Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

NCARB Project-Planning-Design ARE 5.0 Project Planning & Design (PPD) Exam Practice Test

ARE 5.0 Project Planning & Design (PPD) Questions and Answers

Question 1

Refer to the exhibit (table showing energy embodied and annual energy demand for Type L and Type H walls).

In the table, Type L wall is lightly insulated and Type H wall is heavily insulated. Approximately how many heating seasons would it take to recover the extra energy involved in selecting the Type H construction?

Options:

A.

One-third of a heating season

B.

Two-thirds of a heating season

C.

Two heating seasons

D.

Three heating seasons

Question 2

Which of the following is the most effective way to reduce noise in mechanical air delivery systems?

Options:

A.

Increase the size of the ductwork

B.

Provide exterior duct insulation

C.

Reduce the free area of the supply air grille

Question 3

Which exterior elements control daylighting? Check the three that apply.

Options:

A.

Roof overhangs

B.

Horizontal girt

C.

Horizontal louvers

D.

Spandrel panels

E.

Vertical louvers

F.

Parapet walls

Question 4

An architect is commissioned to design a lodge in a location where the water service is insufficient for a sprinkler system. The architect plans to maximize sight lines by using exposed columns and roof structure in the primary assembly space.

Which of the following systems meet these requirements? Check the three that apply.

Options:

A.

6" diameter steel columns with open web girders and joists

B.

12" diameter peeled log columns with glulam beams and 4" wood decking

C.

8" cast-in-place concrete columns and beams and 8" precast planks

D.

6" precast concrete columns, beams, and 8" precast concrete planks

E.

3" light gauge steel columns with 6" "z" purlins and 28 gauge corrugated metal decking

F.

6 x 6 cedar columns with 6" light gauge "z" purlins and fire retardant treated plywood decking

Question 5

Refer to the exhibit (urban commercial site sketch).

In the urban commercial site shown in the sketch, which is the most convenient location for a truck entrance and exit from the site?

Options:

A.

A

B.

B

C.

C

D.

D

Question 6

Which of the following are characteristics of heavy-timber construction? Check the four that apply.

Options:

A.

Fire resistance

B.

Suitability to create unusual layouts or irregular forms

C.

Susceptibility to differential shrinkage

D.

Relatively rapid on-site erection times

E.

Susceptibility to rot

F.

Presence of sapwood to prevent insect damage

Question 7

A new, sprinklered, mid-rise office building of Type II-A construction has a ground-level restaurant and offices above. The restaurant has an A-2 occupancy and the offices have a B occupancy. The architect needs to provide fire separation between the two occupancy types and select the most cost-efficient floor/ceiling assembly option.

Which one of the following assemblies is most appropriate?

Options:

A.

1-hour-rated assembly with 2 x 10 wood joists

B.

2-hour-rated assembly with lightweight precast concrete

C.

1-hour-rated assembly with open web steel joists @ 24" o.c.

Question 8

Refer to the exhibit (louvered sunscreen cantilevered with beam). Assume the cantilevered beam is weightless.

Which of the following is the moment diagram?

Options:

A.

A

B.

B

C.

C

D.

D

Question 9

The rehabilitation of a warehouse for a commercial occupancy has a heavy anticipated electrical distribution load and it is expected that the current of the electrical system will be expanded in the near future.

The least expensive and most flexible electrical distribution system would be comprised of which one of the following?

Options:

A.

Paralleled sets of aluminum wire in conduits

B.

Paralleled sets of copper wire in conduits

C.

Single large aluminum or copper conductor

D.

Aluminum or copper bus duct with tap boxes

Question 10

An architect's client is focused on lighting energy savings and daylighting design in a new 3,000 ft² commercial building addition to expand showroom and office square footage. The client requests reasonable daylighting measures in the design.

What should the architect recommend to the client?

Options:

A.

Isolate electric lighting for daylight-responsive control to within a single zone

B.

Provide for daylight-responsive control of electric lighting

C.

Limit ample access to daylight to the interior spaces only

D.

Increase sunlight in the vicinity of critical visual tasks

Question 11

In order to minimize stratification, in a forced-air heating system, which locations of supply and return grilles should be avoided?

Options:

A.

Low supply, high return

B.

High supply, low return

C.

Low supply, low return

D.

High supply, high return

Question 12

Refer to the exhibit (concrete rigid frame building with aluminum curtain wall system).

The drawing shows a proposed concrete rigid frame building enclosed in an aluminum curtain wall system. To save money, the contractor proposed to eliminate the curtain wall system and substitute steel stud framing, which is anchored between the columns and beams and covered with a stucco finish.

What is the most likely result of this substitution?

Options:

A.

Wind load on the stud framing will transfer directly to the concrete frame and overload it.

B.

The substitution will work and will save construction cost.

C.

The stucco will crack due to movement of the frames under lateral loading.

D.

Increased dead load of the stucco system will overload the frames.

Question 13

Which of the following roofing types is the most appropriate for installation during below-freezing weather conditions on a roof with less than a 2:12 slope?

Options:

A.

A cold-tar built-up roof

B.

A self-sealing shingle roof

C.

A ballasted EPDM roof

Question 14

Heavy steel columns and rigid connections between columns and beams

Vertical steel trusses in the external walls

Light steel columns and flexible connections between columns and beams

Vertical steel trusses in the internal walls

Which structural design concept minimizes the cost of steel structure needed to resist wind and earthquake loads in high-rise buildings?

Options:

A.

Heavy steel columns and rigid connections between columns and beams

B.

Vertical steel trusses in the external walls

C.

Light steel columns and flexible connections between columns and beams

D.

Vertical steel trusses in the internal walls

Question 15

A multistory warehouse is to be converted into a high-tech office building. The owners propose a variety of services and flexibility to tenants, including cable/internet, fiber optic communications, dish/satellite, and security systems.

In order to accommodate this broad array of electronic and communications services, the architect should recommend which of the following electrical and communications distribution systems?

Options:

A.

Poke-through system

B.

Cellular deck system

C.

Raised access floor system

D.

Flat cable wiring system

Question 16

A 100,000-square-foot distribution warehouse has roof drains around the perimeter.

Which combination of structure and roofing system insulation is most cost effective?

Options:

A.

Level rigid frame with tapered rigid insulation

B.

Sloped rigid frame with rigid insulation

C.

Level open web joists with tapered rigid insulation

D.

Sloped open web joists with rigid insulation

Question 17

An architect has just received client approval of the Schematic Design documents for a three-story, outpatient medical clinic. The clinic is located within a mixed-use development governed by

a City-approved Planned Development (PD) document. The medical clinic design utilizes standardized departmental layouts and includes outpatient clinics, as well as treatment spaces,

administrative spaces and public/lobby spaces.

The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza

must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop.

The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The

building entrance faces northwest, convenient to the parking but not visible from the highway.

The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would

include a second building (2 story, 80,000 BGSF) and/or a parking deck.

Other considerations for the project include:

    Protected tree requirements are defined in the PD document.

    Easy pedestrian access must be provided from Sycamore Boulevard.

    All required parking for the clinic must be accommodated on site.

    Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF).

    Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes.

    All service equipment needs to be screened; see PD document for restrictions.

    Signage opportunities are important to the client.

    Acoustical privacy is a concern of the healthcare system.

The following resources are available for your reference:

    Drawings, including a perspective, plans, and exterior elevations

    Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion)

    Exterior Material Cost Comparisons

    Planned Development Document

    IBC Excerpts, showing relevant code sections

    ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design

The client decides to build-out and lease the second floor shell space as a lunch cafe with cooking classes as an additional function in the evening.

Options:

A.

Required parking will be determined based on occupancy of the lunch cafe area.

B.

Required parking will be determined based on the occupancy of the cooking classroom area.

C.

Required parking will be determined based on the building area.

Question 18

During design development of a new motel, the owner receives a cost estimate which was higher than what they had budgeted for. The project descriptions are as follows:

• Number of units: Twenty

• Construction type: V-B

• Number of stories: Two

• Structural system: Light wood frame

• Mechanical system: Central air system

The client wants the architect to reduce the initial construction cost without sacrificing the potential return on investment.

Options:

A.

Change the number of stories to three.

B.

Change the central air system to individual through-the-wall units at each room.

C.

Change the scope to an eighteen-unit development.

D.

Change the structural system to a precast concrete system.

Question 19

A site has been engineered with a 1:20 grade.

Which of the following sidewalk designs would be the most cost-effective way to get from the top to the bottom and still be in compliance with the accessibility standards?

Options:

A.

Switchback ramps at 1:12 with a handrail

B.

Cutting diagonally across the slope at 1:10 with a handrail

C.

Cutting diagonally across the slope at 1:12 with no handrail

D.

At the same grade as the slope with no handrail

Question 20

A church congregation has hired an architect to help them determine the feasibility of converting a retail strip mall space into a new church. The space is 30' wide and 125' long and is in an interior location with tenants on both long sides. The client has requested the following:

Natural light into the central gathering space

Nursery space for young children

Church office space

Adequate restrooms

Visually appealing landscaping

Which of the following should the architect consider to help determine if the project can move forward? Check the three that apply.

Options:

A.

Analyze the existing building exits to determine their adequacy for the new use classification.

B.

Check the existing roof structure to determine potential locations for skylights.

C.

Investigate the existing water and sewer services to determine their adequacy for the new use classification.

D.

Conduct a demographic survey to determine the number of children to be served by the nursery.

E.

Conduct a demographic survey of church membership to determine the capacity of the new restrooms.

F.

Engage a landscaping consultant to determine visually appealing landscaping options.

Question 21

Which of the following strategies is most appropriate for a new shopping center to be constructed on a nearly flat site flowing into a municipal subsurface storm-drainage system that is at capacity during a 5-year storm?

Options:

A.

Extending the storm sewers to catch basins in all roads and drives in the development

B.

Grading roads, locating buildings, and sizing culverts to create retention basins

C.

Sectioning, sizing, and pitching drainage ways, culverts, and basins to reduce runoff time

D.

Conducting all site drainage along the curbs of service streets

Question 22

Click on the shading device illustration that most effectively reduces summer solar heat gain through a west-facing window in the Northern Hemisphere.

Options:

Question 23

An architect has just received client approval of the Schematic Design documents for a three-story, outpatient medical clinic. The clinic is located within a mixed-use development governed by

a City-approved Planned Development (PD) document. The medical clinic design utilizes standardized departmental layouts and includes outpatient clinics, as well as treatment spaces,

administrative spaces and public/lobby spaces.

The site needs to accommodate four different vehicular traffic flows: patient traffic, staff traffic, service and delivery traffic, and emergency services traffic. In addition, a pedestrian plaza

must connect to the mixed-use development sidewalks. The plaza must provide space for bicycle parking and will serve as the future bus stop.

The site design addresses several challenges related to building orientation. The southeast facade, with excellent visibility from the highway, is the location of all service equipment. The

building entrance faces northwest, convenient to the parking but not visible from the highway.

The client believes future patient volumes will outgrow the clinic. The PD document allows for a planned Phase 2 development on the adjacent vacant site to the southwest. Phase 2 would

include a second building (2 story, 80,000 BGSF) and/or a parking deck.

Other considerations for the project include:

    Protected tree requirements are defined in the PD document.

    Easy pedestrian access must be provided from Sycamore Boulevard.

    All required parking for the clinic must be accommodated on site.

    Programmed area includes 109,450 Departmental Gross Square Feet (DGSF) / 130,184 Building Gross Square Feet (BGSF).

    Exterior material percentages are dictated by the PD document and shall not exceed specific percentages for Primary and Secondary Finishes.

    All service equipment needs to be screened; see PD document for restrictions.

    Signage opportunities are important to the client.

    Acoustical privacy is a concern of the healthcare system.

The following resources are available for your reference:

    Drawings, including a perspective, plans, and exterior elevations

    Building Program, including client's departmental program and detailed program for Treatment 01 (Infusion)

    Exterior Material Cost Comparisons

    Planned Development Document

    IBC Excerpts, showing relevant code sections

    ADA Excerpts, showing relevant sections from the ADA Standards for Accessible Design

The client proposes massing changes to the current design as well as programming for future phases.

Which of the following scenarios is permitted?

Options:

A.

Program the next phase on the adjacent vacant site for inpatient services.

B.

Combine the two phases into a single six-story building.

C.

Design an additional parking lot for use by local businesses after office hours.

Question 24

An architect is working with a developer to determine which of three available sites should be the preferred location for a new office building that will primarily utilize passive energy systems. All three sites are located in a cold, northern climate with winter winds predominantly from the north and west.

Site descriptions:

Site A: Located at the top of a hill; small vegetation and brush; expansive views in all directions.

Site B: Located along a river; heavily wooded area on the north side; coniferous trees shading the southern face of the building.

Site C: Located on a rocky, south-facing slope; wooded on the eastern edge; native grasses on southern boundary.

Primary goal: maximize solar energy potential while maintaining winter wind protection.

Which site should be selected?

Options:

A.

Site A

B.

Site B

C.

Site C

Question 25

The design of a large, one-story building to be used for the storage of confidential documents is being evaluated for security. The owners wish to have as much storage space as possible.

Which of the following design strategies would be the most economical solution to maximize security?

Options:

A.

Increase building setbacks

B.

Add visual surveillance cameras

C.

Minimize building entries and windows

Question 26

Which existing site elements are most important to locate in preparing a schematic design phase site plan for an adaptive reuse project?

Options:

A.

Structures and site improvements to be removed

B.

Utilities and services

C.

Structures and site elements programmed to remain

Question 27

Refer to the exhibit (graph of moving walkway speed vs. nominal passengers per hour).

Based on the graphic shown, which of the following moving walkway speeds will deliver 4,500 passengers per hour utilizing a single lane?

Options:

A.

110 ft per minute

B.

130 ft per minute

C.

150 ft per minute

D.

170 ft per minute

Question 28

When designing a three-story wood-frame home located in a high wind region, the addition of a green roof with a two-foot soil bed would do which one of the following?

Options:

A.

Increase the structure's resistance to overturning

B.

Require additional tie-downs

C.

Increase the structure's resistance to racking

Question 29

Which of the following design elements will affect pedestrian security within a site? Check the four that apply.

Options:

A.

Impervious pavement

B.

Type of landscaping

C.

Parking quantity

D.

Number of site access points

E.

Transparency of fences and barriers

F.

Location of adjacent activity

Question 30

In the design of a project, the architect should do which of the following in order to respond to the requirements imposed by governmental authorities that have jurisdiction over the project?

Options:

A.

Implement a code search checklist to capture key design code information.

B.

Implement a staff training program that will guarantee compliance with all applicable codes.

C.

Include a provision in the construction contract that delegates code compliance to the contractor.

D.

Include a provision in the architect's contract with the owner that ensures compliance with all applicable codes.