The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?
Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?
Fill in the blank with the appropriate word. When activities are logically linked, they become the . __________
Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?
You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:
You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?
You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter. They would like some idea of how long the project will take based on the information in the project charter. While you are uncomfortable giving any type of estimate at this point, you work with your assigned project to create a quick time estimate. What type of estimate have you created for management?
You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?
You are the project manager of the AHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day of early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?
You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?
You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?
You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?
You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should at the 45 percent milestone today, but due to some early delays you're running late. What is the schedule variance of your project?
Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?
Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?
Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?
You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. What is the estimate at completion for this project that you will need to report to management?
Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?
You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so you will need to update the schedule and the schedule baseline. The schedule baseline is a component of what?
Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?
Gary is the project manager of the NHF project, which is a part of a program in his organization. According to the PMBOK, how will Gary provide feedback to programs and portfolios?
Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?
Examine the figure given below:
If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?
Mary is the project manager for her company. She's working with the project team to compress the project schedule as the project must be completed by December 30. For some of the project activities, she and the project team have agreed to crash the project work. What must be true of these project activities for crashing to be acceptable?
You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?
John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of work for the project plan. Which of the following can be categorized as a project phase? Each correct answer represents a complete solution. Choose all that apply.
You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record this communication requirements based on your stakeholder analysis?
Lara has been assigned to a construction project. The project includes constructing a residential building with fifty flats. On which of the following events will the project be considered successful?
You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your cost variance for this project?
Kay is the project manager of the QUI Project. This project is done but is also considerably over budget. Kay has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Kay do with the information regarding the schedule delays and cost overruns?
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project Management process are you working with when you create a new target schedule?
You are the project manager of the NHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day for the early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but you must be careful not to increase project risk beyond an acceptable level of risk exposure. Which of the following approaches is most likely to increase project risk?
In which of the following group decision making techniques does the largest block in a group decide the group decision even if a bulk is not achieved?
Paula works as a project manager for her organization. She is working with the project team to define the activity attributes. Which of the following is NOT a valid activity attribute?
You are the project manager of the HGH Project. Thomas, your project sponsor, asked you to submit status reports every week, but now he wants you to submit the status reports every other week. What project management plan would you need to update to reflect this change from Thomas?
All of the following statements about the critical path are false except for which one?
Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for each identified stakeholder may be, and classifying the stakeholders by common characteristics, concerns, and their perception of the project. Andy and his project team want to define an approach as a result of this information to gain support from the stakeholders for their project. What should Andy and his project team create in this scenario?
Amy works as a project manager for BlueWell Inc. She is working on the SDI project, which has a BAC of $2,816,000. She is currently 20 percent complete with this project, though she should be 25 percent complete with the project work. The project has consumed $495,000 of the project budget to date. Management has asked her the project's Estimate To Complete (ETC) based on the current project performance. What is the ETC for this project?
What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?
You are the project manager for the GHY Project. This project has stakeholders, both internal and external, that need to receive performance reports from you on a regular basis. You have decided that in addition to emailing the weekly performance report, you will also keep the performance reports available on your secured project management Website. The Website is an example of what type of communication reporting?
Fill in the blank with an appropriate phrase. The ________is defined in terms of either the product or the type of customer or industry sector.
What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?
You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start-to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?
Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?
You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?
Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?
You are the project manager of the NHQ project. This project is slightly larger than the TR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?
You are working with your project team to control the project schedule. You will need five inputs to this process throughout your project. Which one of the following is an output of the project schedule control, and NOT an input?
Beth is the project manager of the KJH project. Sarah is Beth's administrative assistant and Ben is the project team leader. Beth's project has eight virtual teams throughout the world that will be working on the activities relevant to the deliverables in their locales. Thomas, the project sponsor, has told Beth that he is to be kept abreast of all communication between her project and the stakeholders. In this project, who is the lead person responsible for communication with all stakeholders?