Identification of impediments that may prevent the Developers from achievingthe Sprint Goal.

E.

A shared understanding of the most important work to be undertaken next toachieve the best possible progress toward the Sprint goal.

Question 26

Which of the following practices might help the Product Owner minimize waste in developing

and sustaining the Product Backlog?

(choose the best two answers)

Options:

A.

Avoid distracting the Scrum Team by maintaining newly gathered ProductBacklog items in a separate Product Backlog until they are fully understood.

B.

Hand off ownership of the Product Backlog to someone else.

C.

Remove items from the Product Backlog that have not been addressed in a longtime.

D.

Only fully describe Product Backlog items when it seems likely they will beimplemented.

Question 27

What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning?

(choose the best answer)

Options:

A.

The Product Owner should select the Sprint Goal for the Scrum Team so that work can begin.

B.

The Developers will find it difficult to create a Sprint forecast they are confident they can meet.

C.

Nothing in particular.

D.

The Scrum Master should not allow this to happen. Look for a new Scrum Master and re-start the Sprint.

E.

Sprint Planning is canceled so refinement can be done first.

Question 28

Why is the Daily Scrum held at the same time and same place?

(choose the best answer)

Options:

A.

The Product Owner demands it.

B.

Rooms are hard to book and must be booked in advance.

C.

The place can be named.

D.

The consistency reduces complexity.

Question 29

Who is accountable for tracking the remaining work toward the Sprint Goal?

(choose the best answer)

Options:

A.

The Developers.

B.

The Project Manager.

C.

The Product Owner.

D.

The Scrum Master.

Question 30

How much time must a Product Owner spend with the Developers?

(choose the best answer)

Options:

A.

Enough so that the Product Owner is confident the Increment will meet the intended value.

B.

40%, or more if the stakeholders agree.

C.

As much time as the Developers tell the Product Owner to be present.

D.

100%

Question 31

Which of the following are true about the Product Owner?

(choose the best two answers)

Options:

A.

The Product Owner is one person.

B.

The Scrum Team can have multiple Product Owners.

C.

The Product Owner can be represented by a committee or a team of people.

D.

The Product Owner is accountable for ordering the Product Backlog.

Question 32

How often should Scrum Team membership change?

(choose the best answer)

Options:

A.

Every Sprint to promote shared learning.

B.

As needed, with no special allowance for changes in productivity.

C.

Never, it reduces productivity.

D.

As needed, while taking into account a short-term reduction in productivity.

Question 33

Who has the final decision about the order of items in the Product Backlog?

(choose the best answer)

Options:

A.

The Scrum Master.

B.

The Stakeholders.

C.

The Scrum Team.

D.

The Developers.

E.

The Product Owner.

Question 34

Which two things should the Scrum Team do during the first Sprint?

(choose the best two answers)

Options:

A.

Make up a plan for the rest of the project.

B.

Define the major product features and a release plan architecture.

C.

Analyze, describe, and document the requirements for the subsequent Sprints.

D.

Build at least one piece of valuable functionality.

E.

Create at least one valuable, useful Increment.

Question 35

Who determines how many Product Backlog items the Developers select for a Sprint?

(choose the best answer)

Options:

A.

The Scrum Team

B.

The Developers.

C.

The Product Owner.

D.

The Scrum Master.

E.

The stakeholders attending Sprint Planning.

Question 36

What enhances the transparency of an Increment?

(choose the best answer)

Options:

A.

Keeping track of and estimating all undone work to be completed in a " hardening " Sprint.

B.

Doing all work needed to meet the Definition of Done.

C.

Reporting Sprint progress to the stakeholders daily.

D.

Updating Sprint tasks properly in the electronic tracking tool.

Question 37

What are two effective ways for a Scrum Team to ensure security concerns are satisfied? (choose the best two answers)

Options:

A.

Add security concerns to the Definition of Done.

B.

Delegate the work to the security department.

C.

Have the Scrum Team create Product Backlog items for each concern.

D.

Add a Sprint to specifically resolve all security concerns.

E.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

Question 38

When does the next Sprint begin?

(choose the best answer)

Options:

A.

The Monday following the Sprint Review.

B.

Immediately after the conclusion of the previous Sprint.

C.

Immediately following the next Sprint Planning.

D.

When the Product Owner is ready.

Question 39

What does it mean for a Scrum Team to be cross-functional?

(choose the best answer)

Options:

A.

The Scrum Team includes not only developers but also business analysts, architects,and testers.

B.

The Scrum Team includes skilled individuals who together have all the skillsnecessary to create value each Sprint.

C.

Developers on the Scrum Team work closely with business analysts, architects,developers, and testers who are not on the team.

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts,architects, developers, and testers.

Question 40

Every Scrum Team should have:

(choose the best answer)

Options:

A.

One Lead Developer and no more than 8 other members.

B.

The competencies and skills needed to deliver an Increment in a Sprint.

C.

At least one representative from each major department, such as, Quality Assurance,Development, and Marketing.

Question 41

A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses?

(choose the best two answers)

Options:

A.

Promote transparency by sharing the Product Backlog and ensuring the ProjectManager has access.

B.

Have a discussion with the Project Manager; share the current impediments andforecast for the Sprint.

C.

Show the Earned Value Analysis (EVA) report.

D.

Scrum does not have Project Managers so disregard their concerns.

E.

Share the last stakeholder briefing document prepared by the Product Owner.

Question 42

When does a Developer become accountable for an item in the Sprint Backlog?

(choose the best answer)

Options:

A.

During the Daily Scrum.

B.

As soon as a Developer on the Scrum Team can accommodate more work.

C.

Never. All Developers on the Scrum Team share accountability for items in the SprintBacklog.

D.

At Sprint Planning when all of the Sprint Backlog items are split evenly across theDevelopers.

Question 43

Why do the Developers need a Sprint Goal?

(choose the best answer)

Options:

A.

A Sprint Goal only gives purpose to Sprint O.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

The Developers are more focused with a common yet specific goal.

D.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

Question 44

In accordance with Scrum theory, how should a group of 100 people be divided into multiple

Scrum Teams?

(choose the best answer)

Options:

A.

Create a matrix of skills, seniority, and level of experience to assign people to teams.

B.

Check with the allocation department to see who has worked together before and make these the first teams.

C.

Understanding the product, the product vision and the rules of the Scrum framework, the people divide themselves into teams.

D.

It does not really matter since you can rotate the teams every Sprint to spread knowledge.

Question 45

True or False: When there are multiple teams working on one product, each Scrum Team should have a separate Product Owner.

Options:

A.

True

B.

False

Question 46

In the middle of the Sprint, the customer decides that there are two new features she wants.

The Product Owner could:

(choose the best two answers)

Options:

A.

Introduce these features at the next Daily Scrum.

B.

Ask the Developers to consider whether they can add these features to thecurrent Sprint without endangering the Sprint Goal.

C.

Add these features to the Product Backlog.

D.

Have the Scrum Master add these features to the current Sprint.

Question 47

What three things might a Scrum Product Owner focus on to ensure the product delivers value?

(choose the best three answers)

Options:

A.

How much of the functionality of the product is being used.

B.

Direct customer feedback.

C.

How quickly or easily the product can be absorbed and used by its customers.

D.

Velocity is increasing over time.

E.

Minimizing changes to project scope.

Question 48

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario.

(choose the best two answers)

Options:

A.

Each Scrum Team should have a separate Product Backlog.

B.

There should be only one Product Owner.

C.

The product has one Product Backlog.

D.

There should be six Product Owners, one for each Scrum Team.

E.

There should be six Product Owners, reporting to a Chief Product Owner.

Question 49

Who is accountable for creating a valuable and usable Increment each Sprint?

(choose the best answer)

Options:

A.

The Scrum Master.

B.

The CEO.

C.

The Developers.

D.

The Scrum Team.

E.

The Product Owner.

Question 50

What happens if the Scrum Team cannot complete its work by the end of the Sprint?

(choose the best answer)

Options:

A.

The Sprint length is unchanged and the Scrum Team continuously learns and adapts.

B.

The Sprint is extended and future Sprints use this new duration.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it does not happenagain.

Question 51

The Scrum Master observes the Product Owner struggling with ordering the Product Backlog.

What is an appropriate action for the Scrum Master to take?

(choose the best answer)

Options:

A.

Offer the Product Owner help in understanding that the goal of ordering the ProductBacklog is to maximize value.

B.

Suggest that the Developers order the Product Backlog to be sure that it is a feasibleordering of work.

C.

Encourage the Product Owner to work with the Developers to see which itemstechnically are fastest to implement.

D.

Suggest the Product Owner extend the Sprint, so he can have more time to order theProduct Backlog.

E.

Present the Product Owner with an ordered Product Backlog to use.

Demo: 51 questions
Total 173 questions