Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Exam Practice Test

Demo: 79 questions
Total 264 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 1

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

Options:

A.

Risks that are tied to the success of the organization

B.

Risks as they apply to the organization's overall risk management philosophy and strategic ambition

C.

Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

D.

Risks related to cost that will impact the major projects that are currently in the execution phase

E.

Risk mitigation actions that will require work from stakeholders

Question 2

An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.

Update the risk register

B.

Meet with the project's stakeholders

C.

Revise the risk management plan

D.

Ensure sufficient resources are available

Question 3

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?

Options:

A.

Reinforce to the stakeholders that the risk identification was done properly during the last sprint.

B.

Highlight the importance of agreeing on the risk identification to avoid further delays.

C.

Conduct a separate meeting to show the risk identification analysis to the stakeholders.

D.

Ensure that the most knowledgeable members of the team validate risk identification processes. 

Question 4

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

What should the risk manager do to avoid the previous issues?

Options:

A.

Use the information for a risk workshop.

B.

Improve monitoring and controlling of activities.

C.

Document the issues in the lessons learned.

D.

Create an issue log to share with the team.

Question 5

A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

Options:

A.

To enable the team in identifying the specific causes of risks associated with project objectives.

B.

To ensure that project priorities are being appropriately factored into risk response plans.

C.

To determine there more attentive project leadership and organizational involvement is needed.

D.

To assign risks and risk severities to functional discipline and departments effectively.

Question 6

A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)

Options:

A.

Applying modern risk management techniques.

B.

Aligning to project constraints and priorities.

C.

Ensuring risk response strategies mitigate all risks.

D.

Minimizing implementation costs.

E.

Obtaining stakeholder acceptance

Question 7

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

Options:

A.

Revisit this risk in the risk register and redefine the mitigation strategy.

B.

Activate the contingency plan to handle this risk during execution.

C.

Mark this new risk as an extremely high priority and inform all stakeholders.

D.

Ask the project sponsor for more budget to deal with this risk.

Question 8

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do?

Options:

A.

Reduce the probabilities of those risks on the risk register

B.

Transfer ownership of those risks to the customer

C.

Implement the risk handling strategies for those risks

D.

Request additional management reserve for those risks

Question 9

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)

Options:

A.

Verify whether or not any identified risks might occur and implement the risk response plan.

B.

Regularly check and report on the status of risks identified according to their prioritization.

C.

Monitor the status and oversee execution of the risk response plan for each identified risk.

D.

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

E.

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

Question 10

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

Options:

A.

Risk description risk response, and quantitative data

B.

Project plan, risk complexity, and secondary risk

C.

Project plan, risk priority, and tool availability

D.

Risk description, risk probability, and risk impact 

Question 11

During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?

Options:

A.

Sensitivity analysis

B.

simul-ation analysis

C.

Monte Carlo simul-ation

D.

Quantitative analysis

Question 12

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders, and this delays the decision-making process.

Options:

A.

Organize training sessions to create awareness around the agile values for stakeholders.

B.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

C.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

D.

Allow stakeholders to discuss without the scrum master's intervention.

Question 13

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource's availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.

What should the risk manager do next?

Options:

A.

Update the risk register to indicate the risk has occurred and close out the expired risk from the register.

B.

Update, continuously monitor, and communicate the residual and secondary risks of the backup resource on the project.

C.

Hire a permanent developer to support the project, and work with the backup resource to eliminate this risk.

D.

Hire another developer to support the project, contingent on when the experienced developer returns. 

Question 14

A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?

Options:

A.

Continue to implement the risk strategy

B.

Meet with team members to address their concerns.

C.

Reduce the number of risk management activities.

D.

Raise the concerns with the project sponsor,

Question 15

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.

The cost control processes is ineffective.

B.

The cost baseline is inaccurate.

C.

The actual reported costs are inaccurate.

D.

The cost related risks are effectively managed.

Question 16

A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

Options:

A.

Risk management plan

B.

Clients' credit scores

C.

Organization's mission and vision

D.

Historical data from the credit portfolio

Question 17

During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?

Options:

A.

Contact the risk managers of the other projects and inform them

B.

Include an escalation process in the risk management plan

C.

Take note of the extensive impact of these risks in the risk register

D.

Address the unique characteristics of these risks on a case-by-case basis

Question 18

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.

What should the risk manager do in this case?

Options:

A.

Document the risk in the risk register for analysis.

B.

Document the detailed risk consequences,

C.

Immediately start the contracting process.

D.

Proceed with the quantitative risk analysis. 

Question 19

A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project's risk register to try to maximize their chances of occurrence.

What should the project team do next?

Options:

A.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

B.

Log the threats in the risk register to try to minimize the probability of occurrence.

C.

Log the threats in the risk register to try to maximize the probability of occurrence.

D.

Update the project management plan to ensure the results of the opportunities are captured.

Question 20

A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.

Given the project's complexity, what should the risk manager do?

Options:

A.

Wait until halfway through the project to identify risks, as most issues will be clear by then.

B.

Conduct the exercise with the key team members, excluding external stakeholders.

C.

Facilitate a risk identification exercise with key stakeholders, considering all factors.

D.

Focus only on identifying the most obvious risks to save time and project resources.

Question 21

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

Question 22

While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.

What should the risk manager do to manage this risk?

Options:

A.

Perform time recovery actions.

B.

Execute the prevention plans.

C.

Execute the contingency plans.

D.

Perform change management.

Question 23

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

Options:

A.

Industrial studies

B.

Commercial risk databases

C.

Organizational process assets (OPAs)

D.

Enterprise environmental factors (EEFs)

Question 24

The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.

What should the risk manager do?

Options:

A.

Follow up on the schedule and assess the best course of action if any delays are detected.

B.

Ensure the equipment constraint is well-documented and manage it as a high-impact project risk.

C.

Raise the issue with the project sponsor so it can be handled as a sales or contractual matter.

D.

Obtain a signed commitment from the customer that equipment will be delivered on time. 

Question 25

A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?

Options:

A.

Time Series Analysis

B.

Regression Analysis

C.

Variance Analysis

D.

Monte Carlo Analysis 

Question 26

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

Options:

A.

Risk mitigation

B.

Risk transfer

C.

Risk acceptance

D.

Risk avoidance

Question 27

A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.

What is an effect of adding the correlation to the model?

Options:

A.

Allows more risks to be included in the model.

B.

Reduces the project completion duration.

C.

Increases the standard deviation of the model.

D.

Increases the probability of correlated activities finishing on time.

Question 28

A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.

What will be the main output of this meeting?

Options:

A.

Evaluating the project's probability of success

B.

Identifying threats and opportunities

C.

Evaluating the project's impact

D.

Performing a qualitative analysis

Question 29

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

Options:

A.

Highlight this situation to the project manager

B.

Conduct a cost-benefit analysis

C.

Change the risk response strategy

D.

Analyze the situation and meet with the risk owner

Question 30

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

Options:

A.

Add more float to the key activity

B.

Add more contingency to the project

C.

Review the plans for the key activity

D.

Increase the budget for the key activity

Question 31

A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.

How should the risk manager address these concerns?

Options:

A.

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.

B.

Refer to the project charter to find guidelines and stakeholder communication channels.

C.

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.

D.

Rewrite the risk register to include the additional possible risks and inform the stakeholders.

Question 32

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.

Risk assessment criteria

B.

Project management plan

C.

Project assumptions

D.

Risk management plan 

Question 33

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

Options:

A.

Request for a skilled facilitator to help resolve conflicts that have arise.

B.

Refer to the team’s ground rules on how to resolve conflicts.

C.

Run a sensitivity analysis to check which risks have the most impact.

D.

Use the assumption analysis techniques to validate the assumptions.

Question 34

A risk manager is assigned to a mobile network deployment project with a strict contractually agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing because critical resources are dedicated to strategic projects in the organization. The risk manager expected the resource manager to notice this, but the resource manager thought the project experts would be alerting the team during the project.

What should the risk manager do to prevent this from happening again?

Options:

A.

Document the risks and response actions in a clear manner.

B.

Communicate with the project manager on the topic.

C.

Assign owners who will be fully accountable to managing the risks.

D.

Define the response plans and take the lead in implementing them.

Question 35

A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.

What should the risk manager do with this risk?

Options:

A.

Put the risk on the watch list.

B.

Seek guidance from subject matter experts (SMEs).

C.

Ignore this risk as it is not critical.

D.

Inform the stakeholders about this risk.

Question 36

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Options:

A.

Review potential next steps with the project team.

B.

Review the scope of work to determine the prescribed project methodology.

C.

Review the policies and practices that are outlined in the risk management plan.

D.

Review the contract and determine the resources and project funding.

Question 37

A risk manager has been assigned to prepare a risk management plan for a new project. Which factor should the risk manager prioritize when tailoring the risk management processes for the new project?

Options:

A.

Available funds for risk management activities

B.

Size and duration of the project

C.

Maturity of the organization's risk management processes

D.

Number of stakeholders associated with the project

Question 38

The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.

What should the project risk manager do next to identify risks?

Options:

A.

Review the risk breakdown structure to ensure project scope is covered.

B.

Use the brainstorming technique to remove personal bias.

C.

Use expert judgment to remove ego or emotional conflict.

D.

Consider the Delphi technique to gather all stakeholder opinions.

Question 39

An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.

What should the risk management expert recommend the agency do first to identify risks and develop the handbook?

Options:

A.

Follow standard risk Identification tools dedicated for agriculture and tailor them to the environment.

B.

Hire an agriculture expert who can develop the required handbook and discuss it with the agriculture minister.

C.

Prepare a list of the key resources that will be used to compile a risk management plan.

D.

Conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks.

Question 40

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices.

What should the risk manager do?

Options:

A.

Ask the sponsor to define the risk strategy to align with client needs.

B.

Develop a framework and engage the team in creating a risk plan.

C.

Train the team on basic techniques and defer the risk strategy for later.

D.

Concentrate on high-priority risks to meet the sponsor's expectations.

Question 41

A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.

What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?

Options:

A.

Release this version and leave changes to be done at the end of the project phase.

B.

Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.

C.

Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.

D.

Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery.

Question 42

A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.

What should the risk manager advise the project team to do?

Options:

A.

Align the project risk thresholds with the risk appetite of a critical region.

B.

Align the project risk thresholds with the organizational risk appetite.

C.

Concentrate on the risk appetites of the influential stakeholders.

D.

Concentrate on the risk appetites of the vulnerable stakeholders. 

Question 43

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.

Review project schedule estimates.

B.

Change the response strategies.

C.

Reduce the contingency reserves.

D.

Conduct a risk planning workshop.

Question 44

A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.

Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).

Options:

A.

Work with the project team to conduct a decision tree analysis for each risk or set of related risks.

B.

Calculate the expected monetary value (EMV) of each risk and use these outputs to inform and defend project reserves.

C.

Conduct a Monte Carlo simul-ation to understand the probabilities of various risk outcomes.

D.

Use the risk breakdown structure (RBS) to calculate the total cost of mitigating all risks and ensure project reserves are adequate to cover this amount.

E.

Focus attention and resources on identified risks with the highest potential to impact the project.

Question 45

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.

How should the risk manager address this concern?

Options:

A.

Risks are documented to the practicable extent possible.

B.

Probability of the risk was very low. so the risk was not documented.

C.

Impact of the risk was assessed to be insignificant, so the risk was not documented.

D.

A similar risk never occurred in the past, so it was not considered. 

Question 46

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

Options:

A.

Perform a FMECA fault tree analysis

B.

Conduct a sensitivity analysis

C.

Perform a decision tree analysis

D.

Conduct an analytic hierarchy process

Question 47

A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.

What should the project manager do to avoid this risk?

Options:

A.

Record this risk and the clients preference in the risk register.

B.

Ask the sales person to lead the communication with the client

C.

Call the client and advise that online communication is easier and faster.

D.

Meet the client and plan tor critical milestone meetings.

Question 48

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Options:

A.

Close and communicate the results of the risk response actions.

B.

Run a workshop to analyze the effectiveness of the risk plan.

C.

Conduct a risk reserve analysis and document the results.

D.

Verify that all risk response actions have been documented. 

Question 49

A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.

What should the risk manager do first?

Options:

A.

Develop a residual risk management plan to manage the residual risks.

B.

Analyze, document, and communicate the residual risks to stakeholders.

C.

Record the residual risks in the watch list for future reference.

D.

Implement the contingency plan when the residual risks occur.

Question 50

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

Options:

A.

Ensuring that the project sponsor is kept well-informed

B.

Arranging periodic risk: management process audits

C.

Communicating the status of risks regularly to stakeholders

D.

Monitoring costs with intervention when necessary

Question 51

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

Options:

A.

Probability of a response triggering a secondary risk

B.

How the response will affect the quality of the components

C.

If the risk response is tied to an activity on the critical path

D.

Verify due dates for the actions have been identified

Question 52

In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

Options:

A.

Exploit

B.

Accept

C.

Share

D.

Enhance 

Question 53

An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?

Options:

A.

Ensure sufficient resources are available

B.

Revise the risk management plan

C.

Update the risk register

D.

Meet with the project's stakeholders

Question 54

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

Options:

A.

Add only the threats to the risk register

B.

Utilize different tools to identify the risks

C.

Plan risk responses to the threats

D.

Update the risk register with the identified risks

Question 55

Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?

Options:

A.

Activate the contingency plan.

B.

Request a reserves increase.

C.

Add the alert to the risk register.

D.

Update the risk response plan.

Question 56

A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?

Options:

A.

Create a new project plan including the new risks.

B.

Review the effectiveness of the risk process.

C.

Update the risk management plan.

D.

Escalate the project risks to upper management. 

Question 57

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Options:

A.

Accept the response because there are no secondary risks were identified.

B.

The response plan should be discontinued and the risk should be accepted and dealt with if it occurs.

C.

Accept the residual risk as it is compatible with the organization's risk appetite.

D.

All identified risks must be addressed because they might significantly impact the project if they occur. 

Question 58

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.

What should the risk manager do next?

Options:

A.

Consult with the project manager to agree that these risks should be removed from the risk register

B.

Keep the risks in the risk register and continue to follow up until the change actually takes place.

C.

Identify workarounds that can be implemented whether or not the change takes place.

D.

Revisit the project the assumptions and constraints to potentially update the risk impact and response. 

Question 59

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

Options:

A.

Compatibility

B.

Urgency

C.

Usability

D.

Proximity

E.

Detectability 

Question 60

A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?

Options:

A.

Risk burndown chart

B.

Ishikawa diagram

C.

Risk breakdown structure (RBS)

D.

Affinity diagram

Question 61

A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?

Options:

A.

Combine individual and focus groups to identify risks and create the overall risk register.

B.

Use focus groups to conduct group risk assessments of the project to identify risks.

C.

Request individual assessments of the project and its deliverables to identify risks.

D.

Use the external risk assessment of the project and its deliverables to identify risks.

Question 62

During a project team meeting, a risk manager realizes that the initial assumptions on the project schedule are too optimistic. The risk manager believes that the project might not meet its deadline as initially stated.

What is the reason for misunderstanding the assumptions from the beginning?

Options:

A.

Government regulations have changed in the last week, and now additional approval processes are required.

B.

The team's compensation was reduced and they lost the motivation to comply with the project deadline.

C.

The stakeholders prepared the initial schedule assumptions based only on the results of the last project.

D.

The sponsor had neither presented the actual results to the stakeholders nor updated the initial assumptions.

Question 63

A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

Options:

A.

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.

B.

The ideal solution is to find alternate documents that provide good visibility on the environment.

C.

The risk identification process can be carried out as long as the project statement is available.

D.

Risk evaluation will be challenging without these elements as a frame of reference.

Question 64

During the project's lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

Options:

A.

Carry out the agreed risk response action should the risk occur.

B.

Provide a numerical estimate of the overall effect of risk on the objectives.

C.

Track identified risks and maintain the viability of response plans.

D.

Develop the overall risk management strategy for risk integration. 

Question 65

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

Options:

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

Question 66

A Scrum team has recently lost its product owner to another team. A new product owner has been hired for the Scrum team. This product owner is currently new to the project, unfamiliar with the team's practices, and does not have a full grasp of the product users. After a few sprints, the product owner is receiving constructive feedback from both internal and external stakeholders related to the direction of the product and its current challenges.

What can the product owner do to improve the product's perception among stakeholders and ensure the team understands the product vision? (Choose 2)

Options:

A.

Re-assess the product goal, place it on the product backlog, and explain it to the team.

B.

Invite more stakeholders to the daily scrum meetings to voice their opinion of the product.

C.

Create sprint goals and communicate them at the sprint planning event.

D.

Invite product teams to more frequent reviews to observe the team's work and encourage feedback.

E.

Invite stakeholders to the sprint retrospective to brainstorm with the team improvements.

Question 67

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

Options:

A.

US$18,000

B.

US$72.000

C.

US$30,000

D.

US$48,000

Question 68

An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain.

What should the risk management team leader do in the early stages of the project?

Options:

A.

Conduct qualitative risk analysis to prioritize potential risks.

B.

Plan a solid risk response plan and secure the necessary funding.

C.

Educate stakeholders on best practices to perform risk management.

D.

Benchmark to an organization which has executed a similar project,

Question 69

A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.

What type of risk response is this?

Options:

A.

Transfer

B.

Accept

C.

Mitigate

D.

Avoid 

Question 70

During a virtual workshop presenting a product to potential clients, a facilitator emails the product brochure and asks attendees to check their spam folder if the email does not appear in their inbox. What kind of threat strategy is the facilitator applying?

Options:

A.

Accept actively

B.

Mitigate

C.

Accept passively

D.

Share

Question 71

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned

B.

Contingency register

C.

Risk register

D.

Issue log

Question 72

A risk manager has been assigned to a project constructing a chemical laboratory. Unfamiliar with chemical laboratories, the risk manager is unsure of where to start objectively identifying risks.

What should the risk manager do?

Options:

A.

Import a risk register from other industry chemical laboratories.

B.

Define chemical laboratory safety risk thresholds.

C.

Review published operational experience reports.

D.

Draft threat and opportunity risks that come to mind.

Question 73

During a project's planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.

The probability and impact rating of the supplier's delay on the project

B.

The response strategy, such as increasing inventory or finding an alternative supplier

C.

The specific event or condition, such as the supplier missing a delivery deadline

D.

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Question 74

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.

What should the risk manager do?

Options:

A.

Schedule a meeting to review and develop realistic risk thresholds with the project team.

B.

Motivate and influence the project team with risk engagement activities like workshops.

C.

Ensure that risk management responsibilities are clearly identified in the risk management plan.

D.

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

Question 75

A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

Options:

A.

Develop and employ an Ishikawa diagram

B.

Analyze the assumptions and constraints

C.

Perform a review of project documents

D.

Create prompt lists for expert interviews

Question 76

After completing the sprint on an agile project, a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project's risk exposure to an acceptable level?

Options:

A.

Update the definition of done (DoD) to improve risk management.

B.

Review the acceptance criteria for upcoming stories.

C.

Prioritize risk mitigation stories for the next sprint.

D.

Check stories in the product backlog to identify risks.

Question 77

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Options:

A.

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

B.

Address these secondary risks as per the risk management plan

C.

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

D.

Update the risk management plan with the new probabily/impact and change the response.

Question 78

The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.

How should this documentation be utilized in the future?

Options:

A.

To return the remaining amount of the contingency reserve

B.

To ensure information is recorded for lessons learned

C.

To comply with the rules and regulations

D.

To hold those who created the risk accountable

Question 79

The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

Options:

A.

The management team agreeing to include more resource for the digital signature initiative.

B.

The organization's professional engineers having reservations about possible information tampering.

C.

A growing number of competitors with digital signatures.

D.

An elimination of manual steps associated with recording wet signatures

E.

The growing adoption of mobile communications in the industry.

Demo: 79 questions
Total 264 questions