You are conducting a Stage 1 audit at an organisation that services refrigeration equipment for a large customer base. The scope of certification is “Provision of refrigeration equipment maintenance and repair services”. You are interviewing the Managing Director to learn more about the organisation and to explore how the requirements for policy, objectives, and risks and opportunities in ISO 9001 are addressed.
The Managing Director explains that they only use sub-contract refrigeration engineers and do not have any full-time refrigeration engineers, which helps to optimise overhead costs. The full-time staff employed are essentially a small team of office staff who process customer enquiries, schedule jobs and process invoices.
The Managing Director adds that the ISO 9001 requirements for competence of personnel extends to both sub-contract and full-time staff. He also states that the full-time staff are aware of the Quality Policy, objectives and plans to address risk and opportunities.
You ask if the sub-contract engineers have been informed of the Quality Policy, objectives and plans to address risks and opportunities, to which the Managing Director replies that this is not applicable as they only use sub-contractors who operate ISO 9001 certificated quality management systems. The documented information provided to the auditor confirms this.
Which clause in ISO 9001 is most likely not to have been fulfilled in this instance?
Scenario 6: Davis Clinic (DC) is an American medical center focused on integrated health care. Since its establishment DC was committed to providing qualitative services for its clients, which is the reason why the company decided to implement a quality management system (QMS) based on ISO 9001. After a year of having an active QMS in place, DC applied for a certification audit.
A team of five auditors, from a well-known certification body, was selected to conduct the audit. Eva was appointed as the audit team leader. After three days of auditing, the team gathered to review and examine their findings. They also discussed the audit findings with DC ' s top management and then drafted the audit conclusions.
In the closing meeting, which was held between the audit team and the top management of DC. Eva presented two nonconformities that were detected during the audit. Eva stated that the company did not retain documented information regarding its outsourced services for an analysis laboratory and regarding the conducted management reviews. During the closing meeting, the audit team required from DCs top management to come up with corrective action plans within two weeks. Although the top management did not agree with the audit findings, the audit team insisted that the auditee must submit corrective actions within the given time frame in order for the audit activities to continue.
Once the action plans were evaluated, the audit team began preparing the audit report. Eva required from the team to provide accurate descriptions of the audit findings and the audit conclusions. The report was then distributed to all the interested parties involved in the audit, including the certification body Based on the report, the certification body together with Eva, as the audit team leader, made the certification decision.
Based on the scenario above, answer the following question:
Why is it important to discuss the audit findings with DC’s top management prior to the closing meeting and the submission of the final audit report?
Below are four of the seven principles on which ISO 9000 series are based. Match a potential benefit to each of the quality management principles (QMP).

Which two of the following work documents are not required for audit planning by an auditor conducting a certification audit?
A person who provides specific knowledge or expertise to the audit team during the audit is known as a/an:
Knowledge and skills are requirements of the auditor ' s competence. Select two from the following topics of knowledge that apply to every member of an audit team auditing an ISO 9001 quality management system.
An audit team leader arrives at a printing organisation to carry out a Stage 2 audit for a certification body. At a meeting with the Quality Manager, she is told that they have won their biggest contract from a computer
manufacturer to print and compile computer documentation packages. They have leased the unit next door for space reasons but have never worked in this sector before. The Quality Manager wants the ISO 9001
certificate to cover the new contract.
Which one of the options is the correct response by the auditor?
At the end of a second-party audit, the audit team enters the meeting room to hold the closing meeting; only two people
are present and waiting for them: the Health and Safety supervisor and the administrative officer. Neither has participated in
the audit. However, the team had previously agreed with the auditee Quality Manager on two nonconformities identified
during the audit (NC1 and NC2).
They said:
Health and Safety supervisor: " Good evening. We are sorry to inform you that the general manager was involved in a
serious car accident, and the other two managers have had to leave urgently to attend to the emergency. "
Administration officer: " Our quality manager, before leaving, left a written message about ' NC2 ' . He declares that the
correction and corrective action have been already implemented and has attached some documents to the message as
evidence of these actions. Therefore, he expects that ' NC2 ' will not be included in the report. "
Which one of the following would be your preferred answer to the Quallty Manager ' s request?
You are preparing for interviews with two members of top management. Based on the information that you gathered about the organization, you conclude that it is the top management who takes all the important decisions and closely supervises and controls employees. Based on this, which management style is practiced in the organization?
You will perform a third-party initial audit of ABC, a car manufacturer located on the outskirts of São Paulo, Brazil.
ABC is a local branch of an American car manufacturer that wants to introduce a new model, the GX-1, into the Brazilian market. In your audit plan, you included a two-hour interview with the Production Engineering department to audit clause 8.3 of ISO 9001.
When you sent the audit plan to ABC for their review, ABC said, “There is no need for that interview because the design of the model GX-1 was made in the USA, and we did not participate in that process.”
Millions of cars have already been sold in the USA and the Far East with fantastic success.
Which one of these potential actions is acceptable?
Noitol is an organisation specialising in the design and production of e-learning training materials for the insurance market. During an ISO 9001 audit
of the development department, the auditor asks the Head of Development about the process used for validation of the final course design. She states that they usually ask customers to validate the product with volunteers. She says that the feedback received often leads to key improvements.
The auditor samples the design records for a recently completed course for the 247 Insurance organisation. Design verification was carried out but there was no validation report. The Head of Development advises that this customer required the product on an urgent basis, so the validation stage
was omitted. When asked, the Head estimates that this occurs about 50% of the time. She confirms that they always ask for feedback and often make changes. There is no record of feedback in the design file for the course.
The auditor raises a nonconformity against ISO 9001. Which one of the following options is the basis for the nonconformity?
You are carrying out an audit at a single-site organisation seeking certification to ISO 9001 for the first time. The organization manufactures cosmetics for major retailers.
You are interviewing the Manufacturing Manager (MM).
You: " I would like to begin by looking at the cleaning controls. "
MM: " We record the cleaning of the equipment at the end of every batch. This document details the minimum cleaning frequency and the procedures to follow for all areas and each item of equipment. The person who carries out the cleaning puts their initial on the document and records the time and date alongside. "
Narrative: You sample production records over 3-days and note down evidence of nonconformity as per the table below.


A small deaning services organisation is about to start work on a hospital dleaning contract for the local Health Trust. You, as auditor, are conducting a Stage 2 audit to ISO 9001 and review the contract with the Service Manager. The contract requires that a cleaning plan is produced. You: " How was the cleaning plan for the contract developed? " Service Manager: " We have a basic template that covers the materials, labour requirements and cleaning methods to be employed. Some of that is specified by the customer. " You: " How does the plan deal with locations like the intensive care wards and the operating theatres, which are included in the contract? " Service Manager: " The basic plan covers general wards, but we will do more frequent cleaning in those areas if the hospital requests it. " You: " Are you aware of the regulatory requirements for cleaning standards in hospitals? " Service Manager: " No. We depend on the hospital to look after that side of things in the contract. " You decide to raise a non-conformity against section 8.2.2.a.1 of ISO 9001. You decide to raise another non-conformity against section 8.2.4 of ISO 9001 when finding that the cleaning plan was amended without the agreement of the Health Trust. A different cleaning chemical was substituted to that specified in the contract. At the follow- up audit, the corrective action proposed was to " obtain a concession from the Health Trust for use of the new chemical. " Which one of the following options is the reason why you did not accept this action taken?
According to ISO 19011, what two activities take place during the conduct of a audit follow-up?
Who would be defined as a witness during a witness audit?
Choose two of the following options:
What does the application of the process approach in a QMS enable?
When should the certification body accept the audit?
You are a member of the audit team of a second-party audit of an organisation with 625 employees. The audit procedure recommends using sampling criteria which requires the review of the documented competence for 25 personnel. The audit team leader developed an audit plan allocating one hour to audit the Human Resources department (from 11:30 am to 12:30 pm). She told you that she could not allocate any additional time.
What would you do?
(A third-party audit has been planned at a single-site organisation. The audit team comprises one audit team leader, one auditor and one auditor who is undertaking his first third-party audit.
During the on-site audit, the auditor who is undertaking his first third-party audit shall...)
You are conducting an ISO 9001 audit of a Materials Recycling Facility (MRF). The organisation processes
waste plastics into raw materials for plastic bottle manufacturers. You reach the manual picking line where operators are removing contaminant materials from incoming products, such as plastic bags, plastic film and badly contaminated items that would compromise the recycling process. You interview the line supervisor.
You: " Why are these plastic items being rejected at this stage? "
Auditee: " They do not meet our processing standards. "
You: " What is the reason for that? "
Auditee: " These items are likely to damage the machinery down the line. They can also compromise our
quality standards. We need to protect our reputation for good quality output materials. "
You: " What happens to the rejected items? "
Auditee: " Some get melted down in another process later on and some are disposed of as waste products that cannot be recycled. "
You: " What happens to the waste products? "
Auditee: " I ' m not sure. I suppose they go to landfill. "
Which two. of the following actions would you take to investigate further?
In the context of a third-party audit, select the issue which is not expected to be included in the audit plan.
Scenario 7: POLKA is a car manufacturing company based in Stockholm, Sweden. The company has around 14,000 employees working in different sectors which help with the design, painting, assembling, and test drives of the final product. The company is widely known for its qualitative products and affordable prices. In order to retain their reputation, POLKA implemented a quality management system (QMS) based on ISO 9001.
Before applying for certification, the company decided to conduct an internal audit to check whether there are any nonconformities in their QMS and if the requirements of ISO 9001 are being fulfilled. The top management appointed Sean, the internal auditor, as the team leader of the internal audit team. Sean required from the top management to have unrestricted access to the employees and executives of POLKA and to the documented information. Furthermore, Sean required to establish a team with a large number of auditors, considering the size and the complexity of the organization. The top management of POLKA agreed with Sean ' s requirements.
The top management, in cooperation with Sean, assigned 10 more employees to the audit team. Following that. Sean planned the audit activities and assigned the roles and responsibilities to each auditor. They began by interviewing employees of different manufacturing departments to check whether they are aware of the process of the QMS implementation. While conducting these activities, one of the auditors asked Sean for permission to audit the department in which he worked on a daily basis, as he was very familiar with the processes of the department.
Along the way, the teams findings showed that the staff were trained, documented information was updated, and the QMS fulfilled the requirements of ISO 9001. The internal audit took three weeks to complete, and on the last week the audit team held a final meeting
The team shared their results and together drafted the audit report This report was submitted to the top management of the company. The report was maintained as documented information, and was available to the relevant interested parties.
Based on the scenario above, answer the following question:
Ten employees of POLKA were part of the audit team that conducted the internal audit. Is this acceptable?
During a third-party audit of a pharmaceutical organisation (CD9000) site of seven COVID-19 testing laboratories in various terminals at
a major international airport, you interview the CD 9000 ' s General Manager (GM), who was accompanied by Jack, the legal compliance
expert. Jack is acting as the guide in the absence of the Technical Manager due to him contracting COVID-19.
You: " What external and internal issues have been identified that could affect CD9000 and its quality management system? "
GM: " Jack guided us on this. We identified issues like probable competition of another laboratory organisation in the airport, legal
requirements on COVID-19 continuously changing, the shortage of competent laboratory analysists, the epidemic declining soon,
shortage of chemicals for the analysis. It was quite a good experience. "
You: " Did you document these issues? "
GM: " No. Jack said that ISO 9001 does not require us to document these issues. "
You: " How did you determine the risks associated with the issues and did you plan actions to address them? "
GM: " I am not sure. The Technical Manager is responsible for this process. Jack may be able to answer this question in his absence. "
Select two options for how you would respond to the General Manager ' s suggestion:
You are auditing an organisation that has been certified to ISO 9001 for 10 years. The organisation is a privately owned, multi-site car tyre fitting company. You are auditing one of the sites.
You have confirmed with the Workshop Supervisor that tyre batch numbers shall be recorded in the Work Schedule. You have sampled recent Work Schedule records and written the following in your audit notes:
No batch numbers for tyres fitted to customers’ cars were recorded in the Work Schedule for job numbers 1/5, 1/16, 2/2, 2/7, 3/2, 3/5, 3/7 and 3/9. 15 jobs completed over the past five days were sampled. The Workshop Supervisor and the Tyre Fitter were aware of this missing information in the records, but no action had been taken.
You decide to raise a non-conformity.

Match the process descriptions below to the process names:

Whistlekleen is a national dry cleaning and laundry company with 50 shops. You are conducting a surveillance audit of the Head Office and are sampling customer complaints. 80% of complaints originate from five shops in the same region. Most of these complaints
relate to customer laundry not being cleaned as customers require. The Quality Manager tells you that these are the oldest shops in the company. The cleaning equipment needs replacing but the company cannot afford it now. You learn that the shop managers were
told to dismiss most of the complaints because of the poor quality of the laundered materials.
On raising the matter with senior management, you are told that there are plans to replace the equipment in these shops over the next five years.
You raised a nonconformity against clause 8.5.1 of ISO 9001.
Based on the scenario, select the three options which best describe the evidence for raising such a nonconformity.
According to ISO 9000, what is quality?
A Health Trust has contracted with Servitup, a catering services company certified to ISO 9001, for one year. You, as auditor, are conducting the first surveillance audit at one site with the Deputy Catering Manager.
You find that two internal audits have been carried out in the first year by the Catering Manager. One of them indicates that complaints from patients are increasing in number, mainly due to food being served too cold. A pre-heated food trolley is sent to the wards from the kitchen. The Deputy Catering Manager comments that the trolley thermometer is often unreliable. Evidence of calibration of the thermometer cannot be produced.
Which four of the following actions could prevent the complaints from recurring?
The following actions need to be carried out during a third-party audit planning stage. Which two actions correspond to the individual(s) managing the audit program before the involvement of the audit team leader’
Which of the following subjects should an auditor discuss when communicating with the auditee’s top management?
(Select one option which defines the purpose of a second-party audit to ISO 9001.)
ABC is a fast food shop that receives orders by phone or the internet. The normal menu includes 15 different types of hamburgers; however, in the
last two days, due to a shortage of a special type of meat, they can only prepare six of the 15 varieties.
You are performing a third-party audit of ABC; you observed that the menu offering food on the website is still the normal one, with 15 different
hamburgers. During a 30-minute period, you observed several customers reluctantly accepting other than the hamburger they preferred. You decided
to raise the following nonconformity as follows:
" There is evidence that ABC has not reviewed the ability to provide customers the offered products " .
The restaurant manager does not accept the nonconformity. She says that ABC had an extensive training programme for all personnel, which you have already seen when auditing Human Resources. This shortage of some hamburgers cannot be considered a management system failure.
Which one would be your answer from the following options?
Select six of the activities that are specifically required by ISO 17021-1 as part third-party (Certification Body) surveillance audit processes.
You are leading a Stage 2 certification audit of a multi-site organisation and have received the audit schedule below;
Head Office and Site 1 - Day 1
Site 2 (150 Km from HQ) - Days 2 and 3
During Day 1 of the audit, the dient informs you that the laboratory at Site 2 has been dosed for decontamination due to a serious outbreak of an infectious disease among workers. In Site 2, all other functions could be audited as planned.
As the audit team leader, what would you do?
Choose the best acceptable action you could take:
® Ask the audit Programme Manager for direction.
Complete the audit on day 3 and report back to the certification body for a certification decision.
Continue the audit on days 2 and 3 and return later to audit the Site 2 laboratory.
Immediately cancel the audit since the audit plan cannot be completed.
Who has the responsibility for assigning work to the audit team?
For a third-party, match the Activity with the Responsibility for conducting it.

Scenario 5: Mechanical-Electro (ME) Audit Stages
Mechanical-Electro, better known as ME, is an American company that provides mechanical and electrical services in China. Their services range from air-conditioning systems, ventilation systems, plumbing, to installation of electrical equipment in automobile plants, electronic manufacturing facilities, and food processing plants.
Due to the fierce competition from local Chinese companies and failing to meet customer requirements, ME ' s revenue dropped significantly. In addition, customers ' trust and confidence in the company decreased, and the reputation of the company was damaged.
In light of these developments, the top management of ME decided to implement a quality management system (QMS) based on ISO 9001. After having an effective QMS in place for over a year, they applied for a certification audit.
A team of four auditors was appointed for the audit, including Li Na as the audit team leader. Initially, the audit team conducted a general review of ME ' s documents, including the quality policy, operational procedures, inventory lists, QMS scope, process documentation, training records, and previous audit reports.
Li Na stated that this would allow the team to maintain a systematic and structured approach to gathering documents for all audit stages. While reviewing the documented information, the team observed some minor issues but did not identify any major nonconformities. Therefore, Li Na claimed that it was not necessary to prepare a report or conduct a meeting with ME ' s representatives at that stage of the audit. She stated that all areas of concern would be discussed in the next phase of the audit.
Following the on-site activities and the opening meeting with ME ' s top management, the audit team structured an audit test plan to verify whether ME’s QMS conformed to Clause 8.2.1 (Customer Communication) of ISO 9001.
To do so, they gathered information through group interviews and sampling. Li Na conducted interviews with departmental managers in the first group and then with top management. In addition, she chose a sampling method that sufficiently represented customer complaints from both areas of ME ' s operations.
The team members were responsible for the sampling procedure. They selected a sample size of 4 out of 45 customer complaints received weekly for electrical services and 2 out of 10 complaints for mechanical services.
Afterward, the audit team evaluated the evidence against the audit criteria and generated the audit findings.
After reviewing the documented information, Li Na claimed that it was not necessary to report the minor nonconformities that were identified; instead, they would be discussed in the next audit phase. Is this acceptable?
You are conducting a third-party audit to ISO 9001 and the next item on your audit plan is ' internal auditing ' .
When reviewing a sample of audit records up to 5 years previously, you find that many contain non-conformance reports and no actions have been taken. You interview the Quality Manager.
You: " I have noted that many of the older files contain non-conformances that have not had any corrective action taken. "
Quality Manager: " Because the business is always changing, the departmental managers tell me that the non-conformances are no longer applicable. I made a decision that any non-conformance over 3 years old is automatically closed "
You: " Do you obtain any confirmation beforehand from the appropriate departments that the non-conformances are no longer applicable. "
Quality Manager: " No, because they are so old I consider that they are no longer appropriate. Please remember that we take a risk-based approach which means we audit where and when it is considered important to do so.
Select one course of action you would now take from the options.
Which two of the following roles do not contribute to the audit outcomes?
TIX provides services to the informatic equipment of large organisations. They operate an ISO 9001:2015 QMS that is being audited by an important
customer (second-party audit). During the audit, the audit team has identified two nonconformities. When preparing the Closing meeting, the audit
team discussed and agreed both nonconformities with TIX ' s quality manager. The Closing meeting was planned for 6pm with the general manager,
quality manager and service manager at the meeting room.
At 6pm, when the audit team enters the meeting room, only two people are present and waiting for them: the Health and Safety supervisor and the
warehouse supervisor. Neither have participated in the audit.
The dialogue among them is as follows:
Audit team leader: " Good evening, could you please inform the three managers that we are ready to start with the Closing meeting? "
Health and Safety supervisor: " Good evening. We are sorry to inform you that the general manager was involved in a serious car accident, and
the other two managers have had to leave urgently to attend the emergency. "
Warehouse supervisor: " They have asked us to listen to what you need to say and to sign whatever we need to sign. We also have a message
from them about the two nonconformities. They wanted us to ask you if you could contact them in a couple of days to determine how to proceed. "
Which one of the following options would be your preferred response to the final comment made by the warehouse manager?
During the opening meeting of a third-party audit of a pharmaceutical organisation (CD9000) with seven COVID-19 testing laboratories in various terminals at a major international airport, you are asked if you could
visit all laboratories. As audit team leader you say that, based on sampling criteria, you had planned to audit only three of them as CD9000 is a multisite organisation.
They tell you that they have worked so hard to get ready for the audit that the supervisors of those laboratories that would not be visited would be quite disappointed.
The following are possible responses to the request, select the two best responses:
Scenario 3:
Fin-Pro is a financial institution in Austria offering commercial banking, wealth management, and investment services. The company faced a significant loss of customers due to failing to improve service quality as they expanded.
To regain customer confidence, top management implemented a QMS based on ISO 9001. After a year, they contacted ACB, a local certification body, to pursue ISO 9001 certification.
The audit team was led by Emilia, an experienced lead auditor, and included three auditors. After an agreement was reached, ACB sent the audit objectives to the audit team.
The audit team began by gathering information about Fin-Pro’s understanding of ISO 9001 requirements. While reviewing documented information, they noticed missing records of training and awareness sessions. They conducted employee interviews to verify attendance.
The team also reviewed the organizational chart and job descriptions to confirm employee competence. They observed the company’s working environment (social, psychological, and physical conditions).
The audit team analyzed the evidence and prepared an audit report with findings and conclusions.
Which statement below represents the level of responsibility demonstrated by the audit team in scenario 3?
Select one of the options that best describes the purpose of conducting a document review:
You are carrying out an audit to ISO 9001 at an organisation which offers consultancy services on the implementation of ISO 9001 quality management systems to manufacturers of cosmetics.
You are interviewing the Technical and Quality Director (TQD), who manages a team of biochemists responsible for providing ISO 9001 consultancy services to customers.
You: “How do you ensure your team’s competence concerning regulatory and ISO 9001 requirements?”
TQD: “We subcontract a part-time lead consultant who has years of experience working as a biochemist in the cosmetics industry. She is responsible for ensuring the team’s competency.”
You: “Do they retain any documented information on the individual competency of each consultant?”
TQD: “No. The lead consultant is a dedicated individual with lots of contacts in the sector. We rely on her decision on the consultants’ competency. She says that she thought that it was not necessary to keep documented information; however, after the event two weeks ago, which could not be solved due to the lack of documentation, she may consider in the future to plan which information we may need to keep.”
You: “How does the organisation enable the consultants you employ to maintain updated their competence on ISO 9001 and regulatory requirements?”
TQD: “As I said before, we leave that up to the lead consultant. She tells us when we need to employ more young consultants and when changes are introduced in the applicable regulations. Our regular survey shows that customers are quite satisfied with our consultants; last year’s objective of customer satisfaction was achieved. We gave a salary increase to consultants when they knew that the objectives had been achieved.”
You decide to raise a non-conformity.
To complete the non-conformity report, click on the blank section you want to complete so it is highlighted in red and then click on the applicable text from the options below. Alternatively, drag and drop the options to the appropriate blank section.

You, as auditor, are in dialogue with the quality lead and managing director of a small business that supplies
specialist laboratory equipment and furniture.
You: " I ' d like to look at how you manage change in the organisation. What changes have you made as a
business, say, over the last 12 months? "
Auditee: " We have made some strategic changes, the main one being that we no longer manufacture our
own products in house. "
You: " That sounds like quite a significant change. What has been the impact of that? "
Auditee: " We now mainly sell other manufacturers ' products, under their brand names, and have outsourced
manufacture of our own brand products to one of our suppliers. Unfortunately, we had to make six members
of our staff redundant. This represents about 20% of our workforce, so this has been quite a challenging
time. "
You: " I ' m sure. What were the reasons for making the change? "
Auditee: " Our manufacturing section was a small operation, and we struggled to cope with fluctuations in
demand. During busy periods, we found it hard to meet lead times, and in quiet periods we had staff with
little to do. This was having an impact on customer satisfaction and meant we had to charge premium prices
that made our product uncompetitive. "
You: " How did you go about the change? "
In relation to the auditor ' s question about how the change was managed, the auditee mentions the steps
listed below. Match the ISO 9001 clauses to the steps.
To complete the table, click on the blank section you want to complete so it is highlighted in red and then
click on the ISO 9001 clauses listed below. Alternatively, drag and drop each clause to show which step the
requirement applies to.

You, as auditor, are in dialogue with the quality lead and managing director of a small business that supplies specialist laboratory equipment and furniture.
You: “I’d like to look at how you manage change in the organisation. What changes have you made as a business, say, over the last 12 months?”
Auditee: “We have made some strategic changes, the main one being that we no longer manufacture our own products in-house.”
You: “That sounds like quite a significant change. What has been the impact of that?”
Auditee: “We now mainly sell other manufacturers’ products, under their brand names, and have outsourced the manufacture of our own brand products to one of our suppliers.”
You: “What were the reasons for making the change?”
Auditee: “Our manufacturing section was a small operation, and we struggled to cope with fluctuations in demand. During busy periods, we found it hard to meet lead times, and in quiet periods, we had staff with little to do. This was having an impact on customer satisfaction, and meant we had to charge premium prices that made our product uncompetitive.”
You: “How did you go about the change?”
In relation to the auditor’s question about how the change was managed, the auditee mentions the steps listed below. The steps represent different elements of the Plan/Do/Check/Act cycle.
Select three steps which apply to the ‘check’ element of the cycle.
Even though past audits have highlighted a consistently large number of nonconformities within an organisation ' s design team, the organisation has not varied the frequency or duration of audits on its audit plan.
The decision for whether this situation is acceptable or not should be governed by which of the following?
A small cleaning services organisation is about to start work on a hospital cleaning contract for the local Health Trust. You,
as auditor, are conducting a Stage 2 audit to ISO 9001 and review the contract with the Service Manager. The contract
requires that a cleaning plan is produced.
You: " How was the cleaning plan for the contract developed? "
Service Manager: " We have a basic template that covers the materials, labour requirements and cleaning methods to be
employed. Some of that is specified by the customer. "
You: " How does the plan deal with locations like the intensive care wards and the operating theatres, which are included
in the contract? "
Service Manager: " The basic plan covers general wards, but we will do more frequent cleaning in those areas if the
hospital requests it. "
You: " Are you aware of the regulatory requirements for cleaning standards in hospitals? "
Service Manager: " No. We depend on the hospital to look after that side of things in the contract. "
You decide to raise a non-conformity against section 8.2.2.a.1 of ISO 9001.
You decide to raise another non-conformity against section 8.2.4 of ISO 9001 when finding that the
cleaning plan was amended without the agreement of the Health Trust. A different cleaning chemical was
substituted to that specified in the contract. At the follow-up audit, the corrective action proposed was to
" obtain a concession from the Health Trust for use of the new chemical. "
Which one of the following options is the reason why you did not accept this action taken?
In the context of a second-party audit, match the activity with the party responsible for conducting it.
Scenario 4:
TD Advertising is a print management company based in Chicago. The company offers design services, digital printing, storage, and distribution. As TD expanded, its management recognized that success depended on adopting new technologies and improving quality.
To ensure customer satisfaction and quality improvement, the company decided to pursue ISO 9001 certification.
After implementing the QMS, TD hired a well-known certification body for an audit. Anne Key was appointed as the audit team leader. She received a document listing the audit team members, audit scope, criteria, duration, and audit engagement limits.
Anne reviewed the document and approved the audit mandate. The certification body and TD’s top management signed the certification agreement.
Before contacting TD, Anne reviewed the audit scope and noticed that TD made changes to it due to the adoption of new printing equipment. However, Anne disagreed with the changes, stating they would affect the audit timeline. She considered withdrawing from the audit.
Based on scenario 4, conducting which of the activities below is NOT the responsibility of Anne?
During a second-party audit of a fruit grower (apples, pears, peaches) by a potential customer complying with ISO 9001:2015, the auditor verifies that there is a large variability in the quality of fruit production. In the last two years, they have noticed an increasing variability in daily production quality. The auditor found a trend of delivered produce showing signs of bruising and over-ripening, which led to an increasing number of customer complaints.
This process has been in operation for decades. The business was founded by the grandfather of the current owners, who did not want to alter the established practices.
The auditor raises a non-conformity against ISO 9001.
Which one of the following options would be acceptable as corrective action by the auditee?
Which of the following is a responsibility of a guide in an audit?
You are conducting a third-party Stage 1 audit at ABC Ltd, a single-site organisation that manufactures wooden furniture. You interview the Technical Director to learn more about the organisation. The Technical Director explains that they have had a successful year and that obtaining ISO 9001 certification will support the further growth of the business. You ask for an overview of the organisation ' s structure and its interrelationships with external interested parties.
The Technical Director shows you a document detailing all business processes and interrelationships. You notice in this document that another organisation called Teak Ltd manufactures wooden furniture on behalf of ABC Ltd. The Technical Director confirms this capability has been accounted for in the scope of the quality management system. You learn that the furniture manufactured by Teak Ltd has accounted for 40% of the sales revenue over the previous 12 months.
Which two of the following options best describe how you would plan the audit of the interrelationship with Teak Ltd during the Stage 2 audit at ABC Ltd?
Scenario 6: Davis Clinic (DC) is an American medical center focused on integrated health care. Since its establishment DC was committed to providing qualitative services for its clients, which is the reason why the company decided to implement a quality management system (QMS) based on ISO 9001. After a year of having an active QMS in place, DC applied for a certification audit.
A team of five auditors, from a well-known certification body, was selected to conduct the audit. Eva was appointed as the audit team leader. After three days of auditing, the team gathered to review and examine their findings. They also discussed the audit findings with DC ' s top management and then drafted the audit conclusions.
In the closing meeting, which was held between the audit team and the top management of DC. Eva presented two nonconformities that were detected during the audit. Eva stated that the company did not retain documented information regarding its outsourced services for an analysis laboratory and regarding the conducted management reviews. During the closing meeting, the audit team required from DCs top management to come up with corrective action plans within two weeks. Although the top management did not agree with the audit findings, the audit team insisted that the auditee must submit corrective actions within the given time frame in order for the audit activities to continue.
Once the action plans were evaluated, the audit team began preparing the audit report. Eva required from the team to provide accurate descriptions of the audit findings and the audit conclusions. The report was then distributed to all the interested parties involved in the audit, including the certification body Based on the report, the certification body together with Eva, as the audit team leader, made the certification decision.
Based on the scenario above, answer the following question:
The audit team delayed audit activities until DC’s top management submitted their action plans. Is this acceptable?
(In the context of a third-party certification audit, please identify the four management responsibilities of the audit team leader in managing the audit and the audit team:)
Select one option that must be considered when determining the scope of a QMS to ISO 9001.
In the context of a third-party certification audit, it is very important to have effective communication. Which is not the responsibility of the audit team leader?
State the correct sequence of events in the certification process for an organisation to obtain third-party accredited certification to ISO 9001.

Scenario 5: Mechanical-Electro (ME) Audit Stages
Mechanical-Electro, better known as ME, is an American company that provides mechanical and electrical services in China. Their services range from air-conditioning systems, ventilation systems, plumbing, to installation of electrical equipment in automobile plants, electronic manufacturing facilities, and food processing plants.
Due to the fierce competition from local Chinese companies and failing to meet customer requirements, ME ' s revenue dropped significantly. In addition, customers ' trust and confidence in the company decreased, and the reputation of the company was damaged.
In light of these developments, the top management of ME decided to implement a quality management system (QMS) based on ISO 9001. After having an effective QMS in place for over a year, they applied for a certification audit.
A team of four auditors was appointed for the audit, including Li Na as the audit team leader. Initially, the audit team conducted a general review of ME ' s documents, including the quality policy, operational procedures, inventory lists, QMS scope, process documentation, training records, and previous audit reports.
Li Na stated that this would allow the team to maintain a systematic and structured approach to gathering documents for all audit stages. While reviewing the documented information, the team observed some minor issues but did not identify any major nonconformities. Therefore, Li Na claimed that it was not necessary to prepare a report or conduct a meeting with ME ' s representatives at that stage of the audit. She stated that all areas of concern would be discussed in the next phase of the audit.
Following the on-site activities and the opening meeting with ME ' s top management, the audit team structured an audit test plan to verify whether ME’s QMS conformed to Clause 8.2.1 (Customer Communication) of ISO 9001.
To do so, they gathered information through group interviews and sampling. Li Na conducted interviews with departmental managers in the first group and then with top management. In addition, she chose a sampling method that sufficiently represented customer complaints from both areas of ME ' s operations.
The team members were responsible for the sampling procedure. They selected a sample size of 4 out of 45 customer complaints received weekly for electrical services and 2 out of 10 complaints for mechanical services.
Afterward, the audit team evaluated the evidence against the audit criteria and generated the audit findings.
According to general principles of sampling procedure, did the audit team select a valid sample for electrical services?
Select the two activities which pertain to Third-Party Audit.
During a Stage 1 audit, the Quality Manager asks that the audit includes coverage of a new work area they have expanded into since the application was made.
Which of the following two actions should the auditor take?
Confidence in the audit process and its ability to achieve its objectives depends on the competence of those involved in performing audits:
According to ISO 19011, select the two participants who need to be competent in performing audits.
How can an organization ensure the objectivity and impartiality of the internal audit function?
Scenario 6: Davis Clinic (DC) is an American medical center focused on integrated health care. Since its establishment DC was committed to providing qualitative services for its clients, which is the reason why the company decided to implement a quality management system (QMS) based on ISO 9001. After a year of having an active QMS in place, DC applied for a certification audit.
A team of five auditors, from a well-known certification body, was selected to conduct the audit. Eva was appointed as the audit team leader. After three days of auditing, the team gathered to review and examine their findings. They also discussed the audit findings with DC ' s top management and then drafted the audit conclusions.
In the closing meeting, which was held between the audit team and the top management of DC. Eva presented two nonconformities that were detected during the audit. Eva stated that the company did not retain documented information regarding its outsourced services for an analysis laboratory and regarding the conducted management reviews. During the closing meeting, the audit team required from DCs top management to come up with corrective action plans within two weeks. Although the top management did not agree with the audit findings, the audit team insisted that the auditee must submit corrective actions within the given time frame in order for the audit activities to continue.
Once the action plans were evaluated, the audit team began preparing the audit report. Eva required from the team to provide accurate descriptions of the audit findings and the audit conclusions. The report was then distributed to all the interested parties involved in the audit, including the certification body Based on the report, the certification body together with Eva, as the audit team leader, made the certification decision.
Based on the scenario above, answer the following question:
Scenario 6 indicates that although the top management did not agree with the audit findings, the audit team began preparing the audit report. Is this acceptable?
Scenario 4:
TD Advertising is a print management company based in Chicago. The company offers design services, digital printing, storage, and distribution. As TD expanded, its management recognized that success depended on adopting new technologies and improving quality.
To ensure customer satisfaction and quality improvement, the company decided to pursue ISO 9001 certification.
After implementing the QMS, TD hired a well-known certification body for an audit. Anne Key was appointed as the audit team leader. She received a document listing the audit team members, audit scope, criteria, duration, and audit engagement limits.
Anne reviewed the document and approved the audit mandate. The certification body and TD’s top management signed the certification agreement.
Before contacting TD, Anne reviewed the audit scope and noticed that TD made changes to it due to the adoption of new printing equipment. However, Anne disagreed with the changes, stating they would affect the audit timeline. She considered withdrawing from the audit.
How do you assess the situation presented in the last paragraph of scenario 4?
You are an auditor from a construction organisation who is conducting a second party audit to ISO 9001 at a steel rolling mill producing
structural steelwork. When auditing the rolling process, you find that the operator who is unloading the furnace does not use the
adjacent infrared pyrometer to measure the appropriate product temperature in readiness for the next production stage.
You: " How do you tell when the billet is ready for the rolling stage? "
Operator: " I ' ve done this job for 20 years. I can tell by the bright red colour. "
You: " What happens if the colour is wrong? "
Operator: " The billet goes back into the furnace. "
You: " Is the pyrometer ever used? "
Operator: " Only in borderline cases. "
You continue to interview the operator and find that around 25% of the billets are sent back to the furnace. This includes 80% of the borderline cases.
Select three options that would provide evidence of conformance with clause 9.1.1 of ISO 9001.
XYZ Corporation employs 100 people, and during a Stage 1 certification audit, certain issues are identified with the Quality Management System (QMS). Which two options describe the circumstances in which you could raise a nonconformity against Clause 6.2 of ISO 9001:2015?
An audit team leader arrives at a printing company to carry out a Stage 2 audit for a certification body. At a meeting with the Quality Manager, she is told that they have won their biggest contract from a computer manufacturer to print and compile computer documentation packages. The Quality Manager wants the ISO 9001 certificate to cover the new contract.
During the audit, a team member found that some print jobs had been rejected by several clients over some months due to spelling errors in the print run. The Print Manager blames the new employees they had to take on because of a big contract.
The auditor finds that the responsibility for checking spelling errors is placed on the printer that sets up the print run.
In line with the policy of the certification body, the audit team raise improvement opportunities in the audit report. Which
three of the following options would represent acceptable opportunities for improvement in the report?
In the context of a management system audit, identify the sequence of a typical process for collecting and verifying information. The first one has been done for you.
To complete the sequence click on the blank section you want to complete so it is highlighted in red and then click on the applicable text from the options below. Alternatively, drag and drop the options to the appropriate blank section.

A Health Trust has contracted with Servitup, a catering services organisation which has been certified to ISO 9001 for 1 year. It provides services to ten, small rural
hospitals in remote locations involving purchase and storage of dry goods and fresh produce, preparing meals and loading heated trolleys for ward service by hospital
staff. An auditor is conducting the first sole surveillance audit at one site with the Deputy Catering Manager (DCM).
At the closing meeting attended solely by the DCM, the auditor informs him that he has found numerous gaps in the QMS processes which lead him to consider
recommending suspension of the organisation ' s certification. He is particularly concerned with the evidence that patient health is being adversely affected by produce
stored beyond its safe consumption date, poor kitchen hygiene and undercooked meals. The DCM says that he cannot make any decisions about these issues in the
absence of the Catering Manager due to illness but will write everything down and report to the Catering Manager.
Which two actions should you take in the context of the audit?
Scenario 1: AL-TAX is a company located in California which provides financial and accounting services. The company manages the finances of 17 companies and now is seeking to expand their business even more The CEO of AL-TAX, Liam Durham, claims that the company seeks to provide top-notch services to their clients Recently, there were a number of new companies interested in the services provided by AL-TAX.
In order to fulfill the requirements of new clients and further improve quality, Liam discussed with other top management members the idea of implementing a quality management system (QMS) based on ISO 9001. During the discussion, one of the members of the top management claimed that the size of the company was not large enough to implement a QMS. In addition, another member claimed that a QMS is not applicable for the industry in which AL TAX operates. However, as the majority of the members voted for implementing the QMS. Liam initiated the project.
Initially, Liam hired an experienced consultant to help AL-TAX with the implementation of the QMS. They started by planning and developing processes and methods for the establishment of a QMS based on ISO 9001. Furthermore, they ensured that the quality policy is appropriate to the purpose and context of AL TAX and communicated to all employees. In addition, they also tried to follow a process that enables the company to ensure that its processes are adequately resourced and managed, and that improvement opportunities are determined.
During the implementation process, Liam and the consultant focused on determining the factors that could hinder their processes from achieving the planned results and implemented some preventive actions in order to avoid potential nonconformities Six months after the implementation of the QMS. AL-TAX conducted an internal audit. The results of the internal audit revealed that the QMS was not fulfilling all requirements of ISO 9001. A serious issue was that the QMS was not fulfilling the requirements of clause 5.1.2 Customer focus and had also not ensured clear and open communication channels with suppliers.
Throughout the next three years, the company worked on improving its QMS through the PDCA cycle in the respective areas. To assess the effectiveness of the intended actions while causing minimal disruptions, they tested changes that need to be made on a smaller scale. After taking necessary actions, AL-TAX decided to apply for certification against ISO 9001.
Based on the scenario above, answer the following question:
According to scenario 1, AL-TAX determined the factors that could hinder their processes from achieving the planned results and implemented preventive actions. This means they employed:
Which of the following is a principle of maintaining audit work documents?
Which one of the following options best describes the purpose of a Stage 1 third-party audit?
Scenario 2:
Bell is a Canadian food manufacturing company that operates globally. Their main products include nuts, dried fruits, and confections. Bell has always prioritized product quality and has maintained a good reputation for many years. However, the company ' s production error rate increased significantly, leading to more customer complaints.
To increase efficiency and customer satisfaction, Bell implemented a Quality Management System (QMS) based on ISO 9001. The top management established a QMS implementation team comprising five middle managers from various departments, including Leslie, the quality manager.
Leslie was responsible for assigning responsibilities and authorities for QMS-related roles. He also suggested including a top management representative in the QMS team, but top management declined due to other priorities.
The team defined the QMS scope as:
" The scope of the QMS includes all activities related to food processing. "
Leslie established a quality policy and presented it to the team for review before top management approval. Top management also proposed a new strategy for handling customer complaints, requiring biweekly customer surveys to monitor customer perceptions.
The quality policy was established by Leslie and approved by top management. Is this acceptable? Please refer to scenario 2.
Which type of audit risk is the risk that a significant defect may occur in the QMS, although the organization has internal control mechanisms in place?
The following are stages of an audit, put them in the order they would be conducted.

Scenario 6: Davis Clinic (DC) is an American medical center focused on integrated health care. Since its establishment DC was committed to providing qualitative services for its clients, which is the reason why the company decided to implement a quality management system (QMS) based on ISO 9001. After a year of having an active QMS in place, DC applied for a certification audit.
A team of five auditors, from a well-known certification body, was selected to conduct the audit. Eva was appointed as the audit team leader. After three days of auditing, the team gathered to review and examine their findings. They also discussed the audit findings with DC ' s top management and then drafted the audit conclusions.
In the closing meeting, which was held between the audit team and the top management of DC. Eva presented two nonconformities that were detected during the audit. Eva stated that the company did not retain documented information regarding its outsourced services for an analysis laboratory and regarding the conducted management reviews. During the closing meeting, the audit team required from DCs top management to come up with corrective action plans within two weeks. Although the top management did not agree with the audit findings, the audit team insisted that the auditee must submit corrective actions within the given time frame in order for the audit activities to continue.
Once the action plans were evaluated, the audit team began preparing the audit report. Eva required from the team to provide accurate descriptions of the audit findings and the audit conclusions. The report was then distributed to all the interested parties involved in the audit, including the certification body Based on the report, the certification body together with Eva, as the audit team leader, made the certification decision.
Based on the scenario above, answer the following question:
According to Scenario 6, the audit team required DC’s top management to submit corrective action plans within two weeks. Is this action acceptable?
Whistiekleen is a national dry cleaning and laundry organisation with 50 shops. You are conducting a surveillance audit of the Head Office and are sampling customer complaints. You find that 80% of complaints originate from five shops in the same region. Most of these complaints relate to damage to customer laundry. The Quality Manager tells you that these are the oldest shops in the organisation. The deaning equipment needs replacing but the organisation cannot afford it now. You learn that the shop managers were told to dismiss most of the claims based on the poor quality of the laundered materials.
On raising the matter with senior management, you are told that there are plans to replace the equipment in these shops over the next five years.
Match the ISO 9001 Clauses to the statements.

At the end of a second-party audit, the audit team enters the meeting room to hold the closing meeting; only
two people are present and waiting for them: the Health and Safety supervisor and the Administrative Officer.
Neither has participated in the audit. However, the team had previously agreed with the auditee Quality
Manager on two nonconformities identified during the audit (NC1 and NC2).
They said:
Health and Safety Supervisor: " Good evening. We are sorry to inform you that the general manager was
involved in a serious car accident, and the other two managers have had to leave urgently to attend to the
emergency. "
The Administration Officer: " Concerning ' nonconformity 2 ' , the General Manager left a message asking us
to tell you that he does not accept it and requests you not to include it in the audit report. Here is a note in
which he explains why. "
Which one of the following would be your preferred answer (as team leader) to the General
Manager ' s request?
Which of the following is a record related to the audit program that should be managed and maintained?