Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

ISTQB CTAL-TM Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 Exam Practice Test

Demo: 68 questions
Total 228 questions

Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 Questions and Answers

Question 1

In what way is the operations team usually Involved In testing7

Options:

A.

To conduct operational acceptance testing

B.

To conduct user acceptance testing

C.

To conduct security testing

D.

To conduct end-to-end transactional testing

Question 2

You are working on a project that is having problems with regressions. With each release of software given to the test team. 50% of the defects found are actually regressions. To combat this you have decided to implement test automation. You have given your automation team the following goal

'Implement lest automation to automate 90% of the manual regression tests before the product release date.’’

Which of the following is likely an issue with this goal being defined as "SMART?

Options:

A.

it is not clear if this is achievable in the time allowed

B.

It is not specific on what needs to be done

C.

It is not relevant to the project objectives

D.

It is not measurable against the goals of the project

Question 3

Which test process improvement model consists of five maturity levels?

Options:

A.

TMMi®

B.

TPI® NEXT

C.

GQM

D.

CMMi®

Question 4

You are working In an environment that is continually pushing process improvements down to the lest team You are skeptical that any of these have actually accomplished any improvement In fact you know that some of the changes have actually impaired progress

Given this information what step of the IDEAL model is missing?

Options:

A.

Diagnosing

B.

Establishing

C.

Acting

D.

Learning

Question 5

Your team has been assigned to lest a new product that is tightly integrated with existing systems The integrations include data transfers and transformations You have access to the architectural design documents and the integration specifications and some of your testers are former developers.

Given this information, what is the most appropriate test approach?

Options:

A.

Model-based and white-box

B.

Experience-based and black-box

C.

Risk-based and non-functional

D.

Requirements-based and functional

Question 6

Your team has been assigned to test a loyalty card program for a supermarket chain. Because this is a highly competitive market significant investment has been made to determine the shortcomings of the products offered by competitors While the feature sets are mostly the same, there is a wide variance In usability and performance and the users perceptions of these quality characteristics

Given only this information what test approach would be most appropriate?

Options:

A.

Model-based

B.

Experience-based

C.

Risk-based

D.

Requirements-based

Question 7

You have decided to help your team improve their skills. One of their assignments is to mentor a junior member of the team Which competency should you expect the mentor to develop during this exercise?

Options:

A.

Social

B.

Professional

C.

Methodological

D.

Biological

Question 8

What is the purpose of the defect management committee?

Options:

A.

To control the flow of defect reports into the system

B.

To validate defect reports and determine fix plans

C.

To implement strict guidelines for defect report creation

D.

To ensure the developers fix all defects

Question 9

What occurs In the retrospective closing?

Options:

A.

Everyone shakes hands

B.

The data collection methods are reviewed

C.

The strengths and opportunities for improvement in the retrospectives are discussed

D.

A brainstorming session is held to discuss the solutions to the root causes of the most significant issues

Question 10

Your team has been working on an Agile project for two months. There is a retrospective at the endof each sprint One of the data items reviewed is how many defects are being caught by users rather than by testers. The test team is being blamed for these escapes

What do you need to do to make these sessions more productive?

Options:

A.

You should attend the retrospective instead of the individual testers

B.

You should do root cause analysis to prove the developers are responsible

C.

You should gather metrics to present to the team regarding all the hours spent testing

D.

You should help the team brainstorm ideas on how to improve the testing to eliminate the escapes

Question 11

What is the purpose of lest control?

Options:

A.

To monitor the testing

B.

To return the test environment to its starting state and data

C.

To project detect trends and outcomes

D.

To take corrective actions required to meet the test objectives

Question 12

Which of the following defect statistics will provide input to be used for improvement in the defect reporting process?

Options:

A.

Number of defect reports re-opened

B.

Number of defects in a particular area of the code

C.

Number of defect reports rejected by the developers

D.

Number of defects found in a phase later than they were introduced

Question 13

In an Agile project, when Is it acceptable lo not write a formal defect report when a defect is found''

Options:

A.

Never

B.

If the defect can be fixed in the same iteration in which it was found

C.

the defect can be fixed in a later hardening sprint

D.

If the defect must be fixed by another team

Question 14

Your team has been assigned to a new project You have a mix of manual testers and automation engineers but everyone is currently doing manual testing. The development learn has alreadydecided to use DevOps as its approach but they have never used it before and are happy to take your input Unfortunately, about 50% of the development is completed already In the testing your team is doing they are finding that about 40% of the defects they catch are actually regressions caused by other changes

Given this information what should you do to help mitigate risk'?

Options:

A.

Review the policies regarding defect reporting and ensure your team is adding all the necessary information to each defect report

B.

Pivot part of the team from manual testing to test automation development to address the regression risk and implement better quality gates to reduce regressions

C.

Optimize the test environment to provide faster testing with more accurate test data and better testing tools to provide wider coverage

D.

Implement code reviews for the development team and require tester signoff before code can be released into the pipeline

Question 15

Your defect opened trend is converging to the closed trend but there is still a gap. What does that gap represent?

Options:

A.

Defects that are projected but have not been found yet

B.

Defects fixed but not yet closed

C.

Defects that have resulted from regressions

D.

Defects that will be introduced to production

Question 16

You are working on a project where the business part of the organization works traditionally with defined requirements, but the development team follows an Agile model Neither team plans to change their approach What is the proper name for this type of project approach''

Options:

A.

Sequential

B.

Hybrid as a transition to Agile

C.

Agile

D.

Hybrid as fit for purpose

Question 17

You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.

Given this information what should you conclude?

Options:

A.

More testing was needed before the production release because the defect detection percentage (DDP) was below 90%

B.

The cost of testing is high and could probably be lowered by spending more money on defect prevention

C.

The cost of testing is just right and is justified by the numbers

D.

More effort should be put on appraisal to help lower the cost of quality

Question 18

You feel that your team has become lazy when applying good software testing techniques You have given each of them a challenge to take a different business rule and build a full decision tableand then collapse that table You will then assess the results For this assessment, what competencies are you validating?

Options:

A.

Professional and methodical

B.

Social and personal

C.

Professional and social

D.

Methodical and personal

Question 19

In what environment are you most likely to see multiple defect management systems used in one project?

Options:

A.

Sequential

B.

Agile

C.

Hybrid

D.

Multi-tenant

Question 20

Which of the following is required to apply an experience-based testing approach''

Options:

A.

Detailed requirements

B.

Usage models

C.

Tester knowledge of the system and its usage

D.

A full risk-assessment to support risk prioritization

Question 21

Which of the following best describes the appraisal costs in the cost of quality'

Options:

A.

The cost spent preventing defects from occurring in the first place

B.

The cost for performing dynamic testing

C.

The cost for fixing defects

D.

The cost for lawyers to deal with a lawsuit over a defect

Question 22

You are managing the test team that is testing a new mobile application that provides a "step-by-step' hiking guide Your risk assessment resulted in the following table:

Your team has clone the depth and breadth testing for the GPS accuracy and usability features but when the product was given to beta testers there were some issues Despite the users reporting the app was easy to use at least one user walked off the edge of a cliff and another one ended up in a river. Your team has confirmed that the functionality is working correctly. and the GPS information is accurate.

What other area of testing should you now prioritize?

Options:

A.

Usability

B.

Functionality

C.

Performance

D.

Security

Question 23

Your team has decided that they will build their own test management tool This will allow them to link the requirements and test cases together providing full traceability It will also allow them to create fully customized reporting and color-coded dashboards They have estimated the time required to create the new tool and the cost These fit within the project schedule and budget

What other consideration should be taken before this decision is made?

Options:

A.

Relative benefits to your vendors

B.

Maintenance costs

C.

Licensing fees to other parts of the organization

D.

Reduction of manual repetitive testing

Question 24

If you are monitoring code coverage during testing to determine what areas still need testing what type of testing is likely occurring?

Options:

A.

Black-box

B.

White-box

C.

Functional

D.

Non-functional

Question 25

Your team has been given the following test objective Ensure that the users are happier with this version than they were with the last version?

What is wrong with the way this is defined?

Options:

A.

It is unlikely that just a version change will make users happier so this is not achievable

B.

It cannot be measured because happier' is subjective

C.

It does not define a timeframe

D.

It is not aligned with the organization's objectives

Question 26

Which of the following Is a way in which risk analysis drives test analysis?

Options:

A.

It determines which tests should be executed first

B.

It guides the selection of test conditions that must be covered by testing

C.

It influences the type of reporting that will be used during execution

D.

it drives root cause analysis for any defects found

Question 27

Your organization has decided to augment your testing team with an offshore team. The offshore team members are experienced testers who are experts in the domain of the system under test Your team is worried about the offshore team taking their jobs and they are resistant to the change You need to pick three of your team members to be the ambassadors for the new team

Which competences will be most important for your ambassadors to possess?

Options:

A.

Professional competence and methodological competence

B.

Methodological competence and social competence

C.

Social competence and personal competence

D.

Personal competence and professional competence

Question 28

You have been assigned t o a project that has a very tight schedule. In fact, given your first analysis you do not think the planned test execution can be completed within the schedule There is no time allowed for defect fixing or for repeating tests. Regression testing has been left out of the planning entirely There is no time to develop test automation. The team has agreed that this Is not the way to run a project, yet they are stuck with the current schedule

Given this information what is the best way to proceed with the testing to try to meet the deadline with the best outcome1?

Options:

A.

Review the personnel plan and get more resources onto the test team

B.

Continue with the current plan but highlight to the project manager that either the deadline will be missed or the testing will not be done

C.

Develop a test automation plan so that automation can be started now

D.

Conduct a quality risk analysis and prioritize the testing based on risk so the highest risk items are tested first

Question 29

Which of the following Is the common set of information to be produced in a test estimate''

Options:

A.

Number of people number of systems lines of code, cost

B.

Time per person budget end date start date

C.

Test effort test duration time to complete, cost

D.

Effort time cost, test activities

Question 30

You are working for an outsource testing company You have a client that will only consider candidates that are highly skilled with Salesforce. regardless of the number of years they have spent testing similar products You have looked through your skills matrix and you have no one with the right type of experience for this project.

What competence area is your team lacking?

Options:

A.

Social competence because they are lacking the ability to work with the rest of the team

B.

Personal competence because they are not confident enough to pass the interviews with the clientand they are not willing to learn Salesforce

C.

Methodical competence because they lack the ability to create test cases from a Salesforce requirements document

D.

Professional competence because they do not have the required domain knowledge in Salesforce

Question 31

You have been asked to make a recommendation on deployment readiness on the software your team has been testing.You have the following metrics:

Given this information what is a critical metric you are missing?

Options:

A.

Number of tests passed

B.

Number of defects outstanding

C.

Residual risk

D.

Planned vs actual cost of testing

Question 32

Which of the following is the proper order for the stages of a tool lifecycle?

Options:

A.

Acquisition Support Evolution Retirement

B.

Acquisition Evolution Support Retirement

C.

Evolution Acquisition Retirement Support

D.

Evolution Support Acquisition Retirement

Question 33

You are working with a development team who have a CI/CD pipeline implemented. They want to integrate your team's existing test automation into the pipeline to augment their unit tests so they will have continuous testing. They have already determined that this is technically possible with the tool you are using but with require some changes to the test automation framework to integrate the results reporting

What will your team need to make this happen?

Options:

A.

Investigation that the tool will be fit for purpose

B.

Training regarding how to make the framework modifications so the integration is possible

C.

A review to determine if this is the best tool to use for the integration with the CI/CD pipeline

D.

investigation of the licensing models of the tool and an understanding of any potential costs

Question 34

Your manager has decided that your team of manual testers should all become test automation engineers Your team is much stronger in analysis than In technical testing so you are concerned about their ability to adapt. What tool capabilities could help with this transition?

Options:

A.

Low license costs

B.

Remote storage of the test automation scripts

C.

High usability with Al-assisted object capture

D.

Good reporting

Question 35

While mining the defect database for patterns of problems in the last release, a Test Manager notices that many of the most damaging failures were caused by defects

injected during the low-level design phase.

Which of the following actions will likely give this project the most effective solution to this problem? [3]

Options:

A.

Increased static analysis during the implementation phase

B.

Mandatory reviews of all important design work products

C.

Formal inspections of the code modules affected by the last release

D.

Increased white-box coverage during system testing

Question 36

You are reviewing the project's traceability matrix after the first cycle of testing. You have discovered that new requirements have been introduced and others have

changed.

What should you do? [2]

Options:

A.

Assign the new requirements to a maintenance release, update the test documentation for the changed requirements.

B.

Ask for more time and budget for testing.

C.

Update the "lessons learned" document to avoid future issues similar to this.

D.

Re-assess the test coverage.

Question 37

You are Test Manager for a project which is in the Test Implementation stage for the first planned iteration, creation of the initial Test Cases and required test data is progressing well.

The Test Strategy documents the Stakeholders view that small teams should collaborate together to create and test functionality which is to be released in iterations, with each release building on the success of the last.

Stakeholders are willing to accept the risks of a partly working system in the early stages. Delivery of working functionality (particularly around interfaces to third party systems and performance of back end databases) is the priority for the early releases.

Which of the following test types would you select for this first planned iteration, in order to meet Stakeholders expectations?

a) Usability testing

b) Structural testing

c) Functional testing of process flows

d) Performance testing

e) Business process testing

f) Component integration testing

You are Test Manager for a project which is in the Test Implementation stage for the first planned iteration, creation of the initial Test Cases and required test data is progressing well.

The Test Strategy documents the Stakeholders view that small teams should collaborate together to create and test functionality which is to be released in iterations, with each release building on the success of the last.

Stakeholders are willing to accept the risks of a partly working system in the early stages. Delivery of working functionality (particularly around interfaces to third party systems and performance of back end databases) is the priority for the early releases.

Which of the following test types would you select for this first planned iteration, in order to meet Stakeholders expectations?

a) Usability testing

b) Structural testing

c) Functional testing of process flows

d) Performance testing

e) Business process testing

f) Component integration testing

Options:

A.

b, c, d and f.

B.

b, d, e and f.

C.

a. b, d and f.

D.

a, c, d and e.

Question 38

Which one of the following is NOT a determining factor when considering the optimal time to conduct a document review? SELECT ONE OPTION

Options:

A.

Management procedures have been reviewed

B.

Review time is built into the schedule.

C.

The document is in a reviewable state.

D.

Suitably skilled reviewers are available.

Question 39

Your organization is considering using open-source tools. You have been told you need to be aware of the terms of the GNU general public license.

What is the basic concept of this license? [1]

Options:

A.

Anyone can use the software anytime for any reason.

B.

A small license fee must be paid to the supplier of the software.

C.

If you're going to distribute the software, you need to do so with the same terms as were applied when you received the

software.

D.

You are allowed to use the software internally, but it cannot be incorporated into any product for which you will receive a profit.

Question 40

Which one of the following will allow phase containment to be assessed within a testing project? SELECT ONE OPTION

Options:

A.

Using the phases of defect introduction and detection data for all phases of the project.

B.

Using the phases of defect introduction, detection and removal data on a phase by phase basis.

C.

Using defect introduction and removal data for the project as a whole.

D.

Using defect removal data for the testing phases of the project.

Question 41

You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the

project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.

At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely,

particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as

"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.

Given this information, which lifecycle model should you recommend? [3]

Options:

A.

Spiral

B.

Iterative/incremental

C.

V-model

D.

Waterfall

Question 42

When, at a minimum, should project risks be re-evaluated? [1]

Options:

A.

Prior to test case creation

B.

At major project milestones

C.

During the creation of the test plan

D.

At the beginning of the test execution phase

Question 43

Which of the following is NOT true when following the V-Model lifecycle to organise and plan testing activities? SELECT ONE OPTION

Options:

A.

Test execution activities run until exit criteria have been met.

B.

Reporting of all test results occurs when testing is complete for the whole project.

C.

System test planning starts when project planning activities commence.

D.

Test analysis activities run concurrently with specification of requirements and design.

Question 44

Which one of the following standards would a Test Manager be expected to understand when planning and organising activities with a Project Manager? SELECT ONE OPTION

Options:

A.

PRINCE2®

B.

CMMI®

C.

TMMI®

D.

ITIL®

Question 45

Which of the following describes the Failure Mode and Effect Analysis (FMEA) risk analysis technique? SELECT ONE OPTION

Options:

A.

FMEA is a quality risk management technique concerned with quality risks that arise from an incorrect understanding of the customer requirements.

B.

FMEA is an analytical process upstream, that attempts to identify the hazards for each risk.

C.

FMEA is where quality risks, their potential causes and their likely effects are identified and then severity, priority and detection ratings are assigned.

D.

FMEA is a risk mitigation process that involves determining every possible type of failure, and designing tests to cover each one.

Question 46

Your company specialises in offering travel insurance policies to the over 60 age bracket. It is starting a new project to modernise the design of its website, which is seen to be inferior to its competitors. The project will use a SCRUM software development methodology.

As senior test manager for your company, you have been asked to identify three test analysts to join the SCRUM development team. There are a number of testers currently not allocated to projects who would be available, all of them have been with the company for a number of years, although some have little or no experience in iterative development.

You must assess their current skillsets to determine whether any of them possess skills that would be of particular relevance for the new project. Which TWO of the following skills should you focus on in your assessment?

Options:

A.

Methodological competence - the ability to analyse the test basis and deal with product risks

B.

Professional competence - technical expertise to implement automated tests and performing exploratory testing

C.

Professional competence - having business domain expertise in travel insurance

D.

Professional competence - coaching and mentoring others to understand SCRUM theory and good practice

E.

Personal competence - a high level of self-management and discipline

Question 47

Your organisation has decided to move from using the V-model software development lifecycle to Agile Scrum. Due to inexperience in Agile methodologies and to mitigate risk, the next project will use a hybrid model, beginning with a traditional requirement definition phase and transitioning to an Agile Scrum approach for development and testing.

Which would be an appropriate test management task to perform FIRST for this next project?

Options:

A.

Ensure the team is adept at combining structured processes with Agile flexibility

B.

Track and review test efforts within the sprints to ensure they align with Agile practices

C.

Produce a detailed test estimate for each test level that will be used in each sprint

D.

Enroll the testers on an online User Story development course to better understand the test basis

Question 48

Which classification information would be most useful to capture for newly identified defects? [2]

Options:

A.

The priority that the business assigned to the project that the defect was found in

B.

The system build that the defect was found in

C.

The name of the configuration manager who built the system

D.

The number of test steps in the test script that found the defect

Question 49

Which of the following BEST explains how test process improvement can benefit an organisation? SELECT ONE OPTION

Options:

A.

It can result in defect free releases into production

B.

It can reduce the demand for test resources to support maintenance releases.

C.

It can prevent developers making errors when writing code.

D.

It can increase the number of applicants for job vacancies.

Question 50

What is the purpose of process improvement assessment models? [1]

Options:

A.

Ensure a consistent approach is used

B.

Assist in the hiring of new testers

C.

Model the failure modes of the product

D.

Identify the test tools needed for testing

Question 51

You are a Test Manager and have started a program of test process improvement. You are following the IDEAL model and have completed the first three phases, now you are ready to go further. Which TWO of the following activities will enable you to complete the remaining phases of the IDEAL model?

Options:

A.

Trial a low-priority improvement in order to assess the difficulty of changing the organisation's processes

B.

Re-prioritise the possible improvements according to their expected return on Investment

C.

Trial one or more of the highest-priority improvements in a pilot project

D.

Decide whether to take a model based or an analytical based process improvement approach

E.

Check to see which benefits have, or have not, been achieved from the improvement made

Question 52

You are managing a project that will be using a model-based testing strategy.

Which of the following is an activity that will be needed in order to implement this strategy? [1]

Options:

A.

Conduct a quality risk analysis with all affected stakeholders.

B.

Conduct operational profiling to determine the expected usage of the system.

C.

Select an appropriate quality standard, such as ISO 9126, to be used to guide the testing.

D.

Create the test charters for the exploratory testing sessions.

Question 53

Assume that you are working for a company that has maintained and tested a car parking permit system for many years. The system holds the name and address of permit holders and automatically writes to the permit holder with a form to renew or cancel their permit each year.

The test plan states the following:

"since the system is considered a stable system. Boundary Value Analysis is the only test case design technique that needs to be applied during testing"

Consider the following change that was detailed in the Requirements Specification for a replacement to an existing parameter held within the system;

• The specified renewal date for each permit must be not be after 31 st January 2020. Which one of the following is a valid test condition that satisfies both the requirement and the test plan?

SELECT ONE OPTION

Options:

A.

Input the dates either side of and including 31/01/2020, and select tests from the regression pack relating to the renewal date and printing only.

B.

Input the date 31/01 /20 in the wrong field to see what happens, and run the whole of the regression test pack.

C.

Input the date 01/02/2020 and confirm this is not accepted. and select tests from the regression test back relating to the renewal date only

D.

Input a date in an invalid format e.g. 31 FEB 2020, and select tests from the regression pack relating to renewal date, policy holder's name, address and printing.

E.

Input the date 01/02/2020 and confirm this is not accepted. and select tests from the regression testback relating to the renewal date only

Question 54

What is a "depth-first" risk-based testing technique? [1]

Options:

A.

Highest risk test cases are executed first

B.

All risk items are tested at least once

C.

Lowest risk test cases are executed first

D.

Non-functional test cases are executed first

Question 55

System testing on your current project is coming to an end and it is time to write the test completion report. The product is an in-house development to support the Sales & Marketing department. Test design was based on requirements analysis.

Which of the following metrics is MOST likely to be useful to help the business stakeholders decide if testing has met its objectives?

Options:

A.

Breakdown by risk level of coverage of product risks

B.

Breakdown by coverage type of the code coverage achieved

C.

Percentage of test cases that have been automated

D.

Breakdown by priority of coverage of requirements

Question 56

Referring to SCENARIO 2 It has been agreed that Project 1 will be delivered using an Agile approach, with user stories delivered across three sprints, each lasting 4 weeks. The programme manager is concerned about RISK 3 and wants the Master Test Plan to specify an effective test process improvement approach.

Which of the following is the best test process improvement approach for Project 1 ? SELECT ONE OPTION

Options:

A.

Test process improvement is not possible for this project as the Agile approach does not allow time to make improvements.

B.

A TMMi assessment should be run at the end of each sprint to identify improvements for the next sprint.

C.

Short post-sprint review sessions should be conducted to identify areas of improvement for the next sprint.

D.

A CTP assessment should be run after each sprint to identify critical test processes that need improving.

Question 57

You have been asked to implement formal reviews at your company. From the list below, what are the correct characteristics of a formal review?

a. Entry and exit criteria have been defined.

b. Checklists created to be used by all reviewers.

c. Consistency with current project plan is checked.

d. Metrics on effectiveness will be gathered.

e. The review will be moderated by a lead auditor.

Options:

A.

c, d and e.

B.

b, c and e.

C.

a, b and c.

D.

a, b and d.

Question 58

Which testing metric identifies defect density? [1]

Options:

A.

Project

B.

Product

C.

Process

D.

People

Question 59

You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but

it is clear that the project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development

team.

At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of the delivered product and will be

watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate

for all test cases covering risks that are classified as "high" or "very high", 95% pass rate for all "medium" risks and 75% pass rate for all "low" and "very low" risks.

Given this information, which of the activities of the standard test process are the most critical for the Test Manager to perform? [3]

Options:

A.

Requirements reviews

B.

Test execution

C.

Test monitoring and control

D.

Project management, particularly regarding scheduling and budgeting

Question 60

Which of the following is a generic good practice when evaluating and selecting a test tool?

Options:

A.

Define the ownership of the tool

B.

Run a pilot project to validate the selection criteria

C.

Identify internal requirements for coaching, mentoring or training in its use

D.

Plan a proof-of-concept to be performed by the first project that uses the tool

Question 61

You have been carefully monitoring the progress of testing for your project. You have been using the established traceability to verify that the requirements and test

conditions are being adequately addressed. The test team is proceeding well in their test case execution and you can see that you are achieving about 80% coverage of

the test conditions per the traceability mapping in your test management system. You have seen a number of defects being logged against test conditions that are failing,

but you do not see a mapping of the test cases to those conditions.

What is likely to be occurring in the testing area that is causing the traceability to break down? [2]

Options:

A.

The test cases are mapped to the test strategy and are bypassing the test conditions.

B.

The testers are running exploratory tests that are not mapped to the test conditions.

C.

The testers are executing the wrong tests.

D.

The testers are not updating the test execution information in the test management system.

Question 62

You are Test Manager on a new project and have estimated the test effort to be 500 days, assuming that you will find no more than 50 defects and 5 test iterations being required. The project manager has said the estimate is too high. Which of the following options could enable you to reduce this estimate?

SELECT ONE OPTION

Options:

A.

Agree an increase in the Unit test coverage before the code is delivered to your test team.

B.

Assign more test analysts to the test execution phase.

C.

Increase the regression test coverage.

D.

Allow more time for the developers to fix the defects found.

Question 63

You have done a comprehensive risk analysis. You have involved the appropriate people in assessing the risks and determining the likelihood and impact of those risks. You have been testing for three months and have been able to mitigate 75% of the high risk items. You have two weeks left in testing and you now do not expect to be able to complete all the items on the high-risk

mitigation list, never mind any from the medium or low-risk lists.

What is the most effective action you should take? [3]

Options:

A.

Use a random selection algorithm to pick tests from the high, medium, and low risk mitigation lists - thereby ensuring that each risk list has some mitigation.

B.

Present your risk mitigation progress and project status to the project's stakeholders, and request additional time or assistance in re-prioritizing the remaining high-risk items.

C.

Concentrate testing in areas that have already found numerous problems.

D.

Retest the highest risk areas to ensure no regressions have occurred.

Question 64

Which of the followingis a factor that is likely to increase the test estimate? [1]

Options:

A.

Use of a new technology

B.

A requirement for high level test documentation

C.

Assigned personnel who are experienced on working with similar projects in similar environments

D.

Static test data

Question 65

Which two of the following activities would normally occur in the Acquisition stage of a tool's lifecycle?

a) Assign a tool administrator to decide on best use of the tool

b) Establish a backup and restore strategy for the tool

c) Review other tools provided by the same vendor

d) Determine how the tool may be impacted by a change to the operating environment

e) Develop and implement a training plan for new users of the tool

SELECT ONE OPTION

Options:

A.

c and e.

B.

a and b.

C.

a and e.

D.

b and d.

Question 66

You are Test Manager working on a project which is improving the user interface for its call centre staff handling customer enquiries. The project has completed UAT for the first iteration; however a large number of defects were raised by call centre staff seconded to help with the User Acceptance testing.

The defects described the user interface as not being intuitive enough with a poor 'help' facility. A user representative spent a week working with developers and system testers to explain the issues, which were subsequently agreed to have resulted from poorly specified usability requirements.

The requirements were defined separately for each iteration and have been formally reviewed by business analysts, developers and the IT director.

The user representative was also able to answer a number of other questions that the system test team had regarding call centre workflows, which improved their domain knowledge.

You have been asked to conduct a project retrospective and recommend improvements for the next iteration which introduces further user interface changes. Which of the following would be the MOST effective improvement for the next iteration?

Options:

A.

System test analysts to attend external training on usability testing techniques.

B.

System test cases to incorporate usability testing and be reviewed by a call centre user representative.

C.

Call centre representatives to participate in reviews of the user interface requirements.

D.

A call centre user representative to be seconded to the system test team to help improve test design.

Question 67

Which statement about defect management in hybrid software development is TRUE?

Options:

A.

When multiple teams are working to different development models, fixes should be aligned to a separate plan that reflects the characteristics of their development model

B.

When multiple teams are working in different development models, they will need to use different defect management tools

C.

Defect management meetings should be held more often by teams working in Agile ways than those working in sequential ways

D.

Defect management meetings should be held more often by teams working in sequential ways than those working in Agile ways

Question 68

Your company, which specialises in the manufacture of luxury garden furniture to the UK market, is to embark on a project that will deliver a major update to its payment processing component, addressing improvements to functional suitability and performance efficiency. You have just selected a performance testing tool but it has not yet been implemented.

A decision has been made to transfer responsibility for functional system test implementation and execution to the company's offshore test team. System test analysis and design will be performed onshore, at the company's UK head office. You have direct management responsibility for all test personnel, onshore and offshore.

Which of the following is a test management activity that is MOST important for this project?

Options:

A.

Creating a resource allocation strategy

B.

Deciding which test techniques should be applied

C.

Defining an approach for usability testing

D.

Implementing the performance testing tool

Demo: 68 questions
Total 228 questions