Labour Day Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

SAP C_TS412_2021 SAP Certified Application Associate - SAP S/4HANA Project Systems Exam Practice Test

Demo: 16 questions
Total 110 questions

SAP Certified Application Associate - SAP S/4HANA Project Systems Questions and Answers

Question 1

What could be a reason to use expert mode in the valuation method for results analysis?

Options:

A.

Billing WBS elements belonging to different company codes

B.

Assignments of different accounts for postings to financial accounting

C.

Usage of different line ID

D.

Valuation in different currencies

Question 2

How can you update the degree of processing for an activity?

Options:

A.

By using results analysis

B.

By changing the activity

C.

By scheduling the activity

D.

By confirming the activity

Question 3

Project structure.

You intent to work with predefined project coding mask to create project definitions. What do you have to consider?

Options:

A.

You can create project coding mask X... event if there are project numbers beginning with X.

B.

The standard project definition must differ from the definition of the operative project.

C.

You can use only numbers for a project coding mask definition.

D.

You can use an indicator to determine that only coded project numbers may be used within the project system.

Question 4

What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question

Options:

A.

Settlement

B.

Milestone trend analysis

C.

Confirmations

D.

Progress analysis

E.

Results analysis

Question 5

What is the reason for assigning billing plans in customer projects?

Options:

A.

Billing plans are prerequisites for quotation creation

B.

Billing plans are used for revenue planning

C.

Billing plans are copied automatically to the sales order item.

D.

Billing plans enable the billing process to be carried out

Question 6

Dates

How are earliest dates and latest dates of activities schedule?

Options:

A.

Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.

B.

Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.

C.

Earliest dates and latest dates are scheduled by forward scheduling.

D.

Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.

Question 7

What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.

Options:

A.

Ensure user status must always be set manually

B.

Allow business processes forbidden by SAP system status

C.

Restrict setting user status for individual users

D.

Utilize priorities for setting the user status

Question 8

You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?

Options:

A.

Vendor selection -> Purchase order handling -> Invoice receipt- Purchase order monitoring -> Goods receipt

B.

. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt -> invoice receipt

C.

Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval

D.

Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt

Question 9

Material

How can the system activate requirements (such as reservations or purchase requisitions)?

Note: There are 2 correct answers to this question

Options:

A.

Immediately, by saving the project

B.

Automatically, using the requirement date and the replenishment lead time

C.

Using a standard milestone activity

D.

When releasing a network or an activity

Question 10

Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question

Options:

A.

Material master

B.

Network activity

C.

WBS element

D.

BOM item

Question 11

Revenues & Payment

Your customer wants to plans and post revenues for WBS elements.

What is crucial for the implementation of revenues planning and posting for WBS elements?.

Options:

A.

At least one WBS element must be a billing element.

B.

The indicator "Project type" must be set to "Customer project".

C.

Revenue planning and billing must be activated in the corresponding network type.

D.

A sales order item has to be assigned to each WBS element used for revenue planning.

Question 12

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

Options:

A.

Set up the requirement date aligned with the activity finish date and an offset of 15 days.

B.

Set up the requirement date manually as February 5.

C.

Set up the requirement date aligned with the activity start date and an offset of 5 days

D.

Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Question 13

You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation.,

and have entered the quotation ...

What is the typical sequence for the following business transactions and document.

Options:

A.

Benefic check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoce ..

B.

Vendor selection - purchase order handing- purchase order monitoring- Benefic Check- Acceptance of performed services.

C.

Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt.

D.

Vendor selection- Purchase order handing-purchase order monitoring-Good receipt- Invoice receipt.

Question 14

You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

Options:

A.

The person responsible for the work center

B.

The person responsible for the superior WBS element

C.

The MRP controller for the network

D.

The person responsible for the network activity

Question 15

You want to exchange data between SAP Project System and Microsoft What interface do you use?

Options:

A.

The EPS interface (External Project Software).

B.

No interface to Microsoft Project is available.

C.

The catalog interface.

D.

you do not need and interface. You can exchange data using object link.

Question 16

Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.

Options:

A.

Usage of cost elements is mandatory

B.

Sales prices are maintained in the DIP profile

C.

DIP is used to create a quotation

D.

Sources can be based on line items

E.

Material determination is mandatory

Demo: 16 questions
Total 110 questions