Pre-Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

Scrum PSM-I Professional Scrum Master I Exam Practice Test

Demo: 87 questions
Total 298 questions

Professional Scrum Master I Questions and Answers

Question 1

A Scrum Master is essentially the same thing as a traditional PM (Project Manager).

Options:

A.

True

B.

False

Question 2

What is the time-box for the Sprint Review?

Options:

A.

As long as needed.

B.

2 hours for a monthly Sprint.

C.

4 hours for a monthly Sprint.

D.

4 hours and longer as needed.

E.

1 day

Question 3

When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint '

(choose the best answer)

Options:

A.

Never The entire Scrum Team is accountable for creating value every Sprint.

B.

At the Sprint Planning Evented

C.

Whenever a team member can accommodate more worn.

D.

During the Daily scrum

Question 4

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

Options:

A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.

C.

No, each Scrum Team stands alone.

D.

No, that is far too hard and must be done in a hardening Sprint.

Question 5

In order to achieve the benefits of Scrum, it is important to enact the value of commitment. What two actions demonstrate the commitment of Scrum Team members? (Choose two.)

Options:

A.

Always deliver the items in the Sprint forecast.

B.

Help the other Scrum Team members.

C.

Do your best

D.

Send out a daily status report.

E.

Work late.

Question 6

(When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

Choose the best answer.)

Options:

A.

When multiple Scrum Teams are working together on a product, they must mutually define and comply with the same Definition of Done.

B.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

C.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

D.

The Scrum Masters from each Scrum Team define a common Definition of Done.

Question 7

(Why do the Developers need a Sprint Goal?

Choose the best answer.)

Options:

A.

A Sprint Goal only gives purpose to Sprint 0.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

D.

The Developers are more focused with a common yet specific goal.

Question 8

Which approach is best for Scrum Teams in order to produce valuable Increments? (Choose the best answer.)

Options:

A.

Each Developer works on the component where they feel that they can contribute.

B.

Each Scrum Team is accountable for developing functionality from beginning to end.

C.

Each Scrum Team works on an independent set of components.

D.

Each Scrum Member works only as an independent layer of the system.

Question 9

What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)

Options:

A.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

B.

Add security concerns to the definition of “Done”.

C.

Add a Sprint to specifically resolve all security concerns.

D.

Delegate the work to the concerned department.

E.

Have the Scrum Team create Product Backlog items for each concern.

Question 10

What is the function or purpose of management in Scrum?

(choose the best answer)

Options:

A.

To identify and remove people that are not working hard enough.

B.

To present the Scrum Teams with insights and resources that help them improve.

C.

To monitor the productivity of the Developers.

D.

To continually monitor staffing levels of the Scrum Team.

Question 11

What are two effective ways for the Scrum Team to make non-functional requirements visible?

(choose the best two answers)

Options:

A.

Run the integration and regression tests before the end of the Sprint, and

capture the open work for the Sprint Backlog of the next Sprint.

B.

Put them on a separate list on the Scrum board, available for all to see.

C.

Add them to the Definition of Done so the work is taken care of every Sprint.

D.

Add them to the Product Backlog to ensure transparency.

Question 12

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

Options:

A.

Recruit additional Developers before the work can begim

B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.

C.

The Developers work overtime during this Sprint

D.

Cancel the Sprint

E.

Remove or change selected Product Backlog items.

Question 13

(Which of the following are the Developers accountable for?

Choose the best two answers.)

Options:

A.

Reporting productivity.

B.

Organizing the work required to meet the Sprint Goal.

C.

Creating a plan for the Sprint, the Sprint Backlog.

D.

Selecting the Product Owner.

Question 14

During the Sprint. Me Scrum Master ' s role is to do which two of the following: (choose the best two answers)

Options:

A.

Facilitate inspection and adaptation opportunities as requested or needed

B.

Coaching the team members in self-management

C.

Ensure the Product Owner attends all scrum events.

D.

Escalate team conflicts to functional line managers

E.

Monitor the progress of the Developers

F.

Assign tasks with the Scrum team.

Question 15

For which of the following is the Scrum Master responsible?

(choose the best answer)

Options:

A.

Properly adopting and using the Scrum framework.

B.

Keeping track of resource allocation.

C.

Managing the performance of the Scrum Team.

D.

The meetings and the objectives that a Scrum Team sets for itself.

Question 16

Who is accountable for tracking the remaining work toward the Sprint Goal? (Choose the best answer.)

Options:

A.

The Developers.

B.

The Scrum Master.

C.

The Product Owner.

D.

The Project Manager.

Question 17

What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement

about which agile practices to apply? (Choose the best two answers.)

Options:

A.

Involve the complete Scrum Team in making a decision.

B.

Use coaching techniques; such as open QUESTION NO:s and active listening.

C.

Ask an external agile coach what they recommend.

D.

Ask team members to take the issue up with to the company’s Human Resources department.

Question 18

How often should Scrum Team membership change?

Options:

A.

As needed, while taking into account a short term reduction in productivity.

B.

Never, because it reduces productivity.

C.

As needed, with no special allowance for changes in productivity.

D.

Every Sprint to promote shared learning.

Question 19

A Scrum Master is introducing Scrum to a new Development Team. The Development Team gas decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?

Options:

A.

Call a meeting between the Development Team and senior management.

B.

Comply with the decision of the self-organizing team.

C.

Consult with the Product Owner to see how he/she feels about the situation.

D.

Begin facilitating productive and useful Sprint Retrospectives.

Question 20

Why does a Development Team need a Sprint Goal?

Options:

A.

A Sprint Goal only gives purpose to Sprint 0.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

The Development Team is more focused with a common yet specific goal.

D.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

Question 21

What are three ways Scrum promotes self-management?

Options:

A.

By having the Scrum Master protect the Scrum Team.

B.

By the Scrum Team deciding what work to do in a Sprint.

C.

By being a lightweight framework.

D.

By removing titles for Scrum Team members.

Question 22

When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

(choose the best answer)

Options:

A.

The Scrum Masters from each Scrum Team define a common Definition of Done.

B.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

C.

When multiple Scrum Teams are working together on a product, they must mutually

define and comply with the same Definition of Done.

D.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

Question 23

Which two things should the Development Team do during the first Sprint? (Choose two.)

Options:

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Define the major product features and release plan architecture

E.

Create an increment of potentially releasable software.

Question 24

What is the function or purpose of management in Scrum?

(choose the best answer)

Options:

A.

To identify and remove people that are not working hard enough.

B.

To monitor the productivity of the Developers.

C.

To present the Scrum Teams with insights and resources that help them improve.

D.

To continually monitor staffing levels of the Scrum Team.

Question 25

Which statement best describes the Sprint Review?

Options:

A.

It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.

B.

It is a demo at the end of the Sprint for everyone in the organization to check on the work done.

C.

It is a mechanism to control the Development Team’s activities during a Sprint.

D.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.

Question 26

True or False A high-performance scrum Team ensures that each increment is complete by running a Release Sprint.

Options:

A.

True

B.

False

Question 27

(True or False: Cross-functional teams are optimized to work on one component or layer of a system only.)

Options:

A.

True

B.

False

Question 28

Which outcome is expected as Scrum Teams mature?

Options:

A.

They will improve their definition of “Done” to include more stringent criteria.

B.

The Sprint Retrospectives will grow to be longer than 4 hours.

C.

There is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.

D.

Sprint Reviews will no longer be needed.

E.

A Scrum Master is no longer needed since they are a mature team now.

Question 29

You have six teams using a traditional method to deliver a product. Your management has asked you to start using Scrum. In the initial project there were separate plans and teams for the layers of a software system, i.e. one for the front-end, one for the middle tier, one for the back-end, and one for the interfaces and services. This resembles what is known as component teams. But you have read that it’s a good idea to have teams organized by feature.

What are the advantages of keeping component teams while starting Scrum?

Options:

A.

There’s less initial disruption than organizing into new teams. As they start, they will discover what works best, and how to potentially re-organize towards this.

B.

Component teams generally have the skills needed to create a working Increment of software that provides business value.

C.

Because they have worked together for some time, they are likely able to start producing shippable Increments faster that new feature teams would.

D.

There are fewer cross-team dependencies than working in feature teams.

Question 30

(What is the Product Owner responsible for during the Sprint Retrospective?

Choose the best answer.)

Options:

A.

Summarizing and reporting the discussions to the stakeholders that they represent in the Scrum Team.

B.

The Product Owner should not take part in Sprint Retrospective.

C.

Participating as a Scrum Team member.

D.

Capturing requirements for the Product Backlog.

Question 31

When a Development Team determines that it will not be able to finish the complete forecast, who has to be

present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

Options:

A.

The Development Team.

B.

The Product Owner and all stakeholders.

C.

The Product Owner and the Development Team.

D.

The Scrum Master, project manager and Development Team.

Question 32

When is a Sprint over?

Options:

A.

When the Product Owner says it is done.

B.

When all Product Backlog items meet their definition of “Done”.

C.

When all the tasks are completed.

D.

When the time-box expires.

Question 33

Which three purposes does the definition of “Done” serve? (Choose three.)

Options:

A.

Guide the Development Team on how many Product Backlog items to select for the Sprint.

B.

Create a shared understanding of when work is complete.

C.

Describe the purpose, objecti ve, and time-box of each Scrum event.

D.

Describe the work that must be done before the Sprint is allowed to end.

E.

Increase transparency.

Question 34

The Product Backlog is ordered by:

Options:

A.

The Product Owner with the most valuable items placed at the top.

B.

Risk, where safer items are at the top, and riskier items are at the bottom.

C.

Items are randomly arranged.

D.

Size, where small items ale at the top and large items are at the bottom.

Question 35

When is implementation of a Product Backlog item considered complete?

Options:

A.

At the end of the Sprint.

B.

When the item has no work remaining in order to be potentially released.

C.

When QA reports that the item passes all acceptance criteria.

D.

When all work in the Sprint Backlog related to the item is finished.

Question 36

What is the time-box for the Sprint Planning meeting?

Options:

A.

4 Hours for a monthly Sprint.

B.

8 Hours for a monthly Sprint.

C.

Monthly.

D.

Whenever it is done.

Question 37

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Options:

A.

The Sprint Backlog.

B.

The Sprint Goal

C.

The release plan.

D.

Sprint Review minutes.

Question 38

When many Scrum Teams are working on a single product, what best describes the Definition of Done?

(Choose the best answer.)

Options:

A.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a

hardening Sprint.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

D.

All Scrum Teams must have a Definition of Done that makes their combined work potentially releasable.

Question 39

What two techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which development techniques to apply? (Choose two.)

Options:

A.

Involve the complete Development Team.

B.

Use coaching techniques; such as open questions and active listening.

C.

Ask an external technical specialist to make the decision.

D.

Send every team member to the company’s HR department to express their concerns.

Question 40

What is the recommended size for a Scrum Team? (Choose the best answer.)

Options:

A.

At least 7.

B.

9

C.

10 or fewer.

D.

7 plus or minus 3.

Question 41

What does it mean to say that an event has a time-box?

Options:

A.

The event must happen at a set time.

B.

The event must happen by a given time.

C.

The event must take at least a minimum amount of time.

D.

The event can take no more than a maximum amount of time.

Question 42

When do Development Team members take ownership of a Sprint Backlog item?

Options:

A.

At the Sprint planning meeting.

B.

During the Daily Scrum.

C.

Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each one may be done by an individual Development Team member.

D.

Whenever a team member can accommodate more work.

Question 43

When is it most appropriate for a Scrum Team to change the definition of “Done”?

Options:

A.

During Spring Planning.

B.

Prior to starting a new Sprint.

C.

During the Sprint Retrospective.

D.

Prior to starting a new project.

Question 44

What happens if the Development Team cannot complete its work by the end of the Sprint?

Options:

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.

Question 45

Every Scrum Team must have a Product Owner and Scrum Master. (Choose the best answer.)

Options:

A.

True. Outcomes affected by their participation and availability.

B.

False. A Product Owner can be replaced by a subject matter expert in the Scrum Team.

C.

False. A Scrum Master is only required when asked for by the Scrum Team.

D.

True. Each must be 100% dedicated to the Scrum Team.

Question 46

What is included in the Sprint Backlog?

Options:

A.

User Stories.

B.

Tasks.

C.

Use Cases.

D.

Tests.

E.

Any of the above (or others) which are a decomposition of the selected Product Backlog items.

Question 47

Which best describes the Product Backlog?

Options:

A.

It is allowed to grow and change as more is learned about the product and its customers.

B.

It provides just enough information to enable a Scrum team to start the design phase of a product.

C.

It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.

D.

It is baselined to follow change management processes.

Question 48

Developers are self-managing, which of the following do they manage? (choose the best answer)

Options:

A.

When lo release, based on this progress.

B.

Stakeholders for the Sprint Review

C.

Sprint Backlog.

D.

Sprint length

E.

Product Backlog ordering

Question 49

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

Options:

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

Question 50

(Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder has just started using the product. The stakeholder is unhappy with the quality of the product, and the Product Owner agrees with the stakeholder’s assessment that the quality is low. How should the Scrum Master respond to the Product Owner?

Choose the best two answers.)

Options:

A.

Explain to the Product Owner that it is up to the Developers to decide on acceptable quality standards.

B.

Encourage the Product Owner to include quality specifications in the Product Backlog and to communicate the stakeholders ' concerns to the Developers.

C.

Work with the Product Owner to understand their desired resolution and help formulate an approach for raising the concern with the Developers.

D.

Bring the concern to the testers to improve how the product is verified.

E.

Tell the Product Owner they have noted the concern and will raise this issue at the Sprint Retrospective.

Question 51

True or False: An increment must be released to customers or users at the end of each sprint.

Options:

A.

True

B.

False

Question 52

At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of “Done”. What two things should happen with the undone Product Backlog item? (Choose two.)

Options:

A.

If the stakeholders agree, the Product Owner can accept it and release it to the users.

B.

Put it on the Product Backlog for the Product Owner to decide what to do with it.

C.

Review the item, add the “Done” part of the estimate to the velocity and create a Story for the remaining work.

D.

Do not include the item in the Increment this Sprint.

Question 53

Who has the final decision about the order of items in the Product Backlog? (Choose the best answer.)

Options:

A.

The Stakeholders.

B.

The Product Owner.

C.

The Scrum Team.

D.

The Scrum Master.

E.

The Developers.

Question 54

When might a Sprint be abnormally cancelled?

Options:

A.

When the Development Team feels that the work is too hard.

B.

When the Sprint Goal becomes obsolete.

C.

When the sales department has an important new opportunity.

D.

When it becomes clear that not everything will be finished by the end of the Sprint.

Question 55

The IT manager asks a Development Team for a status report describing the progress throughout the Sprint.

The Development Team asks the Scrum Master for advice. The Scrum Master should:

(Choose the best answer.)

Options:

A.

Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

B.

Tell the Development Team to figure it out themselves.

C.

Tell the Development Team to fit the report into the Sprint Backlog.

D.

Create and deliver the report to the manager herself.

E.

Ask the Product Owner to send the manager the report.

Question 56

What enhances the transparency of an increment?

Options:

A.

Doing all work needed to meet the definition of “Done”

B.

Reporting Sprint progress to the stakeholders daily

C.

Keeping track of and estimating all undone work to be completed in a separate Sprint.

D.

Updating Sprint tasks properly in the electronic tracking tool.

Question 57

For which is the Scrum Master responsible?

Options:

A.

Managing the performance of the Scrum Team.

B.

The meetings and the objectives that a Scrum Team sets for itself.

C.

The Scrum framework being adopted and used properly.

D.

Keeping track of resource allocation.

Question 58

When must a scrum Team release each increment? (choose the best answer)

Options:

A.

when the Scrum Team finishes their work

B.

Alter every Sprint. without exception

C.

Whenever the product s tree of detects

D.

When it makes sense to release It.

Question 59

When must a Product Owner release each Increment? (Choose the best answer.)

Options:

A.

When it makes sense.

B.

When the Scrum Team finishes their work.

C.

Whenever the product is free of defects.

D.

After every Sprint, Without exception.

Question 60

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

Options:

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Development Team’s ability to deliver.

D.

Its Definition of “Done”.

E.

All of the above.

Question 61

What does n mean tor a scrum Team to be cross-function at? (choose the best answer)

Options:

A.

The Scrum Team includes skilled individuals who together have all the skins necessary to create value each sprint

B.

Developers on the Scrum Team work closely with business analysis architects developers, and testers who are not on the team

C.

The Scrum Team includes not only developers but also business analysts, architects, and testers

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers, and testers

Question 62

Who determines how work is performed during the Sprint?

Options:

A.

Architects.

B.

The Development Team.

C.

The Scrum Master.

D.

Subject matter experts.

E.

Development Team managers.

Question 63

What are three benefits of self-organization? (Choose three.)

Options:

A.

Increased creativity.

B.

Increased rule compliance.

C.

Increased accuracy of estimates.

D.

Increased self-accountability

E.

Increased commitment.

Question 64

True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.

Options:

A.

True

B.

False

Question 65

(Which of the following might the Scrum Team discuss during a Sprint Retrospective?

Choose the best answer.)

Options:

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Developers’ ability to deliver.

D.

The Definition of Done.

E.

All of the above.

Question 66

Which technique is the best way the Scrum Master can ensure that the Development Team communicates effectively with the Product Owner?

Options:

A.

Monitor communications between them and facilitate direct collaboration.

B.

Teach the Development Team to talk in terms of business needs and objectives.

C.

Teach the Product Owner about the technologies employed during the Sprints.

D.

Act as a go-between for them.

Question 67

Who creates a Product Backlog Item’s estimate?

Options:

A.

The Development Team after clarifying requirements with the Product Owner.

B.

The Product Owner with input from the Development Team.

C.

The most senior people in the organization, including architects and subject matter experts.

D.

The Scrum Master.

E.

The Development Team, alone.

Question 68

Scrum has a role called “Project Manager”.

Options:

A.

True

B.

False

Question 69

You are the Scrum Master of a new, to be developed product. Development is going to require 45 people. What is a good first question for you to suggest the group thinks about when forming into teams?

Options:

A.

How will we make sure all teams have the right amount or expertise?

B.

What is the right mixture of senior and junior people on each team?

C.

Who are going to be the team leads?

D.

Who are the subject matter experts on each team?

Question 70

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

Options:

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update the Sprint burndown chart.

D.

Answer questions from the Development Team about items in the current Sprint.

E.

Work with the stakeholders.

Question 71

(The Developers ask their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a component. Without that component, there will not be enough work in the next Sprint to occupy the full team. As the Scrum Master, what advice would you give the Product Owner?

Choose the best answer.)

Options:

A.

Remind the Product Owner that their primary concern is the flow of value reflected in the ordering of the Product Backlog.

B.

Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate Sprint.

C.

Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Developers.

Question 72

Which are properties of the Daily Scrum? (Choose two.)

Options:

A.

It is facilitated by the team lead.

B.

It is held first thing in the morning.

C.

It is fifteen minutes or less in duration.

D.

It is free from and designed to promote conversation.

E.

It consists of the Scrum Master asking the Team members the three questions.

F.

Its location and time remain constant.

Question 73

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (Choose two.)

Options:

A.

A shared understanding of the most important work to be undertaken next to achieve the best possible progress toward the Sprint goal.

B.

An update of completed tasks and of the remaining work so the Scrum Master can plan the next day.

C.

A status report for the upper management indicating what each individual has done, will be doing, and what is impending him/her.

D.

An updated Scrum board to make Sprint progress transparent for the stakeholders.

E.

New impediments for the Scrum Master to take care of.

Question 74

Who should make sure everyone on the Development Team does their tasks for the Sprint?

Options:

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Development Team.

E.

All of the above.

Question 75

Which does a self-organizing Development Team choose?

Options:

A.

Sprint length.

B.

How to best accomplish its work.

C.

Stakeholders for the Sprint Review.

D.

When to release, based on its progress.

E.

Product Backlog ordering.

Question 76

How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning?

(choose the best answer)

Options:

A.

All development work and at least some testing.

B.

as much as is required to meet the Scrum Team ' s Definition of Done.

C.

A proportional amount of time on analysis, design development and testing

D.

As much as they can fit into the Sprint, with remaining work deferred to the next Sprint

Question 77

The Product Owner must release each Increment to production.

Options:

A.

When it makes sense.

B.

To make sure the Development Team is done every Sprint.

C.

Whenever the product is free of defects.

D.

Without exception.

Question 78

Who creates the Definition of Done?

(choose the best answer)

Options:

A.

The Scrum Master

B.

The Product Owner

C.

The scrum Team

D.

The Developers

Question 79

Which two ways of creating Scrum Teams are consistent with Scrum ' s values?

(choose the best two answers)

Options:

A.

Bring all the people together and let them organize into Scrum Teams

B.

Managers personally re-assign current subordinates to new teams.

C.

Existing teams propose how they would like to go about organizing into the new

structure.

D.

Managers collaborate to assign individuals to specific teams.

E.

The Chief Product Owner determines the new team structures and assignments.

Question 80

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum?

(choose the best two answers)

Options:

A.

Identification of impediments that may prevent the Developers from achieving the Sprint Goal.

B.

An update of completed tasks and of the remaining work so the Scrum Master

can plan the next day.

C.

An updated Scrum board to make Sprint progress transparent for the

stakeholders.

D.

A shared understanding of the most important work to be undertaken next to

achieve the best possible progress toward the Sprint goal.

E.

A status report for the upper management indicating what each individual has done, will be doing, and what is impeding him/her.

Question 81

User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What should the Scrum Team do?

(choose the best answer)

Options:

A.

Let the user documentation remain undone and accumulate until after the last development Sprint. It will then be done by any available technical writers.

B.

The Developers on the Scrum Team should write the user documentation.

C.

Wait until you have a technical writer on your Scrum Team to take care of this.

D.

Form a separate team of technical writers that will work on an on-demand basis for the various Product Owners. Work order will be first in, first out.

Question 82

Which of the following are true about the length of the Sprint? (Choose two.)

Options:

A.

The length of the Sprint should be proportional to the work that is done in between Sprints.

B.

It is best to have Sprints of consistent length throughout a development effort.

C.

Sprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing.

D.

Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint.

E.

All Sprints must be 1 month or less.

Question 83

Who must attend the Daily Scrum?

Options:

A.

The Scrum Master and Product Owner.

B.

The Development Team.

C.

The Development Team and Product Owner.

D.

The Scrum Team.

E.

The Development Team and Scrum Master.

Question 84

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the Best answer)

Options:

A.

The Quality Assurance Team

B.

The Scrum Team

C.

The Product Owner

D.

The Scrum Master

E.

The Developers

Question 85

Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)

Options:

A.

Release Planning.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Question 86

Which of the following is required by Scrum? (Choose all that apply.)

Options:

A.

Sprint Retrospective.

B.

Members must be stand up at the Daily Scrum.

C.

Sprint Burndown Chart.

D.

Release planning.

E.

All of the above.

Question 87

True or False A scrum Master fulfills the same role as a traditional Project Manager

Options:

A.

True

B.

False

Demo: 87 questions
Total 298 questions