Which of the following tools and techniques are utilized in the Close Project or Phase process?
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
Which Knowledge Areas include processes from the Closing Process Group?
The individual or group that provides resources and support for a project and is accountable for success is the:
Which of the following is an example of the simplest fixed-price contract?
During which process would you obtain stakeholders’ formal acceptance of the completed project scope?
Completion of the product scope is measured against the product:
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
Information collected on the status of project activities being performed to accomplish the project work is known as what?
What is the number of stakeholders, if the project has 28 potential communication channels?
Sensitivity analysis is typically displayed as a/an:
Which of the following choices is a contract closure tool or technique?
When is a project finished?
Which of the following characteristics are found in a functional organizational structure?
Those who enter into a contractual agreement to provide services necessary for a project are:
During which process would stakeholders provide formal acceptance of the completed project scope?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
What is a technique used in the performance reporting process?
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
In which Process Group are lessons learned documented?
An input to Close Project or Phase is:
Which tools or techniques are used during the Close Project or Phase process?
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
The person assigned by the performing organization to be responsible for achieving the project objectives is the:
The three processes of Project Cost Management are:
What is the term assigned to products or services having the same functional use but different technical characteristics?
An input of the Control Schedule process is the:
A project manager should document the escalation path for unresolved project risks in the:
A tool and technique used during the Perform Qualitative Risk Analysis process is:
The approaches, tools, and data sources that will be used to perform risk management on a project are determined by the:
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
Which is a communication method used in the Report Performance process?
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
Plan Schedule Management is a process in which Knowledge Area?
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
What is an objective of the Developing Project Team Process?
What quality control tool graphically represents how various elements of a system interrelate?
Which of the following are the components of the scope baseline?
Which of the following is an output of the Monitor and Control Project Work process?
The total of the planned value (PV) is also known as:
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Which enterprise environmental factors may influence Plan Schedule Management?
Which standard examines an enterprise’s project management process capabilities?
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
Which of the following is a tool or technique used in the Determine Budget process?
Projects are authorized by which of the following individuals?
Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
Perform Integrated Change Control is the process of:
One of the fundamental tenets of modern quality management states that quality is:
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
Quality and credibility of the qualitative risk analysis process requires that different levels of the risk’s probabilities and impacts be defined is the definition of what?
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
Which technique is used in Perform Quantitative Risk Analysis?
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
Who is responsible for reviewing change requests and approving or rejecting the change requests?
What is the name of a graphic display of project team members and their reporting relationships?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
Which tool and technique is used in Conduct Procurements?
Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?
A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?
Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and controlling project work?
To which process is work performance information an input?
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
Which of the following is an example of push communication?
Which tool or technique is effective in a project in which the deliverable is not a service or result?
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
The traditional organization chart structure that can be used to show positions and relationships in a graphic top-down format is called a:
Which of the following are documented directions to perform an activity that can reduce the probability of negative consequences associated with project risks?
Which of the following is a component of three-point estimates?
Which document describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results?
Issue change requests and adapt approved changes into the project’s scope, plans, and environment is an activity included in which of the following project management processes?
Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work days. What should be your concern?
What is the tool and technique used to request seller responses?
A risk may be graded into different priorities by which process?
What’s budget?
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
Tools and techniques used in Direct and Manage Project Work include:
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
The Plan Stakeholder Management process belongs to which Process Group?
Tools and techniques used for Plan Communications include the communication:
In the basic communication model, which term refers to the method that is used to convey the message?
When can pre-assignment of project team members occur?
Which tool or technique is an examination of industry and specific vendor capabilities?
One of the key benefits of the Plan Human Resource Management process is that it:
The following is a network diagram for a project.
The shortest non-critical path for the project is how many days in duration?
Which of the following is an output of Define Scope?
Which items are components of a project management plan?
Which provides the basic framework for managing a project?
Which of the following inputs is required for the WBS creation?
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
The following is a network diagram for a project.
The free float for Activity H is how many days?
Requirements documentation will typically contain at least:
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
Which of the following is contained within the communications management plan?
At which stage of the project should certain factors such as the unavailability of human resources due to constraint be considered?
What is the function of a Project Management Office (PMO)?
Which quality planning tools and techniques are used to visually identify logical groupings based on natural relationships?
Which of the following are three inputs to the risk register?
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?
Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Which document defines how a project is executed, monitored and controlled, and closed?
An input to the Create WBS process is a:
The following is a network diagram for a project.
The free float for Activity E is how many days?
Which type of managers do composite organizations involve?
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Which of the following is an input to the Perform Qualitative Risk Analysis process?
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
The purpose of developing a project scope management plan is to:
An input to the Collect Requirements process is the:
The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
Through whom do project managers accomplish work?
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
Which type of tool would be used for the quality planning activity?
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
The process of defining how the project scope will be validated and controlled is known as:
Which of the following processes are part of the Project Integration Management Knowledge Area?
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
Stakeholder management strategy is an output of:
Which project risk listed in the table below is most likely to occur?
What is one of the objectives of Project Risk Management?
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?
What causes replanning of the project scope?
Project Stakeholder Management focuses on:
Which of the following includes how requirements activities will be planned, tracked, and reported?
Which of the following documents allows the project manager to assess risks that may require near term action?