Labour Day Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

SAP C_TS422_2020 SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Exam Practice Test

Demo: 22 questions
Total 148 questions

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Question 1

The settings for MRP can be maintained at different levels. If settings have been maintained in different places, in which sequence does the system search for the MRP settings? Please choose the correct answer.

Options:

A.

Plant Settings -> MRP Group —> Material Master

B.

Material Master -> Plant Settings -> MRP Group

C.

Material Master -> MRP Group -> Plant Settings

D.

MRP Group —> Material Master -> Plant Settings

Question 2

Before a user can add multiple production versions in a material master, what information should be collected?

There are 3 correct answers to this question.

Options:

A.

Validity dates

B.

Lot sizes

C.

BOM status

D.

Work center hierarchy

E.

Task list group number

Question 3

Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?

Options:

A.

Use the material staging report.

B.

Use the batch information cockpit.

C.

Use the material where-used report.

D.

Use batch determination.

Question 4

A customer is considering switching from order-related settlement to productrelated settlement. What are capabilities of cost collectors? There are 2 correct answers to this question.

Options:

A.

They can be created automatically during month end process.

B.

They can be applied to make-to-stock production order.

C.

They can be used for repetitive manufacturing.

D.

They can be used for manufacturing with collective orders.

Question 5

You want to integrate an existing planned order into Advanced Production Planning. Which report do you use? Please choose the correct answer.

Options:

A.

/SAPAPO/UPD_LOC_SP_PL

B.

/SAPAPO/CURTO_CREATE

C.

/SAPAPO/PPDS_DELTA_ORD_TRANS

D.

/SAPAPO/CREATE_LOCATION

Question 6

Which task list types can have parallel sequences? There are 2 correct answers to this question.

Options:

A.

Routings (N)

B.

Master recipes (2)

C.

Rate routings (R)

D.

Reference operation sets (S)

Question 7

You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible. Which settings do you make to achieve this?

Options:

A.

Planning strategy 50 (Planning without final assembly) and the corresponding Mixed MRP indicator

B.

Planning strategy 20 (Make-to-Order) and the corresponding individual Collective indicator

C.

Planning strategy 20 (Make-to-Order) and the corresponding Mixed MRP indicator

D.

Planning strategy 50 (Planning without final assembly) and the corresponding individual Collective Indicator.

Question 8

MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?

Options:

A.

It is converted into a production order.

B.

It is converted into a reservation.

C.

It is converted into a planned order.

D.

It is converted into a schedule line.

Question 9

Which options are available for an SAP S/4HANA deployment? There are 2 correct answers to this question.

Options:

A.

SAP S/4HANA private cloud

B.

SAP S/4HANA Professional services cloud

C.

SAP S/4AHANA Enterprise Management cloud

D.

SAP S/4HANA on premise

Question 10

What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

To determine the work in progress along the production line

B.

To provide timely updates of inventory management for the staged components

C.

To stage different components for a production line simultaneously

D.

To reduce the total production lead time for along production line

Question 11

What determines whether the planned independent requirements in MRP consume other requirements?

Options:

A.

Requirements type

B.

Order type

C.

Requirements profile

D.

Consumption sequence procedure

Question 12

What does the industry sector determine? Note: There are 2 correct answers to this question.

Options:

A.

Whether a material master field is required, changeable, displayed, or hidden

B.

Which transaction you can use to create a new material

C.

Which material master views can be maintained

D.

Whether material numbers are assigned internally or externally

Question 13

In your project, you have several materials that are planned by different people. How can you assign the planning responsibility?

Options:

A.

MRP type

B.

MRP group

C.

MRP controller

D.

MRP planning file

Question 14

You want to represent setup time as a graphical object in the Detailed Scheduling Planning Board. Which actions are needed? There are 2 correct answers to this question.

Options:

A.

Run setup minimization heuristics or optimizer.

B.

Create and assign setup group/setup keys in the production data structure.

C.

Create and assign a new graphical object for setup time in the planning board.

D.

Create and assign a setup matrix with setup transition time to the resource

Question 15

If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?

Options:

A.

Fill up to the maximum stock level

B.

Fill up to the reorder stock level

C.

Fill up based on the lot size procedure

D.

Fill up to the safety stock level

Question 16

How can you set up the supply source for the SAP Kanban process? Note: There are 3 correct answers to this question.

Options:

A.

Using purchase orders for external procurement

B.

Using stock transfer reservations for stock transfer

C.

Using run schedule quantities for in-house production

D.

Using purchasing costs for automated source prioritization

E.

Using quotations for internal and external procurement

Question 17

What are properties of MRP Live? There are 2 correct answers to this question.

Options:

A.

It uses the same BAdis as classic MRP

B.

Data is read sequentially from the database tables

C.

The code is written in SQL Script

D.

It is executed on the database server

Question 18

Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?

Options:

A.

Operation network

B.

Resource network

C.

Work center hierarchy

D.

Setup matrix

Question 19

What does the bill of material usage (BOM usage) control at the BOM item level? There are 2 correct answers to this question.

Options:

A.

Default values for the item status

B.

Allowed material type

C.

Default unit of measure

D.

Maximum allowed low-level code

Question 20

You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

Options:

A.

Make-to-order production (20)

B.

Planning without final assembly (50)

C.

Planning with final assembly (40)

D.

Planning at assembly level (70)

Question 21

Which of the following functions can be performed when the production order has the status "Created" (CRTD)? Please choose the correct answer.

Options:

A.

A user can trigger material staging via mass processing (transaction COHV).

B.

A user trigger printing of shop floor paper manually (transaction CO02).

C.

A user trigger material availability check via mass processing (transaction COHV)

D.

A user can schedule a background job to release production orders (transaction COOIS).

Question 22

Which of the following time elements does MRP use during backward scheduling

for in-house production?

There are 2 correct answers to this question.

Options:

A.

Planned delivery time

B.

Opening period

C.

Goods receipt processing time

D.

Planning time fence

Demo: 22 questions
Total 148 questions