Which of following is output of 'Defining the programme'?
Which of following is input for 'managing the tranches'?
Which of the following defines an Emergent programme?
Here are three statements about the programme justification for the Smart Meter Programme. In which document should the statements be recorded?

Which of the following is an Information Baseline?
The task of organizational realignment relies heavily on getting results from existing staff and enhancing skills. Here are items of information to be recorded in the stakeholder engagement and communications plan. Under which heading should they be recorded?

Which of the following statements best defines 'transformational Flow'?
Which of the following is kind of a vision led programme?
Which of below statements are false?
The Department of Utilities Oversight (DOUO) is the regulating body overseeing utility companies in the region. The regulator has advised UU that they are concerned there will be a lack of competition in the industry, once UU sales are increased. UU has contacted both the DOUO and other water companies in the region to work on identifying solutions that would be practical for everyone.
Is this an appropriate application of the 'collaborate across boundaries' principle, and why?
The programme is in the ‘plan progressive delivery' process. The programme manager has recommended that the funds for the HR Work should come from a different source to the funding for the project work.
During which activity is the SRO responsible for providing formal approval for this recommendation?
Which activity from the Smart Meter Programme should be delivered using a continual improvement approach?
The CFO has been appointed as the SRO for the Smart Meter Programme.
Is this appointment an appropriate application of the ‘organization’ theme, and why?
Which type of cost is associated in training, moving and supporting an operational unit?
For a programme that focuses on Political and societal change which scenario will lead to lower probability of success?
Which principle ensures creating a 'Vision'?
Which document has the as-is state of organization?
During the ‘plan progressive delivery’ process, it was decided that the call centre managers would hold a weekly meeting with all call centre staff to update them on progress and understand any concerns that they might have. This information was documented by the programme manager.
Which theme is being applied?
Which of following is correct about Benefits Management?
Which of the following statements is FALSE?
Which of the following is NOT set out by the Programme Brief?
POTI model is part of which governance theme?
Halfway through Tranche 2, North City local government announced a new incentive programme to support green initiatives that help residents reduce their carbon footprint. UU is applying for this funding, claiming that its water smart meters and leak detection systems qualify as eco-friendly mechanisms aligned to the new government scheme. The cost of the application process will be more than paid for if UU is approved as part of the incentive programme.
Is this an appropriate application of the justification' theme, and why?
Which of following is not responsibility of Programme Office?
At the end of Tranche 2, the programme office lead reported that the overall programme cost would exceed the current budget. The SRO has recommended to the sponsoring group that the programme budget be increased, to enable the programme to deliver the full target operating model, as originally planned.
Which theme is being applied to the ‘evaluate new information' process?
Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?

The following statement needs to be recorded:
"The vision statement will be developed and tested in a facilitated workshop with the senior officers from each department, before final approval by the CEO."
In which section of the programme strategy should this be recorded?
The programme is in the ‘deliver the capabilities’ process in Tranche 1. The Employment Contracts Project needs to identify the skills and qualifications for call centre staff. The Call Centre Manager is concerned that the delivery of the web-based portal, being delivered in Tranche 2, will affect the skills required. They are worried that this may lead to some considerable rework during Tranche 2.
Which role should be responsible for making sure that the Call Centre Manager’s concerns are properly managed?
Which of following Best defines capital cost?
Programme needs to create a working environment that is both robust and flexible enough to be able to cope with frequent and sometimes radical changes of boundary. Which programme management principle suggests this?
Which of the below is not a critical organizational element?
Where in the transformational flow would the Benefits Map normally be created?
In delivering the capability, who is responsible for aligning projects with benefits realization?
The project team working on the Training Project in Tranche 3 needs to understand the new processes and knowledge required by staff members to develop a coherent set of training materials. The project team also needs to know the skills and qualifications for each role, and any new processes. The project manager is concerned that some of the documentation provided is outdated and does not now reflect the current processes being developed.
Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?
Which one of below options is the delivery mechanism for 'stakeholder engagement'?
Which is not a valid response for a threat?
Which of the following is an influencer type of stakeholder?
Which of the following is NOT normally a characteristic of the Vision Statement?
Which of the following is an activity in Defining a Programme?