Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

PMI PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Exam Practice Test

Demo: 144 questions
Total 476 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 1

A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.

How should the team address this issue?

Options:

A.

The team member that is complaining should talk individually with the scrum master to remove impediments.

B.

They should ask for more details about the impediments and then resolve them when the team has more time to investigate.

C.

The team member that is complaining should address the impediments in daily scrum, communicating them directly.

D.

Team members should state that they need to prioritize their work instead of responding to daily emails about impediments.

Question 2

What should the team do?

Options:

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Question 3

What should the agile team lead do?

Options:

A.

Create a new team to deliver the dependencies, and bring team B under performance management.

B.

Conduct a vision-sharing session with the teams to communicate the project's overall goals.

C.

Swap team members from both teams so that deliveries are better supported.

D.

Discuss negotiating the delivery timelines with team A.

Question 4

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?

Options:

A.

Add the releases into a roadmap with milestones and activities.

B.

Identity dedicated tasks and activities with regular feedback loops.

C.

Deliver in small and continuous iterative releases.

D.

Identify the requirements' schedule within set time scales.

Question 5

What should the agile practitioner do?

Options:

A.

Commend the team on trying the idea, then encourage discussion regarding alternatives

B.

Ask a manager to direct the team on fixing the process

C.

Encourage the team to continue executing the idea to see if it improves

D.

Privately speak with the team member to convey that their idea worsened the outcome

Question 6

The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.

What should the agile practitioner do?

Options:

A.

Discuss the issue with the team at the next daily standup meeting.

B.

Discuss the issue with the team at a special meeting for this purpose.

C.

Discuss the issue with the project stakeholders at a special meeting for this purpose.

D.

Discuss the issue with the team at the next project retrospective.

Question 7

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

Options:

A.

High-risk and high-value

B.

High-risk and low-value

C.

Low-risk and low-value

D.

Low-risk and high-value

Question 8

Answer Options:

Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team's velocity is constant.

Question 9

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

Options:

A.

Capture risks and make them visible, and use a burndown chart to focus on reducing risks early in the project.

B.

Ask the Scrum Master to extend the sprint's duration to allow more time to work through technical issues.

C.

Place the impacted stories on the story board, and use daily stand-ups to make the product owner aware of the technical issues.

D.

Seek guidance from the development manager.

Question 10

What agile tools can help the team address these issues?

Options:

A.

Information radiators and wireframes

B.

Information radiators and story maps

C.

Process flows and personas

D.

Personas and extreme characters

Question 11

When working with Lean approaches, which process includes the sequence of steps for delivering value and those required to carry them out?

Options:

A.

Value stream mapping

B.

Long-term Lean planning

C.

Business process modeling

D.

Planning poker

Question 12

During refinement, the team tester has a question about part of the acceptance criteria for a given user story. Who should clarify the acceptance criteria?

Options:

A.

The sponsor, since they understand the business value.

B.

The Scrum Master, since they coordinate with the team and define the acceptance criteria.

C.

The Product Owner, since their vision is the basis for the acceptance criteria.

D.

The developer, since they write the code that would be tested.

Question 13

A project manager is working on a user story about migrating to a new version of a database but is unsure of the dependencies. What can the product owner request from the team to understand the risks?

Options:

A.

Refinement meeting

B.

Daily standup meetings

C.

Retrospective

D.

Spike

Question 14

How can this issue be resolved?

Options:

A.

Break down the feature into smaller parts, and commit to completing the minimum viable product.

B.

Complete the iteration to which they have already committed, and include the feature in the next release.

C.

Change the planned features to include only the vitally important one.

D.

Extend the iteration to complete the feature.

Question 15

An executive sponsor of a new Scrum team actively attends Scrum ceremonies.

How does this benefit the team?

Options:

A.

It helps the team to focus on and meet sprint goals.

B.

It reminds the team about who sponsors the project.

C.

It provides high-level project updates to the sponsor.

D.

It helps to quickly resolve issues using the sponsor's influence.

Question 16

What can an agile practitioner conclude about team A and team B's estimates?

Options:

A.

Team B has underestimated scope compared to team A.

B.

Team A is more confident in delivering velocity than team B.

C.

Both teams need to indicate their proposed technology before the estimates can be analyzed.

D.

Both teams have estimated the project to be of same size.

Question 17

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders and this delays the decision-making process.

How should the scrum master proceed?

Options:

A.

Allow stakeholders to discuss without the scrum master's intervention.

B.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

C.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

D.

Organize training sessions to create awareness around the agile values for stakeholders.

Question 18

In several recent agile team status meetings, there have been discussions about increases in costly bugs and late product deliveries, resulting in lower quality and higher costs. Team members feel they spend too much time in planning and process meetings, then feel rushed to complete their work.

How should the agile lead implement an effective and efficient solution?

Options:

A.

Review the quality assurance and control processes with the team to ensure that even new team members understand the service level agreement (SLA) made with the customer.

B.

Suggest the team commit to a 2-month trial using Kanban. Focus on delivering value to the customer using pull criteria before advancing work. The team will have planning meetings as needed with no special meetings about the process.

C.

Hire a consultant team to perform a root cause analysis, which will determine the fundamental issues from both perspectives, then meet with the team to determine the best method to get the project back on track.

D.

Work with the team to create a spike story for the next iteration to investigate the issue. Create a plan to get the project back on track and present it at the next status meeting to gain stakeholder acceptance.

Question 19

During agile training, an aspiring scrum master with experience in predictive projects asks about the differences between the Kanban approach and the agile approach.

How should the agile trainer respond?

Options:

A.

The Kanban approach relies on storyboards.

B.

The Kanban approach focuses on adaptive, simultaneous workflows.

C.

There are no work-in-process limits in the Kanban approach.

D.

Kanban teams employ a pull system.

Question 20

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Options:

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.

B.

Send the team the latest version of the release plan so they can provide feedback.

C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.

D.

Ensure all iteration goals are fully developed at the beginning of the project.

E.

Refine the product backlog and identify the Minimum Viable Product

Question 21

An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.

What is the sponsor looking at?

Options:

A.

Project management plan

B.

Product backlog

C.

Gantt chart

D.

Product roadmap

Question 22

A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project.

Which action should the scrum master take?

Options:

A.

Share the information radiator.

B.

Email the latest release plan.

C.

Invite them to the next retrospective.

D.

Send the latest project report.

Question 23

An agile team is having difficulties in obtaining the participation of a true user to be a part of their team. In the absence of a true user, the development manager steps in to act as a proxy for the user.

What can the agile team do to improve value delivery in the absence of a true user?

Options:

A.

Improve the velocity of each iteration.

B.

Add a variety of skilled programmers and expert testers to the team.

C.

Reduce the length of each iteration.

D.

Add a variety of users, such as business analysts and domain experts, to the team.

Question 24

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.

What should have been done to avoid this?

Options:

A.

A comprehensive user story with all non-functional requirements should have been created

B.

Non-functional requirements should have been added to the acceptance criteria

C.

Non-functional requirements should have been added to the definition of done

D.

A team review of the scope of work should have been conducted

Question 25

During sprints, the development team members are frequently invited to various meetings to provide technical opinions, consuming the team's working time and causing compliance issues. Which action should the scrum master take to address this situation?

Options:

A.

Request additional resources to prevent compliance issues while still fostering a collaborative workplace.

B.

Escalate the concern to the product owner and request that they prioritize the development work.

C.

Designate a single team member to attend the meetings and establish a capacity buffer for each sprint.

D.

Reject all external meetings for the development team so they can fully focus on their sprint tasks.

Question 26

What is the first thing an agile development team should do when planning an iteration?

Options:

A.

Assign the tasks to one team member.

B.

Separate the stories into tasks.

C.

Estimate the stories' tasks.

D.

Help establish the next sprint's goal.

Question 27

A project manager noticed that a team member had been a consistently high performer until a few months ago. Recently, the team member seems distracted and is not performing well.

How should the project manager handle a review with the team member?

Options:

A.

Talk to the team member about project deliverables and how poor performance is unacceptable.

B.

Discuss performance with the team member on the project deliverables and provide constructive feedback.C Inform the learn member that this project is complex and consider moving them to another project

C.

Extend support to the team member as this is the first project in which the team member underperformed.

Question 28

Options:

A.

Add new security features to the backlog and prioritize.

B.

Execute a spike to research security features for the project.

C.

Ask questions to determine where and how the product owner wants to use the product.

D.

Ask questions to determine if the product owner can define the desired level of security.

Question 29

An agile leader has been assigned to a project that involves significant technical complexity. What should the agile leader do to set the project up for success?

Options:

A.

Address this impediment by obtaining suitable training for the team.

B.

Address the risks resulting from complexity within sprint zero.

C.

Facilitate team brainstorming of the risks resulting from complexity for the risk register.

D.

Motivate the team to try new technical approaches.

Question 30

During the advanced stages of implementing a complex design, an agile practitioner realizes that the architecture is not scalable for user requirements. The architect suggests a workaround that is minimally adequate but may cause some performance issues.

What should the agile practitioner do?

Options:

A.

Tell the team that this is unacceptable for the upcoming project.

B.

Implement the workaround since performance issues can be addressed in the next iteration.

C.

Calculate the cost of redoing the architecture and seek management approval.

D.

Brainstorm with the team to identify a solution.

Question 31

An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?

Options:

A.

Review the burndown chart to identify ways to increase efficiency.

B.

Chair a weekly team retrospective focusing on identifying areas for continuous improvement.

C.

Ask a senior manager to initiate a root-cause analysis.

D.

Identify team key performance indicators (KPIs) and create positive incentives when targetsare achieved.

Question 32

An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?

Options:

A.

Work with team members to resolve the issue.

B.

Escalate the issue to the product owner.

C.

Allow team members to resolve the issue.

D.

Escalate the issue to senior management.

Question 33

What should the team have done to improve retrospective outcomes?

Options:

A.

Invited subject matter experts (SMEs)

B.

Conducted problem detection to determine root causes

C.

Measured and reported the outcome of improvement actions to the team

D.

Kept track of all current issues in a log and then reviewed their progress at the end of every iteration

Question 34

An agile team is building a training safety video based on current government regulations. The agile coach knows the regulations are likely to change before the release date.

How should the agile coach address this change?

Options:

A.

Plan for the second release to include regulatory changes and new features.

B.

Hold off making changes during the current release because the regulatory changes cannot be planned for.

C.

Verify the team is building the product in increments which can be adapted at the last minute if necessary.

D.

Monitor regulatory discussions to get a head start on the upcoming regulatory changes.

Question 35

A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time.

What should the product owner do?

Options:

A.

Schedule regular meetings with the scrum team to write, groom, and size user stories

B.

Focus on stories based on the highest number of story points to first address those items with the highest value

C.

Seek regular input from project stakeholders, and reflect this input in the backlog’s priorities

D.

Schedule in-person monthly meetings with key stakeholders to review the project’s progress

Question 36

A new project has been approved and is critical for an organization. The project sponsor has a limited budget, and the deadline to have all requirements meet the definition of done (DoD) is short.

Which approach should the agile practitioner take to facilitate the project's success?

Options:

A.

Set up weekly calls with the key stakeholders to participate in iteration reviews and release decisions.

B.

Analyze the impacts of these constraints on the project followed by a report sent to the sponsor to anticipate any risk of delays.

C.

Set up a meeting with the client to review the scope and timelines to manage expectations.

D.

Encourage the team to build increments and ensure the customer provides early feedback for a minimum viable product.

Question 37

The team is derailed by a demand from a senior manager unrelated to the project. How does the agile coach help the team?

Options:

A.

By coaching the team to outperform previous velocity

B.

By coaching the team to adhere to expectations set by the scrum master

C.

By encouraging overestimation to increase velocity

D.

By advising the team to remain committed and focused on project goals

Question 38

What should the Scrum Master advise the team to do?

Options:

A.

Implement the story since the team is running behind schedule.

B.

Create a spike to finalize the story's technical approach.

C.

Transfer the story to a Scrum team experienced in solving similar problems.

D.

Ask the product owner to reduce the story's priority and wait until more technical details are available.

Question 39

What should the agile project manager do?

Options:

A.

Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.

B.

Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.

C.

Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.

D.

Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.

Question 40

Which of the following allows DevOps to enable and sustain a fast workflow from development into operations?

Options:

A.

A mindset shift to establish controls over all development and operations processes.

B.

Planned incremental iterations and a focus on people over processes.

C.

A culture of collaboration, tools, and processes to support continuous delivery.

D.

New tools that enable teams to continuously build, test, and integrate.

Question 41

DRAG DROP

All the developers on a project team are working offshore in a different time zone, resulting in many issues. Match the issues to the agile practitioner's recommendations for resolutions below. (Drag the Problems/Issues on the left to the box in the center, corresponding to the correct Recommendations for Resolution on the right)

Options:

Question 42

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?

Options:

A.

Lead time

B.

Team velocity

C.

Burndown rate

D.

Earned value (EV)

Question 43

An agile team had unexpected technical problems in a project and was not able to complete the deliverables on time. During the retrospective meeting, the team openly discussed the causes for these issues and what can be done to avoid similar situations in the future.

What agile values and principles did the team demonstrate?

Options:

A.

The team is being proactive by discussing how to better balance demands and capacity and make sure they have the right competencies.

B.

The team shows respect for one another by listening to everyone's opinions and valuing human interaction during face-to-face meetings.

C.

The team is providing one another with fast feedback to find those responsible for any mistakes so they can be avoided in the future.

D.

The team eliminates potential waste by discussing who should be responsible for future risk management by actively applying the pi an-do-check-act (PDCA) method.

Question 44

What should be proposed to the team?

Options:

A.

Have other team developers attend training to learn database skills.

B.

Monitor the retrospectives of two additional sprints before taking action.

C.

Plan fewer stories for the sprint to reduce the database engineers' workload.

D.

Ask the Scrum Master to work with the product owner to remove backlog stories that have database dependency.

Question 45

Options:

A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Question 46

The transition of a monthly news publication from paper to digital is planned to start in the next few weeks. There is a debate between the product owner and the development team about the initial features to be made available and the first five stages of implementation.

What should the scrum master do to address this situation?

Options:

A.

Request more clarification from the client relations team.

B.

Ask the team to define the minimum marketable feature

C.

Tell the team to proceed with coding the items as currently defined.

D.

Encourage open discussions to help the team reach agreement

Question 47

Two team members are working together to deliver an asset management tool. The code delivered by team member A during this sprint is not aligning with the specifications written by team member B. Both team members do not seem to agree on the look and feel of some functionality.

What should the Scrum Master do in this situation?

Options:

A.

Understand the root cause of this issue and recommend discussing their differences to find common ground.

B.

Hold a team meeting to discuss these issues and help direct the whole team on how to proceed further.

C.

Let the two team members resolve the conflict on their own.

D.

Ask their functional manager to intervene and resolve the issue.

Question 48

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

Options:

A.

Schedule a meeting to engage stakeholders to prepare for kickoff

B.

Schedule a meeting to agree to the goals for all future iterations.

C.

Guide the team to work collaboratively and share learnings.

D.

Organize a sprint planning meeting to define actions.

E.

Organize a meeting to outline roles and responsibilities.

Question 49

In a Scrum team, who should be responsible for the budget and release plans?

Options:

A.

The Scrum Master assigns someone on the team to handle the budget, and the Product Owner is responsible for release plans

B.

The finance department is responsible for the budget, and the Product Owner is responsible for release plans

C.

The Scrum team as a whole, as they are self-organizing and share accountability

D.

The Product Owner is responsible for both the budget and the release plans

Question 50

During a retrospective, a team member claims that a specific set of documentation that is continuously updated during iterations is not being used by any stakeholder.

What should the team do?

Options:

A.

Continue updating the documentation but initiate an analysis to identify its value and act on the findings.

B.

Stop updating the documentation since no one is using it.

C.

Continue updating the documentation since it is clearly required by the process.

D.

Stop updating the documentation and initiate an analysis to identify its value and act on the findings.

Question 51

What should the agile project leader do?

Options:

A.

Bring up the new member's impediments at the next meeting to demonstrate team support of input

B.

Assure the new member that inputs on impediments are valued and demonstrate this at the next meeting

C.

Have a senior lead work with the new member to avoid a negative impact on team productivity

D.

Privately work with the new member to address any impediments

Question 52

An employee just received an Agile certification and has been promoted to team leader. They are working on a project that is experiencing issues with late deliverables. After monitoring project progress, they notice that one impediment is continuously repeated at start of each phase, affecting team's productivity.

How should the team leader exhibit servant leadership?

Options:

A.

By being a change agent

B.

By being the authority on processes

C.

By being a coach

D.

By removing impediments

Question 53

A diverse team can sometimes create misunderstandings and conflict, leading team members to isolate. How can an agile project manager promote effective communication and collaboration among team members with diverse backgrounds and perspectives?

Options:

A.

Reduce emotions by emphasizing areas of agreement rather than areas of difference.

B.

Create a shared vision for the team and use techniques to increase empathy and positive interaction.

C.

Coach the team to focus on areas of agreement and the company's profitability.

D.

Confront the team and follow the formal procedures as described in the project management plan.

Question 54

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the Scrum Master do?

Options:

A.

Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule.

B.

Ask the team to find a workaround so that they can continue with the current project management plan.

C.

Advise the team to continue working on the sprints as the release plan has been set.

D.

Ask the team to estimate the amount of rework needed so that adjustments can be made to both the project and release plan.

Question 55

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

An agile team consisting of eight members is in their 11th iteration of a project. In the last iteration, the team was not able to complete every scope item it had committed to before the demonstration.

Which approach should the agile lead take?

Options:

A.

Coach the team to decompose the backlog activities to granular, simple tasks that are easier to estimate and complete.

B.

Evaluate the team's capacity and help them select user stories for the iteration based on 60% of their capacity utilization.

C.

Discuss options to add more people to the team so they can complete the tasks on time and within budget.

D.

Evaluate the team's capacity and help them select user stories for the iteration based on 80% of their capacity utilization.

Question 56

A project team held a working session with a finance team to understand the procurement process. After the meeting, while the agile lead was facilitating the value stream mapping exercise, one of the team members asked: "When calculating the cycle time, which factors should be considered?"

How should the agile lead respond?

Options:

A.

Total time and average process time

B.

Critical path and queue lengths

C.

Delays and bottlenecks in the process

D.

End date/time and start date/time

Question 57

A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing its teams.

What strategy should be employed to re-organize the teams?

Options:

A.

All the teams from both products should be simultaneously called together and allowed to completely self-manage

B.

Teams that worked on similar components in the separate products should be combined to minimize disruption and capitalize on synergies

C.

After grouping individuals by role, multi-discipline teams should be created that are comprised of one member from each role

D.

Features should be prioritized and then teams should be organized around those priorities

Question 58

Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched.

How should this situation be handled?

Options:

A.

The Agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.

B.

The Agile practitioner should inform the stakeholders that the UI has already been approved by the project team and sponsor, so the team is committed to staying the course.

C.

All stakeholders should go through the approved project charter and business requirements document to reduce the number of late changes or requests.

D.

The stakeholders should contact the project sponsor to get the project halted until new requirements are agreed upon.

Question 59

During a retrospective, the team agrees that they have limited competence in using a newly introduced tool. What should the team do?

Options:

A.

Explore options for increasing knowledge in the next iteration's backlog.

B.

Experiment with the tool's usage by adding extra tasks in the current iteration.

C.

Propose alternative tools that the team is more competent using.

D.

Ask a tool expert to join the team and perform the relevant work.

Question 60

Options:

A.

Small user stories

B.

Simple acceptance criteria

C.

Lean features

D.

Lean backlogs

Question 61

What should the product owner do?

Options:

A.

Determine the required tasks for implementing the high-level features

B.

Identify the detailed design for the high-level features

C.

Prioritize the product backlog for the upcoming release

D.

Estimate the user stories in the iteration backlog

Question 62

During sprint retrospectives, some team members are very vocal and tend to dominate the conversation, while others are more reserved and less likely to participate. What should the Scrum Master do?

Options:

A.

Encourage all team members to participate, and have them type their retrospective feedback into the agile lifecycle management tool.

B.

Ask more specific questions during the retrospectives.

C.

Use retrospective techniques, such as silent writing, clustering, and dot voting to field feedback prior to discussion by the team.

D.

Ask team members to email feedback that can be summarized in a spreadsheet for the team.

Question 63

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.

What should the Scrum Master do?

Options:

A.

Tell the technical lead to do the testing

B.

Facilitate an open and focused team discussion that reinforces team agreements

C.

Ask the team manager to advise the technical lead that all tasks are important

D.

Encourage the team to take ownership of the delivery

Question 64

To create the project vision, an agile team has scheduled an initial meeting with their customer representative. What should the team bring to this meeting?

Options:

A.

A list of templates to be used to create the project vision

B.

A list of project stakeholders and user stories

C.

A checklist for future acceptance tests for project deliverables

D.

A list of questions for the team and customer representative

Question 65

The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.

What should the team do next?

Options:

A.

Ask for a team extension so that an engineer with the needed experience can be added to the team.

B.

Suggest that the Product Owner perform the initial investigation and present the outcome to the team.

C.

Request that the Product Owner include a spike in the next iteration's backlog so they can perform an initial investigation.

D.

Propose alternative components with which the team has experience.

Question 66

Options:

A.

Keep sprints short.

B.

Invite the stakeholder to the daily stand-ups.

C.

Ask the stakeholder for estimates for each user story.

D.

Schedule more demos during each sprint.

Question 67

One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.

What should the agile practitioner do?

Options:

A.

Be transparent with all the stakeholders and make them aware of the issues encountered and the current project's status.

B.

Ensure the agile leader documents a risk in the risk register and communicates the risk to the project sponsor.

C.

Support the team's decision, and since the team is confident about being able to resolve the issues in time, do not raise the issues as risks with the stakeholders.

D.

Ask the product owner to make a decision as to whether or not all the stakeholders should be kept informed about the current project's status.

Question 68

An agile practitioner is in the process of refining requirements. The requirements keep changing based on with whom the agile practitioner speaks.

What should the agile practitioner do in this situation?

Options:

A.

Ask the Scrum Master to help reduce the rate of change.

B.

Work with the Agile Coach to document the requirements in a collaborative way.

C.

Work with the stakeholder directly rather than go through different layers of people.

D.

Work with the development team to confirm the requirements.

Question 69

Options:

A.

Networking

B.

Social awareness

C.

Communication

D.

Leadership

Question 70

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

Options:

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Question 71

A product owner is responsible for a new product. The internal customer questions using an agile approach because they need a product that works without any bugs or missing features once it is launched.

What should the product owner do?

Options:

A.

Plan regular retrospectives with the development team to continuously improve processes to eliminate any potential issues with the product.

B.

Apply an agile approach to write the specifications in an incremental way and develop the product once the final specifications are agreed upon.

C.

Set up test-driven development to focus on customer requirements and eliminate issues in the software as testing progresses,

D.

Ask the customer to provide additional representatives to help test and evaluate the product for early and frequent feedback.

Question 72

Options:

A.

Parametric

B.

One-to-one comparison

C.

Affinity

D.

Planning poker

Question 73

What should the project team do next?

Options:

A.

Estimate the project team's capacity.

B.

Determine how much work can be delivered.

C.

Calculate how much work will fit into the next iteration.

D.

Estimate items in the product backlog.

Question 74

A new software development team has just been formed. 5 sprints have passed and the team is now familiar with their way of working. In the 6th sprint, the scrum master notices the team members arguing about the technical design of an upcoming new feature during a backlog refinement meeting. After the refinement meeting, the scrum master notices team members talking about the topic informally and taking sides. There is noticeable tension among the team.

How should the scrum master help the team to resolve the issue?

Options:

A.

Bring a subject matter expert (SME) from the technology design team to act as a consultant for the team.

B.

Coach the team individually then the whole team during the Sprint review on how to resolve this conflict.

C.

Delegate the decision for the best feature implementation to the most senior team member.

D.

Decide on the technical implementation that best fits the purpose of the technical design.

Question 75

A team is preparing to demonstrate new product capabilities to a leadership team. The demonstration will show working software and a listing of the projected value of the capabilities.

What should the team do to ensure the demonstration is successful?

Options:

A.

Provide an understanding of business value and customer feedback.

B.

Align with stakeholder expectations and releasable product increments.

C.

Show self-management and tailoring processes for continuous improvement.

D.

Provide collaboration and knowledge sharing of product increments.

Question 76

How should the project team address this issue?

Options:

A.

Suggest pair programming during the retrospective.

B.

Ask the product owner to re-prioritize the user stories at the next retrospective.

C.

Re-estimate the story points with team members at the next iteration planning meeting.

D.

Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.

Question 77

During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.

What should the scrum master do?

Options:

A.

Ask the developers to keep their estimation so that the team is transparent with their level of understanding of work.

B.

Agree with the team to keep their estimation as the final number of story points will be the average of all team members.

C.

Propose to consider the estimations of only senior developers and have the junior developers learn from them.

D.

Encourage the team to keep their estimation as this will help surface different constraints and assumptions that others might have missed.

Question 78

A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.

What should the project lead do to help the team?

Options:

A.

Coordinate a collaboration session so all the team members are involved in the solution process.

B.

Plan a minimum viable product (MVP) in collaboration with the product owner to reduce technical complexity and move issues to the next release.

C.

Provide training for all team members to enable higher technical skills and the ability to resolve complex issues.

D.

Hire external consultants to advise on solution options and train team members in any technical gaps.

Question 79

What should the agile project leader do?

Options:

A.

Re-estimate the project.

B.

Finish the product as it was initially planned.

C.

Try to include as many changes as possible.

D.

Ask the product owner for approval to proceed.

Question 80

During planning, a project team and sponsor created a visual representation of the high-level specifications of the features and user stories to be implemented in a product. Consensus was achieved on this high-level depiction of the product characteristics, but the sponsor is having difficulty understanding what to develop and when.

How should the project manager explain this to the customer and save time in the meeting?

Options:

A.

Team performance and velocity can be determined only after the project has started

B.

Point out the Walking Skeleton and highlight the basic features that provide value.

C.

Create a kanban board for visualizing the work in process (WIP) and future development.

D.

High-level release planning is part of iteration 0 and works as a proof of concept

Question 81

Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.

What should the agile coach do?

Options:

A.

Incorporate quality assurance in the planning stage of product development.

B.

Schedule a dedicated meeting with the product owner to tackle this roadblock.

C.

Conduct a brainstorming exercise to get to the root of the issue and devise action plans.

D.

Conduct a retrospective meeting at the end of the current iteration to identity necessary improvements.

Question 82

A Product Owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog.

What should the Product Owner do next?

Options:

A.

Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting

B.

Reprioritize backlog items to future iterations

C.

Work with the team to deploy the first half of the backlog to ensure that value is realized

D.

Meet with project stakeholders to review the backlog and determine if the scope should be adjusted

Question 83

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.

Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

Options:

A.

Code is unit tested, code is peer reviewed, functional testing is passed, business testing is passed, and all acceptance criteria are met.

B.

Code is unit tested, all acceptance criteria are met, business testing passed, code is merged, code is peer reviewed, and documentation is updated.

C.

All acceptance criteria are met, documentation is updated, functional testing is passed, business testing is passed, and code is peer reviewed.

D.

Code is unit tested, all acceptance criteria are met, business testing is passed, functional testing is passed, code is merged, and documentation is updated.

Question 84

Why should an agile coach model agile principles and behaviors, become self-aware, and be present?

Options:

A.

To better listen, serve, and help the team grow their strengths individually and as a team

B.

To convince people what they need to do

C.

To help better disguise the command and control approach

D.

To understand team dynamics and develop a high performing team

Question 85

An agile team is struggling with an issue. A team member mentions that another team had a similar issue that was resolved, but lessons learned documents are unavailable.

What should the agile practitioner do?

Options:

A.

Suggest that all agile teams share weekly reports on their projects.

B.

Encourage the team to independently find a solution.

C.

Work with the team to create a solution for disseminating team knowledge throughout the company.

D.

Recommend hiring an external expert to advise on the best methods for sharing knowledge among teams.

Question 86

What is the risk of using Agile in a distributed team?

Options:

A.

Frequent integration of work produced

B.

Lack of shared knowledge of user stories

C.

Need for more locations to learn Agile

D.

Unclear team structure

Question 87

At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised.

How should this situation have been prevented?

Options:

A.

The team should have reviewed the definition of done prior to the iteration review.

B.

The testers should have ensured that test cases accurately reflected the product owner's expectations.

C.

The team should have conducted more demonstrations with the product owner during the iteration.

D.

The product owner should have provided clearer explanations during the planning meeting.

Question 88

An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.

What should the team do next?

Options:

A.

Run automated tests on the legacy functionality.

B.

Ask the customer to write tests that will be used to know when a story has been correctly developed.

C.

Start coding on the selected user stories to meet the requirements.

D.

Write tests that will be used to know when a story has been correctly developed.

Question 89

An agile project manager has noticed their teams declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Develop a reward system related to position and years of experience.

B.

Clarify project goals and project contract constraints.C Promote cross-training and —entering among tea— members

C.

Introduce performance standards and evaluation methods.

Question 90

An agile practitioner notices that a project is increasing open defect counts after every subsequent iteration.

What should the agile practitioner do?

Options:

A.

Create an issue on the backlog to investigate the root cause and assign a team resource to resolve the issue immediately.

B.

Request increased velocity from the development team to clear off some defects and stay on track with the current iteration's work.

C.

Ask the team to determine how to adapt to this increase in the next retrospective.

D.

Stop work on in-progress user stories to clear defects from the product owner and increase velocity on defect resolution.

Question 91

A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?

Options:

A.

Sort the stories in the backlog by descending story points and release the stories at the top of the list equal to the team's velocity.

B.

Prioritize the most valuable product features in the backlog first.

C.

Determine the features with the highest risk and release those first.

D.

Determine which features comprise the smallest feature set that could be successful in the market and establish viability of the product.

Question 92

During an interview for an agile team lead for a global company, a candidate is asked: "How do you ensure your project is aligned with the stakeholders' priorities?"

How should the candidate respond?

Options:

A.

Engage the change management team to determine prioritization of the backlog.

B.

Allow the stakeholders to decide on the priority and build the backlog.

C.

The entire team should discuss and prioritize the backlog factoring in stakeholder input.

D.

Only the agile team lead and team need to decide how to prioritize the project deliverables.

Question 93

During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance.

How should the agile practitioner handle the recommendation?

Options:

A.

Record the suggestion to be considered for future projects.

B.

Invite the team to evaluate the suggestion and measure the effectiveness of the implementation.

C.

Let the product owner consider the proposal and decide whether to adopt the suggested practice.

D.

Let the team's senior members decide whether to adopt the suggested practice.

Question 94

What should the agile team lead do?

Options:

A.

Ask the team to conduct research to find a viable solution.

B.

Select a better technology for team implementation.

C.

Obtain customer input on their technology requirements.

D.

Consult the product owner about their non-functional requirements.

Question 95

A scrum master is part of a team that has just agreed on the project scope and deliverables for a global, multilingual manufacturing company that has many staff members moving between locations. The team consists of 20 people and the budget is US$5 million. The kickoff meeting is scheduled for the following month.

What should the scrum master do as a first step?

Options:

A.

Organize a sprint planning meeting and include stakeholders.

B.

Invite the product owner to create a stakeholder map.

C.

Identify the key stakeholders at the earliest opportunity.

D.

Invite the key stakeholders to the kickoff meeting.

Question 96

During a project's last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.

What should the agile practitioner do?

Options:

A.

Inform the product owner's manager so that corrective action may be taken.

B.

Communicate this to the product owner, and offer to help facilitate discussions with the team.

C.

Encourage a team member to raise this during the retrospective to ensure that the product owner is aware.

D.

Escalate this issue to the sponsor so that corrective action may be taken.

Question 97

What should a Scrum Master do when one team member falls behind in their tasks?

Options:

A.

Move the task to another team member who has spare capacity in the sprint

B.

Ask the team for suggestions

C.

Privately offer the team member encouragement to meet task commitments

D.

Notify the product owner

Question 98

When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents.

How should the agile practitioner address this concern?

Options:

A.

Educate the QA manager that in agile quality is integrated from the beginning to end of the project

B.

Write backlog items that include QA as part of the description

C.

Ask for the current QA documents and incorporate them into the technical debt backlog

D.

Ask the product owner to write tests and QA controls into the acceptance criteria

Question 99

In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?

Options:

A.

"Inspect and adapt" are two of the three pillars in Scrum. The roles in Scrum are divided among the product owner, scrum master, and development team in a way that makes it possible to inspect the efficiency and adapt the way responsibilities are shared to maximize efficiency if needed.

B.

Scrum is a collaboration framework that encourages the Scrum team - the product owner, scrum master, and development team - to collaborate in a way that fosters fast value creation with respect for each team member's opinions and individual preferences.

C.

The product owner is responsible for the product backlog and long-term plans, the scrum master is responsible for the Scrum process, and the development team is responsible for the sprint backlog and progress toward the sprint goal. This facilitates clear accountability and effective value creation.

D.

The product owner is responsible for the product and sprint backlog. The scrum master follows up on progress, and the development team estimates and decomposes the backlog items into manageable pieces. This ensures each person has the roles they are best at and feel most comfortable with.

Question 100

Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?

Options:

A.

Ensure the teams are working together daily throughout the product development and are keeping the team's progress up to date.

B.

Ensure there is an environment where team members feel comfortable sharing their ideas, concerns, and feedback.

C.

Ensure the customer is provided with regular project status updates and that the meeting minutes are well documented.

D.

Ensure the team is able to release new features and updates frequently so that customers can see the product and provide feedback.

Question 101

A new Agile team is forming to address a high-priority project. Team members are dispersed over a wide geographic area. The Scrum Master and the team are currently defining their working agreement.

What should be part of the working agreement for a dispersed team?

Options:

A.

Identify support needed from external vendors to assist dispersed team members.

B.

Meet face to face at regular intervals to enhance shared understanding.

C.

Designate one person to communicate with all team members working at different locations.

D.

Define what project work can be done by dispersed team members.

Question 102

What should the agile practitioner do?

Options:

A.

Regularly circulate an updated, detailed version of the project plan

B.

Frequently update the online project management office (PMO) repository site

C.

Invite the stakeholders to daily stand-ups

D.

Post a project board in an area where all can view it

Question 103

An organization wants to increase value delivery in its agile projects.

What should the agile teams do?

Options:

A.

Perform analysis and development work, but no testing because that should be managed by another specialized team.

B.

Master available technology and tools to provide informative dashboards to the stakeholders.

C.

Work with product owners and turn product backlog items into potentially shippable product increments.

D.

Complete projects by their deadlines and share the budgets upfront with project sponsors.

Question 104

What should the practitioner do?

Options:

A.

Post and discuss rises in the burndown chart

B.

Adjust story points to account for technical debt

C.

Log technical debt as an impediment

D.

Add refactoring tasks to all stories

Question 105

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.

What should the team have done to avoid this?

Options:

A.

Escalated the issue to management

B.

Ensured the early engagement of key stakeholders

C.

Provided feedback to the architecture team to change the enterprise architecture standards

D.

Raised an exception for non-adherence to the enterprise architecture standards for this product

Question 106

A team retrospective was going well until the team lead introduced the "define the next experiment" topic; then the discussion became an argument. A new team member feels strongly that the approach used on their previous team would improve this team's efficiency and effectiveness. The team lead is adamant that they remain with the current approach and the discussion dissolves into a circular argument.

Options:

A.

Remind the group that all input is welcome but dissension is not productive and suggest the group move on to another task more agreeable to everyone.

B.

Restate both stances, ask for details of both approaches, and create a chart of similarities and differences.

C.

Construct an Ishikawa diagram for each approach, and use the 5 Whys technique to determine the effectiveness of each approach.

D.

Interject and request this experiment be postponed for 2 months, so the new team member has time to observe the current approach.

Question 107

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?

Options:

A.

Organize separate meetings with each individual team member.

B.

Create a safe environment for discussions during meetings.C Emphasize rules that need to be respected during meetings

C.

Allow team members to talk when they feel comfortable without any pressure.

Question 108

An agile team wants to collectively determine a project's size. What will the team be doing if they use the planning poker technique to accomplish this?

Options:

A.

Estimating story points by comparing them to similar, past features

B.

Estimating stories by placing them in buckets

C.

Using the number of dots for votes to estimate story points

D.

Estimating the relative size of stories by using story points

Question 109

What should the team do?

Options:

A.

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.

Invite the regional sales manager to the next iteration review to share the progress.

D.

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

Question 110

How could the project leader have avoided this?

Options:

A.

Led by example by encouraging the team to engage in consensus-driven decision making

B.

Iterated the need for agile teams to make quick decisions, then followed up with that team member

C.

Empowered a team member to facilitate decision making then made a final decision on behalf of the team

D.

Refrained from participating in the team's decision-making process, except to document and communicate results

Question 111

A senior manager has asked an agile team to ensure that the data for the burndown charts are updated in real-time. However, the team is not comfortable with this approach as they think this is not productive.

What should the scrum master do?

Options:

A.

Ask the product owner to manage and share the metrics with appropriate stakeholders.

B.

Meet with requestors to agree and align on reporting requirements.

C.

Deny the request and explain the team's stance to the stakeholders.

D.

Work with the team to create the metrics requested by the stakeholders.

Question 112

The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company’s steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.

What is the estimated project conclusion?

Options:

A.

Twelve months

B.

Three months

C.

Six months

D.

Two months

Question 113

Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?

Options:

A.

Just-in-time (JIT) refinement

B.

Stories to be released in each sprint

C.

Infrastructure updates

D.

Funding decisions

Question 114

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager.

What should the Scrum Master do?

Options:

A.

Dismiss the team member

B.

Discuss the situation with the functional manager

C.

Report the functional manager to the project sponsor

D.

Demand that the functional manager respect the project charter

Question 115

What should the agile practitioner do?

Options:

A.

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used

B.

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.

Propose to completely eliminate test automation, since this is a quality assurance function

D.

Suggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and reduce redundancy

Question 116

As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.

Which two actions should the scrum master take? (Choose two.)

Options:

A.

Proactively engage the resource managers to lead the team and provide the required support.

B.

Request the enterprise coach and human resources support the team with the transition.

C.

Document the pros and cons and review with stakeholders to determine the dependencies.

D.

Protect the team from disruptions and seek an exemption for status quo.

E.

Assess the impacts of the change and brainstorm potential solutions.

Question 117

As user stories are developed, what should be done to record and update acceptance criteria?

Options:

A.

Add more user stories.

B.

Use sprint retrospectives.

C.

Update current user stories.

D.

Update new tasks in the project plan.

Question 118

An agile coach is facing a dilemma: On one hand, there is a requirement that is vital and will consume all capacity of the team. On the other hand, there are some chore-related tasks that will improve the team's ability to produce results. The team insists on implementing these tasks since they will increase efficiency.

What should the agile coach do?

Options:

A.

Characterize chores as low priority since they do not add obvious value to the product

B.

Delegate chore-related tasks to another team.

C.

Escalate the issue to the shareholders/steering committee.

D.

Get the product owner and team to meet to prioritize the work.

Question 119

An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.

Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)

Options:

A.

Conduct thorough requirements analysis and validation.

B.

Allocate experienced developers and perform code reviews.

C.

Plan for sufficient support resources post-deployment.

D.

Develop comprehensive testing involving the quality assurance team.

Question 120

What should the agile practitioner do?

Options:

A.

Complete the test cases before creating the story in the backlog

B.

Define the detailed business requirements so that the team can continue with development

C.

Define the user stories with just enough detail so the team can collaborate continuously

D.

Ensure the acceptance criteria includes testing scenarios, so the team can do thorough testing

Question 121

The project lead of a newly created Agile project delivery team realizes that there are gaps in the knowledge of some team members. The lack of specific skills will add risk to the project delivery if the project becomes too dependent on specific resources for complete delivery.

What should the project lead do to address the gaps and develop a high-performing team?

Options:

A.

Ask each team member to document their solutions extensively in a knowledge repository for knowledge exchange between the team.

B.

Pair team members and ensure review of technical deliverables by partners in each sprint before integration of the solution.

C.

Create an environment of continued learning by providing opportunities for team members to develop their skills as generalized specialists.

D.

Replace the team members with highly qualified individuals that have experience in the specific technologies required for completing delivery.

Question 122

An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased. What should the agile practitioner do to get the team back on track?

Options:

A.

Escalate the issue to the project sponsor.

B.

Remove stories to increase velocity.

C.

Hold a stand-up to address the issue.

D.

Facilitate a team retrospective.

Question 123

During its first sprint, a new Scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories.

What should the team do?

Options:

A.

Cross-train some members in the automation framework to broaden their capacity with that skill

B.

Ask the product owner to add team members to boost this particular skill set

C.

Send a member to automation framework training when funds are available

D.

Avoid using test automation by swarming on the testing tasks and using manual testing

Question 124

What should the agile project manager have done to avoid this?

Options:

A.

Invited end customers to attend the stand-ups

B.

Organized design review sessions with the customer to obtain sign-off

C.

Held regular meetings with the product owner and project team to elicit detailed business requirements

D.

Conducted frequent review meetings with the customer to continually enhance delivery effectiveness

Question 125

A product owner adds user stories to the backlog on a daily basis. The stories are vague requests, and the product owner expects the details to be clarified once the team works on the prioritization list.

How should the team members address this challenge so that the prioritization meeting does not become a brainstorming session?

Options:

A.

Ask the product owners to invite a subject matter expert (SME) to the meeting so the prioritization meeting will be more effective.

B.

Ask the product owner to review their items with the product owner's teammates before adding user stories to the backlog.

C.

Ask the product owner to schedule a meeting with a subject matter expert (SME) to review items before adding user stories to the backlog.

D.

Ask the product owner to review the stories with the scrum master before the prioritization meeting takes place.

Question 126

A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.

Should the team add the feature's story points to their burndown chart?

Options:

A.

Yes because the story has been tested and accepted by the business as per the definition of done (Do

B.

Yes, because the development work is complete and quality assurance (QA) and release are external dependencies.

C.

No. any work that is not released cannot be considered complete as per the definition of done (Do

D.

No, because the product owner has not reviewed the release implementation checklist for potential issues.

Question 127

Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?

Options:

A.

Assign story B more than 8 story points to provide a better estimate

B.

Add points to story B’s iteration to account for the error but keep story B at 3 points

C.

Assign more resources to story B to bring it in line with the estimate

D.

Reestimate all stories including values for A, B, and C

Question 128

During a sprint review, the Product Owner identifies a required improvement for a feature’s user interface (UI) delivered during the sprint.

What should the Product Owner do next?

Options:

A.

Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer

B.

Create a user story for this new improvement and prioritize it for the next sprint

C.

Document it as a requirement creep

D.

Ask the team to take on additional story points to improve the UI

Question 129

An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?

Options:

A.

Include security concerns on the agenda for every meeting.

B.

Request that a security expert be added to the team.

C.

Add security as a non-functional requirement to the risk register, and review regularly.

D.

Ensure that planning and prioritizing includes consideration of security requirements.

Question 130

A user interface (UI) developer has features for channels ready for review. During the team review, the architect is disappointed that Splunk software has not been implemented for better server and client logs. The architect insists on the implementation of Splunk software, which will impact the release date.

Which one of the following is the ideal option for the team to resolve this conflict?

Options:

A.

Have the team brainstorm and propose error logging at the client level, which will have a higher impact with less effort within the release timeline.

B.

The product owner should explain to the architect that monitoring, alerting, and logging are not essential for the customer and can be prioritized post-release.

C.

Inform the sponsor that features are being added and will extend the release date after getting approval and communicating this to the architect.

D.

Ask the developer to build and let the testing be postponed until after the release, and inform the architect that the feature will be implemented.

Question 131

After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.

If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?

Options:

A.

Stakeholders should have regularly been engaged to obtain feedback and reduce the functionality risk.

B.

The team should have used the lean principle of delay, so that actual facts could be considered rather than assumptions and predictions.

C.

Interdependent teams should have been engaged using a collaborative approach to identify and leverage the best support.

D.

An owner should have been identified to obtain timely stakeholder feedback.

Question 132

A project manager was assigned to lead the development of a new application for a company. The application will be widely used by all company employees around the world. During the first meeting with key project stakeholders, the project manager was asked to find a way to determinate all possible types of users who may interact with the application that is going to be developed.

What should the project manager do next?

Options:

A.

Push it back due to the number of users and socialize the idea of developing a standard application and training session for all users.

B.

Identity and create personas that can help the team better understand the needs of the target user base.

C.

Build a minimum viable product (MVP), a standard application for all users, and release the new version (per users/areas).

D.

'Engage the human resources (HR) team to identify the key users and interview all of them accordingly.

Question 133

A scrum team is experiencing lengthy discussions leading to no concrete actions during their scrum events. The scrum master determines that these inefficient meetings are producing waste.

What should the scrum master do to make the meetings more efficient?

Options:

A.

Issue fixed agendas and a decision log for all scrum events to ensure that only relevant agenda points are discussed and decisions are appropriately captured.

B.

Remind the team of the purpose of each scrum event, and implement a policy that long conversations deviating from the scope of each event will be stopped.

C.

Ask the product owner to conduct these discussions in individual meetings with the team members.

D.

Remind the team that staying on topic during meetings is part of being a self-managing team.

Question 134

An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work.

What metrics should the team use to measure performance?

Options:

A.

Lead time, throughput, and due date performance

B.

Work in progress limits, Kanban board, and time boxes

C.

Work item types, sprint cadences, and defect classes

D.

Burndown charts, scatter diagrams, and throughput

Question 135

In an adaptive environment, project managers use their skills and expertise to help the team adapt to changing circumstances and deliver to their stakeholders. While some agile practitioners may argue that the role of a project manager is not needed in self-organizing teams, pragmatic agile practitioners and organizations recognize that project managers can add benefit in many situations. The key difference is that their roles and responsibilities may look somewhat different in an adaptive environment.

What are some of the practices a project manager can bring to an adaptive environment?

Options:

A.

Building a collaborative decision-making environment with key stakeholders, teams, and sponsors.

B.

Ownership of detailed project planning, user histories, retrospectives, showcases and metrics board

C.

Ensuring agile values and principles are adopted by all teams involved in delivery of the project.

D.

Developing the project charter, writing the project plan, and following the achievement of all milestones.

Question 136

When a team member encounters an issue in an agile environment, what should they do?

Options:

A.

Limit communication between the team members and the customer to prevent unnecessary anxiety

B.

Manage communication between all team members and the customer to promote effective and transparent collaboration

C.

Manage communication between a few team members and the customer so that they may convey information to other team members

D.

Facilitate one-on-one communication between team members to reduce conflict and inefficiencies

Question 137

When working on a new product, what should an agile team do to ensure alignment with external stakeholders?

Options:

A.

Hold a kick-off meeting to assign roles.

B.

Review the project vision statement.

C.

Ask the product owner for a detailed product-specification document.

D.

Work with the Scrum Master to ensure that agile principles are followed.

Question 138

In a planning meeting, the client does not have a clear understanding of the most beneficial features of a project, because there are too many stakeholders with different requirements.

How should the project manager approach this project?

Options:

A.

Define all requirements so value can be added by delivering a high-level plan at the initiation phase.

B.

Suggest the Product Owner prioritize the work items by feature to maximize value.

C.

Ask the customer to define the requirements of all stakeholders and select the most valuable features.

D.

Ensure the client has a clear idea about the features and end product before the project starts.

Question 139

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?

Options:

A.

Notify the product owner and begin resolution.

B.

Communicate the issue to the team in the next stand-up meeting.

C.

Immediately begin resolution, and communicate it to the team during the retrospective.

D.

Work on the next activity, and communicate it to the team during the retrospective.

Question 140

When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?

Options:

A.

Calculated planned percent complete (PPC)

B.

Many small minimally marketable features (MMFs)

C.

Story points rather than cost estimates

D.

Calculated earned value (EV)

Question 141

During a backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog.

What should the team do?

Options:

A.

Add this threshold requirement request as acceptance criteria in all impacted stories

B.

Create a spike story to analyze the impact of the threshold requirement on current stories

C.

Conduct design planning session to review the performance threshold requirement

D.

Identify the tasks for the new performance threshold requirement

Question 142

How can an agile team working on a new product ensure alignment with external stakeholders?

Options:

A.

Ask the product owner to provide a detailed product specification document

B.

Conduct story-mapping exercises to clarify deliverables and release priorities

C.

Hold a kick-off meeting to assign roles and responsibilities

D.

Work with the scrum master and stakeholders to ensure agile principles are followed

Question 143

Options:

A.

MoSCoW method

B.

Planning poker technique

C.

Weighted average calculation

D.

INVEST scale

Question 144

A project team identifies a number of technical challenges with features in the next sprint.

What should they do?

Options:

A.

Request direction from the technical manager

B.

Encourage the Product Owner to reallocate the features to another sprint

C.

Determine who is best qualified to address the challenges

D.

Ask the Product Owner to assign the tasks to the most appropriately skilled resources

Demo: 144 questions
Total 476 questions