Weekend Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

SAP C_TS422_2022 SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Exam Practice Test

Demo: 24 questions
Total 80 questions

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Question 1

If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?

Options:

A.

Fill up to the maximum stock level.

B.

Fill up to the safety stock level.

C.

Fill up based on the lot size procedure.

D.

Fill up to the reorder stock level.

Question 2

What does a line hierarchy in repetitive manufacturing represent?

Options:

A.

A production line with more than one work center

B.

A production line with prioritized work centers

C.

A production line with a parallel sequence in the routing

D.

A production line with an alternative sequence in the routing

Question 3

which actions does the system perform by default when you save a confirmation for a finished

product in repetitive manufacturing?

Note: There are 3 Correct answers to this question.

Options:

A.

Posting of production costs to the production cost collector

B.

posting of goods receipt for the product

C.

Reduction of associated capacity requirements

D.

Archiving of document for assembly scrap

E.

Material staging for next order in sequence

Question 4

Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?

Note: There are 2 correct answers to this question

Options:

A.

Total replenishment lead time

B.

Operation duration

C.

Planned delivery time

D.

In-house production time

Question 5

For production orders, cost object controlling (COC) can be carried out on an order-related or product- related basis. Which of the following do you have to consider?

Note: There are 2 correct answers to this question.

Options:

A.

In pro duct-related COC, all costs are debited and credited to a product cost collector.

B.

Order-related COC is beneficial in a flexible production environment

C.

Product-related COC is used in manufacturing for co-products

D.

In order-related COC, individual production orders do NOT have cost segments.

Question 6

Advanced Planning uses master data and transaction data from SAP S/4HANA In which data objects can you set the Advanced Planning flag?

Note: There are 2 correct answers to this question.

Options:

A.

Work Center

B.

Production Version

C.

Material

D.

plant

Question 7

What are some benefits of planning with planned independent requirements? Note: There are 2 correct answers to this question.

Options:

A.

Reduced production times

B.

Reduced delivery times

C.

Option to use make-to-order production

D.

Option to forecast planning for production resources

Question 8

What is the work center hierarchy in capacity planning?

Options:

A.

A group of work center in a parallel sequence that is used to split production quantities and work on them in parallel

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of alternative work centers for production, structured in hierarchy levels by priorities

Question 9

You are trying to create a production order and NO valid production version can be selected. What could be the reasons?

Note: There are 2 correct answers to this question.

Options:

A.

NO bills of material (BOMs) are assigned to the production versions.

B.

All production versions for the material are locked.

C.

The order lot size is NOT within the validity range of a production version.

D.

NO production lines are assigned to the production versions..

Question 10

Which business processes are affected by settings in the order-type-dependent parameters?

Note: There are 2 correct answers to this question.

Options:

A.

Check material availability.

B.

Schedule production orders.

C.

Define integration with cost accounting.

D.

Select master data.

Question 11

You need to model goods receipt processing time in detailed scheduling. Which modeling options do you have?

Note: There are 3 correct answers to this question.

Options:

A.

Model a separate resource in the production data structure.

B.

Model a handling resource in the location master.

C.

Model a transportation lane and carrier selection in the location master.

D.

Model a separate inbound resource in the location master.

E.

Model a goods receipt time in the material master.

Question 12

What does the material type influence?

Note: There are 2 correct answers to this question.

Options:

A.

Which document types and class categories are allowed

B.

Which material master screens appear and in which sequence

C.

Whether the material is produced in-house, procured externally, or both

D.

Which plant-specific and plant-independent statuses are allowed

Question 13

Which information is required when you create a product master in SAP S/4HANA?

Note: There are 2 correct answers to this question.

Options:

A.

Product type

B.

Selection screen for views

C.

Selection screen for plants

D.

Base unit of measure

Question 14

What does forecasting in the demand planning cycle include?

Note: There are 3 correct answers to this question

Options:

A.

One-off events

B.

Past quotation quantities

C.

Past sales order quantities

D.

Market intelligence

E.

Past production planning quantities

Question 15

How would you define pegging in the context of Advanced Planning?

Options:

A.

An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements

B.

An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements

C.

An evaluation to verify if there are material or capacity shortages in the ^ network after the production planning run

D.

An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run

Question 16

Which of the following processes lead to an entry in the MRP planning file?

Note: There are 3 correct answers to this question.

Options:

A.

Changing the storage bin in warehouse management

B.

Changing the procurement type in the product master

C.

Changing the operation times in the production data structure

D.

Changing the stock in inventory management

E.

Changing the purchasing contract in materials management

Question 17

You want to create a production order. What methods can you use?

Note: There are 2 correct answers to this question.

Options:

A.

Create by order release

B.

Convert a purchase requisition

C.

Create in Kanban process

D.

Create without material

Question 18

You Have a scheduling agreement with a vendor, you want classic MRP to automatically create

schedule lines in case of material shortage, what must you do?

Note: there are 2 correct answers to this question.

Options:

A.

Add the agreement to the source list and mark it for MRP relevance.

B.

Set the creation indicator for purchase requisition on the initial screen of the MRP run.

C.

Add the agreement to the quota arrangement and mark it for MRP relevance.

D.

Set the creation indicator for delivery schedule lines on the initial screen the MRP run.

Question 19

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

Options:

A.

To increase the number of planning levels

B.

To simplify the structure of bills of material

C.

To reduce the number of material masters

D.

To make the assignment of components easier

E.

To reduce the number of changes required in bills of material

Question 20

Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing?

Note: There are 2 Correct answers to this question?

Options:

A.

Run MRP with quota arrangement

B.

Run PP/DS heuristic for repetitive manufacturing

C.

Assign planned orders manually in the planning table

D.

Assign planned orders manually in the planning table

Question 21

What is the difference between co-products and by-products?

Options:

A.

Only co-products are identified by a special item category in the bill of material (BOM)

B.

Only co-products can be manufactured in isolation from the main product

C.

Only co-products have a zero inventory valuation

D.

Only co-products appear in the process or production order settlement rule

Question 22

Which time elements can be reduced by a reduction strategy?

Note: There are 3 correct answers to this question.

Options:

A.

Goods receipt processing time

B.

Move time

C.

Wait time

D.

Float after production

E.

Queue time

Question 23

which SAP application can be used for forecasting in Supply Chain Planning?

Note: there are 2 correct answers to this question.

Options:

A.

Integration Business Planning (IBP)

B.

Capacity Requirement Planning (CRP)

C.

Supply Chain Management (SCM)

D.

Material Requirement Planning (MRP)

Question 24

Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?

Options:

A.

Make-to-stock production (10)

B.

Planning with final assembly (40)

C.

Make-to-stock production (20)

D.

Planning without final assembly (50)

Demo: 24 questions
Total 80 questions