Halloween Sale Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 75only

PRINCE2 PRINCE2-7-Practitioner PRINCE2 Project Management Practitioner (Version 7) Exam Practice Test

PRINCE2 Project Management Practitioner (Version 7) Questions and Answers

Question 1

As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.

Under which ‘directing a project’ activity is this informal consultation provided?

Options:

A.

Authorize a stage or exception plan

B.

Give ongoing direction

C.

Authorize initiation

D.

Authorize the project

Question 2

The Louistown City Council operates a well-established and standardized project management framework that includes a defined procedure for developing business cases. For the LouisShopping Project, a ‘strategic business case’ was included in the project brief submitted to the project board at the conclusion of the ‘starting up a project’ process. The project has now entered the ‘initiating a project’ process, during which the full business case is being built upon the strategic business case, which was itself derived from the Council’s five-year strategic plan for the ‘Louistown is Open for Business’ portfolio.

Does this represent an appropriate application of the ‘business case’ practice, and why?

Options:

A.

Yes, because developing the business case from multiple perspectives – strategic, economic, and commercial – ensures a comprehensive and robust justification for the project investment

B.

Yes, because the project should align its approach to business case development with the City Council’s established procedure, which serves as the equivalent of PRINCE2’s recommended business case lifecycle

C.

No, because the full business case should be developed from an outline business case prepared during the ‘starting up a project’ process, and using a ‘strategic business case’ instead is not compliant with the method

D.

No, because responsibility for developing the full business case for each project in the portfolio lies with the portfolio office, not the project team

Question 3

During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.

Is this an appropriate use of the ‘give ongoing direction’ activity, and why?

Options:

A.

Yes, because a project board member may raise concerns and provide ongoing direction within the authority delegated to the board

B.

Yes, because the senior user has an obligation to formally approve key specialist products produced during stages 2 and 3 as a standard action within the ‘give ongoing direction’ activity

C.

No, because the ‘give ongoing direction’ activity is only triggered when the project manager proactively requests a review by the project board, not when individual board members identify concerns independently

D.

No, because the Heritage Director should first seek the agreement of the full project board before raising individual concerns, to ensure a unified project board position is presented to the project manager

Question 4

ISSUES

During stage 1, BuildyBrick was appointed by the procurement team manager as the main contractor for the project. The project is now in stage 3 and BuildyBrick is part way through the site preparation. Following an environmental survey report, BuildyBrick will have to delay the site clearance by several weeks to enable protected amphibians to be relocated. There are two options to deal with this issue. The first is to wait for BuildyBrick to clear the site, but this will take longer. The second is to hire an additional contractor to clear the site more quickly, but this will cost more. Both of these options can be completed within cost and time tolerances, but appointing an additional contractor is beyond the project manager’s delegated authority.

Here are three actions related to the resolution of this issue.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.

Project executive

B.

Senior user

C.

Senior supplier

D.

Project assurance

E.

Project manager

Action 1:

Review the issue report and decide which response should be authorized.

Action 2:

After the decision is made, update the issue record with the selected response and decision.

Action 3:

Once the appointment is authorized, confirm that the supplier resources required for the additional site-clearance work can be provided.

Question 5

Before the end of stage 2, the project board authorizes a change that adds more trees and seating to the external landscaping. The change can be delivered in stage 3 without any forecast breach of project tolerance. While preparing the next stage plan, the project manager incorporates the additional products and work, updates the relevant product descriptions and product register entries, and reviews whether the project initiation documentation needs to be updated.

Is this an appropriate application of ‘prepare the next stage plan’, and why?

Options:

A.

Yes, because the next stage plan should reflect authorized changes, with affected product information and the project initiation documentation updated where necessary

B.

Yes, because every authorized change must be implemented through an exception plan before the related work may enter the following stage

C.

No, because authorized changes should remain outside the next stage plan until the project has been re-authorized by the business layer

D.

No, because project assurance should prepare the next stage plan and update the affected product information independently of the project manager

Question 6

The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.

Is this an appropriate application of the quality practice, and why?

Options:

A.

Yes, because the portfolio office should manage the project’s quality-control activities on behalf of the project manager

B.

Yes, because the business layer may use the portfolio office to perform independent quality-assurance activity on its behalf

C.

No, because assurance information may be provided to the project board and not to the business layer

D.

No, because a portfolio office may assess strategy but may not review the delivery of individual projects

Question 7

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

Options:

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

Question 8

A high-level requirement that the design should be consistent with its surroundings was recorded during ‘starting up a project’. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.

Which management product should be updated with this information?

Options:

A.

Project product description

B.

Work package

C.

Product flow diagram

D.

Project plan

Question 9

A product description contains only the following quality specification for the car-parking component: “The shopping centre will include an underground car park.”

Is this an effective application of the quality practice, and why?

Options:

A.

Yes, because confirming that a car park exists completely specifies its required quality

B.

Yes, because the statement provides sufficient information to confirm whether the required component has been delivered

C.

No, because all details of the car park should be recorded only in the quality management approach

D.

No, because the product description needs sufficiently detailed, measurable quality specifications and tolerances to support planning and verification

Question 10

At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

Options:

A.

Yes, because the project manager is authorized to manage the project on a day-to-day basis within set tolerances throughout each stage, without requiring additional project board decisions

B.

Yes, because the Portfolio Director, as the commissioning authority, has the right to determine the reporting frequency and format that best suit portfolio-level oversight

C.

No, because it is the City Council, rather than the Portfolio Director, that should hold the authority to commit funding across multiple stages of the project

D.

No, because the project board must review the continued viability of the business case and authorize the next stage at each stage boundary, rather than approving multiple stages in advance

Question 11

While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.

Is this an appropriate application of ‘starting up a project’, and why?

Options:

A.

Yes, because the primary purpose of assessing the project approach at this stage is to clarify the prospective obligations of the project team and each external supplier when delivering the project products

B.

Yes, because the way the project work will be delivered directly influences how the management approaches are designed, and identifying risks early helps ensure the PID accurately reflects how sustainability will be managed

C.

No, because a risk that is classified as manageable does not pose a threat to overall project viability and should be deferred for consideration during the initiation stage when more detailed planning takes place using the traditional delivery method

D.

No, because any sustainability requirements that the project must satisfy should be captured as user quality expectations in the project product description, not as risks in the project log

Question 12

During the ‘initiating a project’ process, the team expects local heritage-protection groups to oppose the proposal. The Heritage Director suggests waiting until the groups contact the project. Instead, the project manager asks the Heritage Manager to identify groups known from previous work, and the manager supplies a list.

Is this an appropriate approach to leading successful change, and why?

Options:

A.

Yes, because the project manager is using existing stakeholder knowledge to identify affected and influential groups proactively

B.

Yes, because identifying a stakeholder guarantees that the stakeholder will support the project and its business case

C.

No, because stakeholder identification should not take place during project initiation

D.

No, because early identification of an opposing group will necessarily increase its opposition

Question 13

BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.

Is this an appropriate application of the plans practice, and why?

Options:

A.

Yes, because the specialist supplier should own the stage plan whenever it delivers most of the stage products, and team managers can prepare the relevant information

B.

Yes, because the project manager should prepare stage plans only for stages involving more than one supplier

C.

No, because each external supplier should prepare the complete stage plan for the stage in which it works

D.

No, because the project manager remains responsible for preparing each stage plan; team managers may prepare team plans and detailed work package information

Question 14

While preparing the risk management approach, the project manager holds a workshop to review the project context: the historic surroundings, sustainability targets and the need to minimize disruption to residents and businesses.

Is this an appropriate application of the risk practice, and why?

Options:

A.

Yes, because the contextual statement is itself a complete set of cause-event-effect risk descriptions

B.

Yes, because understanding the project’s context and objectives is necessary to design a risk management approach

C.

No, because risk responses must be selected before the risk management approach can be fully prepared

D.

No, because project objectives should not influence how risk is managed

Question 15

PLANS

Here are three items of information included in the stage 2 plan.

Under which heading (A–F) should each item be recorded?

Choose only ONE heading for each item of information. Each heading may be used once, more than once, or not at all.

Options:

A.

Dependencies

B.

Planning assumptions and prerequisites

C.

Products to be delivered

D.

Budget

E.

Tolerances

F.

Monitoring, control and reporting arrangements

Item 1:

The plan assumes that limited familiarity with new sustainable technologies will increase the likelihood of design errors, so additional time has been allowed for quality control.

Item 2:

During stage 2, the project manager will send the project board a summary of design progress every two weeks.

Item 3:

Stage 2 will produce archi

Question 16

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project

B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package

C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options

D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working