Question 1

Which of following is not a principal control for managing the tranches?

Options:

A.

Business Case

B.

Benefit Review

C.

Business Case

D.

Dependency management

Question 2

Which of the following will not be in Issue register?

Options:

A.

Date issue was raised

B.

Description of issue

C.

How issues will be identified, captured and assessed

D.

Categorization of issue

Question 3

Which of the following is Not a core element of successful communication?

Options:

A.

Stakeholder identification and analysis

B.

Message Clarity and consistency

C.

Feedback Collection system

D.

Identifying correct people to communicate

Question 4

Who approves Business Case?

Options:

A.

Sponsoring Group

B.

SRO

C.

Programme Manager

D.

BCM

Question 5

Who produces Business Case?

Options:

A.

Sponsoring Group

B.

SRO

C.

Programme Manager

D.

BCM

Question 6

Which of the following statements best defines 'transformational Flow'?

Options:

A.

Common factors of success derived from lessons learned in programmes that had both positive and negative results

B.

Allow organizations to put in place right leadership, delivery team, robust organization structures and controls

C.

Provides a route through lifecycle of a programme, from its conception through to delivering new capability

D.

Temporary flexible organization created to coordinate, direct and oversee implementation of set of related projects

Question 7

For a programme that focuses on Political and societal change which scenario will lead to lower probability of success?

Options:

A.

New legislation reacting to societal trends

B.

Change to current legislation

C.

Changes to public service delivery model

D.

Long term societal effects

Question 8

Which of the following defines an Emergent programme?

Options:

A.

Evolved from concurrent, individual projects with need to ensure compliance to organization strategy

B.

Must do programmes often due to result of an external event and aimed to avoid negative implications

C.

Translation of political priorities into a programme to refine and deliver desired changes

D.

Programme focused on transforming the way business functions

Question 9

Which of the following is a critical organizational element?

Options:

A.

Leading change

B.

Stakeholder engagement

C.

Quality management and assurance

D.

Delivery mechanisms for change

Question 10

Which of the following is not an Input to delivering the capability?

Options:

A.

Project outputs

B.

Project dossier

C.

Business Case

D.

Blueprint

Question 11

Which of following is correct about Benefits Management?

Options:

A.

Ensures programme does right things and is aligned with strategy

B.

Ensures programme is aware of positive and negative impact it might generate

C.

Is tightly aligned to transformational flow processes

D.

All of above

Question 12

When approval to proceed is given at the end of Defining a Programme, what does this mean?

Options:

A.

The approval authorizes the work of all projects in the first tranche of programme.

B.

The approval authorizes the SRO to proceed with the whole programme.

C.

The approval authorizes the start of the first project in the first tranche only.

D.

The approval only acknowledges that the documents developed so far are acceptable.

Question 13

In delivering the capability, who is responsible for aligning projects with benefits realization?

Options:

A.

BCM

B.

Programme Manager

C.

Both

D.

None

Question 14

Which is not a valid response for a threat?

Options:

A.

Avoid

B.

Enhance

C.

Accept

D.

Reduce

Question 15

At which transformational flow basic programme controls are established?

Options:

A.

Identifying the programme

B.

Defining the programme

C.

Managing the tranches

D.

None of above

Question 16

Where in the transformational flow would the Benefits Map normally be created?

Options:

A.

Identifying a Programme

B.

Defining a Programme

C.

Managing the Tranches

D.

Realizing the Benefits

Question 17

Which of following is output of 'Identifying the programme'?

Options:

A.

Programme Mandate

B.

Appointment of programme board and SRO

C.

Business Case

D.

Benefit profiles

Question 18

As the influence of a stakeholder increases, it is recommended that a 'higher' level of engagement is appropriate. Which of the following describes this increasing engagement?

Options:

A.

Keep informed, active consultation, maintain interest

B.

Active consultation, keep informed, maintain interest

C.

Keep informed, maintain interest, active consultation

D.

Maintain interest, active consultation, keep informed

Question 19

Which of following Best defines capital cost?

Options:

A.

Costs associated to roles for programme management

B.

Costs of activities associated in realizing the benefits

C.

Cost of BCM and change team

D.

Cost of fixed assets

Question 20

Which of following is a key attribute for a SRO?

Options:

A.

Good knowledge of project management approaches

B.

Should represent a relevant business area

C.

Have ongoing operational responsibilities

D.

Have access to and credibility with key stakeholders

Question 21

Which of following is input for 'managing the tranches'?

Options:

A.

Programme preparation plan

B.

Programme Brief

C.

Approval to proceed

D.

Assurance review reports

Question 22

In which document would you expect to find the levels of confidentiality to be applied in the programme?

Options:

A.

The Information Management Strategy

B.

The Quality Management Strategy

C.

The Resource Management Strategy

D.

The Benefits Management Strategy