When preparing their bid, a contractor organizes their costs into different categories. The following items are examples of which type of cost?
Permits and inspections
Mobilization and startup
Jobsite safety and security procedures, including personnel
Administrative costs attributable to the work
Construction
Contingency
Overhead
Insurance
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI’s estimating and bidding guidance divides project costs into:
Direct (construction) costs – labor, materials, equipment directly incorporated into the work.
Indirect costs / Overhead – project overhead (jobsite-specific) and home-office overhead.
Contingencies and profit.
The items listed in the question are classic examples of project (jobsite) overhead costs:
Permits and inspections – required to enable the work but not physically part of the building.
Mobilization and startup – moving equipment, setting up trailers, temporary utilities.
Jobsite safety and security procedures – safety staff, fencing, lighting, etc.
Administrative costs attributable to the work – site management staff, office supplies, communications.
These are necessary to execute the project but are not directly installed in the construction work, so they are categorized as overhead, making Option C correct.
Why others are incorrect:
A. Construction – refers to direct, installed work (concrete, steel, finishes, etc.), not these support functions.
B. Contingency – covers unknowns and risks; it is separate from known overhead items.
D. Insurance – is a specific cost category (builder’s risk, liability, etc.), distinct from the listed overhead activities, even though it may sometimes be grouped in “General Conditions” in a detailed estimate.
Relevant CSI references:
CSI Project Delivery Practice Guide – chapters on cost planning and estimating.
CSI CDT Body of Knowledge – sections on types of project costs (direct, indirect/overhead, contingency, profit).
The emphasis shifts from overall relationships and functions to more technical issues during which design phase?
Preliminary design
Schematic design
Design development
Construction documents
In CSI’s project delivery / design-phase framework, the design development (DD) phase is where the emphasis shifts from big-picture concepts to more detailed, technical decisions:
Earlier phases like schematic design focus on overall relationships, general size, massing, and functions of spaces and systems.
Once the project enters design development, the team refines those schematic decisions into more precise technical solutions, coordinating architectural, structural, mechanical, electrical, and other systems, and beginning to define materials, systems, and outline specifications.
By the construction documents phase, the design is largely established and the emphasis is on fully detailing and documenting the agreed technical decisions for pricing, permitting, and construction.
CSI’s practice guides describe DD as the phase in which design decisions are “developed and refined” and more technical information is incorporated, bridging from conceptual/schematic level to the level needed to create final construction documents. That wording corresponds directly to “the emphasis shifts from overall relationships and functions to more technical issues,” which is why Design development (C) is correct.
A. Preliminary design – Not a standard CSI primary phase label; in many frameworks this term is used informally or overlaps with early conceptual planning, where the focus is still on overall functional relationships, not detailed technical issues.
B. Schematic design – Focuses on general arrangement, shape, and relationships of spaces and systems, not yet at the more detailed technical decision level.
D. Construction documents – This phase emphasizes complete, coordinated, enforceable documentation (finalizing drawings and specs), not the initial shift from conceptual to technical; that shift has already occurred in design development.
CSI-aligned references (no external links):
CSI Project Delivery Practice Guide – chapters on Schematic Design, Design Development, and Construction Documents phases.
CSI Construction Specifications Practice Guide – overview of how design phases relate to the development of specifications.
CSI CDT Exam Study/Practice materials – sections describing the purpose and focus of each design phase.
Which team member is actively involved and interested in all phases of the project?
Contractors
Owners
Architects/engineers
Manufacturers/suppliers
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI’s project delivery framework places the owner at the center of the facility life cycle. The owner:
Initiates the project by defining needs and project goals.
Selects the project delivery method and engages the design and construction teams.
Participates in planning, design decisions, funding, and approvals.
During construction, the owner is responsible for payments, change decisions, and acceptance of the work.
After construction and closeout, the owner (often through a facility management group) is responsible for operation, maintenance, and long-term performance of the facility.
CSI repeatedly highlights that only the owner is engaged from the earliest concept through long-term operation and eventual renovation or disposal. All other parties (designers, contractors, manufacturers) participate for limited phases.
Therefore, the party “actively involved and interested in all phases of the project” is clearly:
B. Owners
Why the other options are incorrect:
A. ContractorsContractors typically become formally involved at procurement/bidding and remain through construction and closeout. They usually have no role in early planning (except in some delivery methods like CM-at-Risk or IPD where they join during design) and no long-term responsibility for operations beyond warranty obligations.
C. Architects/engineersThe A/E’s primary involvement is during planning and design, and then construction administration during construction and closeout. After the project is turned over, their involvement often ends unless separately engaged for post-occupancy evaluations or future work. They do not normally manage day-to-day operations and maintenance.
D. Manufacturers/suppliersManufacturers and suppliers participate mainly in product selection, submittals, and furnishing materials and equipment during design-assist and construction phases. They may have continuing obligations for warranties or support, but they are not engaged in every phase of the project’s life cycle as the owner is.
Key CSI-Related References (titles only):
CSI Project Delivery Practice Guide – roles and responsibilities of the owner, design professional, contractor, and others.
CSI Facility Management Practice Guide – owner’s role during operations and the extended facility life cycle.
CSI CDT Study Materials – diagrams and explanations of project participants over the facility life cycle.
Which of the following establishes a baseline from which deviations are identified?
General requirements
Supplementary conditions
Project manual
General conditions
Comprehensive and Detailed Explanation From Exact Extract (CSI-Based)
According to the Construction Specifications Institute (CSI) and CDT exam content, the General Conditions of the Contract form the foundational “baseline” set of administrative, procedural, and legal requirements for every construction contract. All other contracting documents—including Supplementary Conditions, Division 01, and specification sections—are modified in relation to this baseline.
Why the Correct Answer Is General Conditions (Option D)
CSI practice guides describe the General Conditions as:
The standard baseline document for project relationships, responsibilities, rights, and procedures.
The “default” set of requirements unless modified by Supplementary Conditions or Division 01.
The document against which all deviations must be clearly identified, especially when supplementary or project-specific requirements alter the standard conditions.
General Conditions define or baseline:
Roles and responsibilities of owner, contractor, A/E
Contract time, payments, changes, submittals, inspections
Dispute resolution
Site conditions, insurance, and protection of work
CSI emphasizes that the General Conditions do not change for each project unless Supplementary Conditions modify them, which reinforces that they form the baseline.
Why the Other Options Are Incorrect
A. General Requirements (Division 01)
Division 01 sections coordinate the administrative and procedural requirements for the project, but they expand upon or modify the General Conditions—not the other way around. They cannot be the baseline because they themselves rely on the baseline established in the General Conditions.
B. Supplementary Conditions
These modify the General Conditions to address project-specific legal or regulatory requirements (e.g., bonding, liquidated damages, insurance). They create deviations, not the baseline from which deviations are identified.
C. Project Manual
The Project Manual is a collection of documents—including bidding requirements, contract forms, General Conditions, Supplementary Conditions, and specifications. It is not itself the baseline; it contains the baseline (the General Conditions).
Key CSI References
CSI Project Delivery Practice Guide – Chapters on Procurement and Contracting, discussing General Conditions as the base document for rights, responsibilities, and procedures.
CSI Construction Specifications Practice Guide – Sections on Contract Documents hierarchy and coordination.
CSI CDT Body of Knowledge – Contractual relationships and use of General Conditions as baseline documents.
The architect/engineer reviews submittals for which of the following reasons?
To correct or change the design
To monitor design conformance
To review installation procedures
To review substitution requests
CSI and standard General Conditions define the architect/engineer’s submittal review purpose as confirming that submittals conform to the design intent shown and specified in the contract documents — not to approve means, methods, or to revise design.
The A/E’s review checks:
General compliance of the submittal with design intent.
Coordination among trades.
Any deviations that require clarification or change approval.
It is not for:
Designing or redesigning (Option A),
Supervising construction procedures (Option C), or
Evaluating formal substitution requests (Option D) — substitutions are separately submitted for approval under Division 01 procedures.
Therefore, the A/E reviews submittals to monitor design conformance, making Option B correct.
CSI Reference:
CSI Construction Specifications Practice Guide, “Submittal Procedures and Responsibilities”; Project Delivery Practice Guide, “Construction Phase — Submittal Review.”
How do private bidding practices compare or contrast with public bidding practices?
A private owner may waive any informality in the bidding, except for the performance bond.
Private bids may be opened in private, but the results must be published in a reasonable time.
The laws and regulations for private bidding are the same as for public bidding.
The private owner may award a contract to a responsive and responsible bidder other than the lowest.
CSI’s project delivery and CDT materials distinguish clearly between public and private procurement:
Public work (funded and contracted by government entities) is typically governed by statutes and regulations that require:
Formal advertisement,
Clearly defined bidding procedures,
Sealed bids opened publicly at a specified time and place, and
Award to the lowest responsive and responsible bidder, except where law allows other defined selection methods.
Private work, by contrast, is not generally bound by these public procurement statutes. CSI explains that private owners have significantly more flexibility, including:
Not being required to publicly open bids,
Being able to negotiate with one or more bidders,
Rejecting any or all bids, and
Awarding the contract to any responsive and responsible bidder they choose, based on value, qualifications, schedule, or other criteria—not solely lowest price.
Because of this flexibility, CSI emphasizes that a private owner may select a bidder other than the lowest as long as the bidder is responsive (submits a bid per the requirements) and responsible (qualified, capable, and reliable). This matches Option D exactly.
Why the other options are incorrect or misleading:
A. A private owner may waive any informality in the bidding, except for the performance bond.While private owners often can waive bid informalities, CSI does not state any universal rule that the performance bond is a special exception in private bidding. Performance bonds are typically part of the contract requirements after award, not a fixed “unwaivable informality” in bid receipt; treatment of bonding is governed by the owner’s requirements and any applicable law, not a CSI rule unique to private work.
B. Private bids may be opened in private, but the results must be published in a reasonable time.Publication of bid results is a hallmark of public work (transparency and accountability). CSI does not require private owners to publish bid results; private owners may keep them confidential if they wish, unless other obligations apply (e.g., corporate policies).
C. The laws and regulations for private bidding are the same as for public bidding.CSI specifically distinguishes between public and private owners: public owners are constrained by statutes and regulations, whereas private owners have much more discretion. The laws governing public bidding and private bidding are not the same, and this is a key CDT concept.
Thus, the CSI-consistent distinction is that private owners are free to award the contract to a responsive and responsible bidder who is not the lowest, making Option D the correct choice.
Key CSI-aligned references (no links):
CSI Project Delivery Practice Guide – procurement and bidding chapters comparing public and private practice.
CSI CDT Body of Knowledge – sections on bidding requirements, “responsive and responsible bidder,” and differences between public and private construction procurement.
In the AIA A201 General Conditions of the Contract for Construction, whom is responsible for property insurance for a project?
Surety, on contractor's behalf.
Owner, unless assigned to contractor.
Owner and contractor, jointly.
Contractor, unless assigned to owner.
CSI’s CDT materials rely heavily on the AIA A201 – General Conditions of the Contract for Construction as the model for understanding roles, responsibilities, and risk allocation. In A201 (both the 2007 and 2017 editions), the default requirement for property insurance (builder’s risk) is placed on the Owner.
The relevant article states, in substance, that:
Unless otherwise provided in the contract documents, the Owner shall purchase and maintain property insurance written on an “all-risks” or equivalent builder’s risk policy.
This insurance is to cover the Work, materials, and equipment to be incorporated into the project during construction, and sometimes temporary structures and portions of the site as specified.
The parties may alter this allocation by specific agreement (for example, by assigning the responsibility to the contractor in the Supplementary Conditions or Agreement), but the baseline A201 allocation is clearly:
Owner is responsible for the property insurance,
“unless otherwise provided” in the contract documents.
Why the other options are not correct:
A. Surety, on contractor’s behalf – The surety’s role relates to bonds (bid bond, performance bond, payment bond), not to providing property insurance for the work.
C. Owner and contractor, jointly – The standard A201 language does not assign joint responsibility; it assigns it primarily to the Owner, subject to modification.
D. Contractor, unless assigned to owner – This reverses the A201 default. Only if the contract documents specifically shift the duty would the contractor procure property insurance.
Therefore, in accordance with AIA A201 as interpreted and taught in CSI’s CDT program, responsibility for property insurance for the Work rests with the Owner, unless the contract documents specifically assign it otherwise, making Option B the correct answer.
Lump sum, unit price, and cost-plus-fee are examples of what?
Delivery method
Bonding system
Basis of payment
Cost estimate
CSI distinguishes between project delivery methods (e.g., Design-Bid-Build, Construction Management at Risk, Design-Build) and methods of compensation / basis of payment for the construction contract.
Lump sum, unit price, and cost-plus-fee are classic examples of basis of payment (sometimes called pricing or compensation methods):
Lump sum – A single fixed price for the entire work, based on the contract documents.
Unit price – Payment based on measured quantities of work items at agreed unit rates.
Cost-plus-fee – The owner reimburses actual costs of the work plus a fee (which may be fixed or a percentage).
These are not delivery methods or bonding systems; they describe how the contractor is paid under the construction contract, so Option C is correct.
Why the others are incorrect:
A. Delivery method – Delivery methods describe the organizational and contractual structure (who holds contracts with whom and when they are engaged), not how payment is calculated.
B. Bonding system – Bonds (bid, performance, payment) are surety instruments, not pricing arrangements.
D. Cost estimate – An estimate is a forecast of probable cost, not the contractual method of payment.
CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – distinctions between delivery methods and compensation methods.
CSI CDT Body of Knowledge – lump sum, unit price, and cost-plus as bases of payment within procurement and contracting.
Which of the following is an example of preconstruction submittals?
Product data
Shop drawings
Schedule of values
Warranty documentations
In CSI/CDT terminology, “preconstruction submittals” are those required at (or very near) the start of the project, before actual construction work proceeds, to set up project administration, payment, and coordination. These submittals are usually specified in Division 01 – General Requirements of the Project Manual and are part of the contract requirements established by the specifications.
Typical examples of preconstruction submittals in CSI-aligned practice include:
Construction/progress schedule
Submittal schedule
Schedule of values
List of subcontractors and suppliers
Insurance and bonds
Temporary facilities and controls plans
Health & safety or site-specific plans (when required)
The schedule of values is expressly listed in standard Division 01 sections as a required early submittal that must be approved before progress payments can be properly evaluated and certified. It breaks down the contract sum into line items for payment and becomes the basis for reviewing the contractor’s pay applications throughout the project. Because it is required at the start of the construction phase and before regular work progress, it is a classic preconstruction submittal, matching Option C.
Why the other options are incorrect:
A. Product dataProduct data (cut sheets, catalog information, performance data, etc.) are action submittals for specific products and materials. Although some may be submitted early, they are typically required as needed before related work is installed, not universally at the very start of the job. They are not classified by CSI as “preconstruction submittals” in the same sense as the schedule of values or project schedule.
B. Shop drawingsShop drawings are also action submittals supporting fabrication and installation of specific work (e.g., structural steel, curtain wall systems, ductwork, etc.). They are provided during the construction phase in accordance with a submittal schedule, not as “preconstruction” administrative submittals that must be in place before construction administration and payments can be properly managed.
D. Warranty documentationsCorrected term: “warranty documentation.”Warranty documentation is typically part of closeout submittals—submitted near Substantial Completion or Final Completion, not at the beginning of the project. Division 01 and individual technical sections usually require warranties to be submitted as part of project closeout procedures, after the work is in place and accepted, not as a preconstruction submittal.
CSI / CDT-aligned references (no links):
CSI Construction Specifications Practice Guide – sections on Division 01, Submittals, and Requirements for Administrative Submittals (including preconstruction submittals).
CSI Project Delivery Practice Guide – chapters on Construction Phase and construction submittal processes.
CDT Exam Content Outline – topics on “Submittals,” “Division 01 – General Requirements,” and “Contract Administration documentation.”
How long after bid opening is a bidder required to honor their bid price for a project?
It should be no less than the time period acknowledged on the bid form.
The time period is thirty days for a private project and indefinitely for a public project.
The time period should conform to requirements set by the Associated General Contractors of America.
The time period as established by the contract for construction.
In CSI’s procurement framework, the bidding documents (especially the Instructions to Bidders and the Bid Form) specify the time period during which a bid must remain open and may not be withdrawn.
CSI emphasizes:
The bid is an offer by the bidder, and the bidding documents define how long that offer is to remain valid.
This period is stated in the bidding requirements, and bidders acknowledge it by signing and submitting the bid form.
Common durations (e.g., 30, 60, or 90 days) are project-specific and are not fixed universally by CSI or any trade association.
Therefore, a bidder is required to honor their bid for no less than the time period that is explicitly stated and acknowledged on the bid form and in the bidding requirements, which corresponds to Option A.
Why the other options are incorrect:
B. Thirty days for private projects and indefinitely for public projectsCSI does not set such a rule. Both public and private owners typically state a specific time limit in the bidding documents. Public contracts often have statutory or policy-based periods, but never “indefinitely.”
C. Requirements set by the Associated General Contractors of AmericaAGC publishes standard forms and guidance, but the binding requirement for bid validity comes from the owner’s bidding documents, not from AGC’s generic recommendations.
D. As established by the contract for constructionAt the time of bidding, there is no executed construction contract yet. The bid validity period must be set before the contract is formed, in the bidding documents themselves. The construction contract applies only after the bid is accepted.
Key CSI Reference Titles (no links):
CSI Project Delivery Practice Guide – Procurement Phase, “Instructions to Bidders” and “Bid Form.”
CSI Construction Specifications Practice Guide – Bidding requirements and bid validity.
CDT Body of Knowledge – “Bidding and Negotiation; Contractor Selection.”
What can value analysis be used for?
To provide the owner with the lowest construction cost.
To enhance project value or reduce initial or long-term cost.
A phase for future work to allow higher quality items up front.
To change the perceived value by owner and stakeholder.
CSI uses the term value analysis or value engineering to describe a structured, function-oriented process that examines the relationship between:
The functions a building element or system must perform, and
The cost of achieving those functions
The objective is to improve value, which can mean:
Reducing initial cost without reducing required performance or quality
Reducing life-cycle cost (operation, maintenance, replacement)
Improving performance, quality, durability, or maintainability for a similar cost
Therefore, value analysis can be used:
“To enhance project value or reduce initial or long-term cost.” (Option B)
CSI stresses that value analysis is not simply “cheapening” the project; it is a disciplined decision-making process that balances cost and function to achieve the best overall value for the owner.
Why the other options are not correct in CSI terms:
A. To provide the owner with the lowest construction cost.The lowest first cost is not the sole or primary goal under CSI’s view. An excessively low first cost may sacrifice performance or significantly increase operation and maintenance costs. Value analysis focuses on best value, not just cheapest construction.
C. A phase for future work to allow higher quality items up front.Value analysis is a process or technique, not merely a “phase for future work.” It also does not inherently mean you always choose higher quality up front; sometimes it leads to lower initial cost, sometimes to better performance, sometimes a balance.
D. To change the perceived value by owner and stakeholder.While owner and stakeholder perception matters, CSI presents value analysis as a technical, function-and-cost-based method, not just a way to change perceptions. The goal is objective improvement of value, not merely altering how the project is perceived.
Key CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – sections on Value Analysis/Value Engineering in design and preconstruction phases.
CSI CDT Body of Knowledge – topics on cost, value, life-cycle thinking, and decision-making.
CSI-related discussions of life-cycle cost and value in project decision processes.
Which meeting is held for the purposes of introducing the design and construction teams, establishing the ground rules for communication, and explaining the administrative process?
Mobilization meeting
Preconstruction meeting
Prebid meeting
Coordination meeting
In CSI’s project delivery framework, the preconstruction meeting (often called the preconstruction conference) is a formal meeting held after award of the construction contract and before substantial field work begins. Its typical purposes match the stem of this question almost word-for-word:
Introduce the key members of the owner’s team, the design team, and the contractor’s team.
Review and establish communication protocols – who communicates with whom, in what format (letters, emails, RFIs, submittals), and through which channels (e.g., via the A/E as the owner’s representative).
Explain administrative procedures for submittals, RFIs, change orders, applications for payment, project meetings, record documents, and closeout requirements.
Clarify roles and responsibilities, lines of authority, and decision-making processes during construction.
Review the project schedule, major milestones, site logistics, and constraints so everyone begins the project with a common understanding.
These points are fully consistent with how CSI’s Project Delivery Practice Guide and typical Division 01 “Project Management and Coordination” sections describe the preconstruction conference: as the kickoff meeting for the construction phase, focused on communication, procedures, and administration—not bidding or detailed technical coordination.
Why the other options are not correct:
A. Mobilization meeting“Mobilization” refers to the contractor’s process of moving onto the site (bringing in equipment, setting up field offices, etc.). While a project might have discussions about mobilization, “mobilization meeting” is not the standard CSI project-delivery term for this formal kickoff. The structured, procedure-focused meeting described in the question is the preconstruction meeting.
C. Prebid meetingA prebid meeting (pre-bid conference) occurs during procurement, before bids are submitted. Its primary purposes are to familiarize prospective bidders with the project, review procurement requirements, visit the site, and answer questions that might affect bids. It does not introduce the already-selected construction team, nor does it establish the project’s communication and administrative procedures for contract execution. That occurs after award in the preconstruction meeting.
D. Coordination meetingCoordination meetings are typically recurring, working meetings during construction to resolve ongoing technical, scheduling, or coordination issues between trades (e.g., MEP coordination). They do not serve as the initial, formal kickoff to introduce teams and set overall administrative and communication “ground rules.”
Therefore, the meeting that introduces the design and construction teams, sets communication ground rules, and explains administrative processes is the Preconstruction meeting (Option B), as aligned with CSI project delivery and Division 01 practices.
Key CSI References (titles only, no links):
CSI Project Delivery Practice Guide – chapters on Construction Phase and Project Meetings (Preconstruction Conference).
CSI Construction Specifications Practice Guide – discussions of Division 01 “Project Management and Coordination” and required project meetings.
CSI CDT Body of Knowledge – topic area: “Construction Phase Services and Communication.”
What is the term used to describe the time it takes to procure an item on site?
Estimated time of arrival
Procurement time
Lead time
Manufacturing time
In CSI’s project delivery and construction phase discussions, the time between ordering an item and its arrival on the project site ready for use is referred to as “lead time.”
For construction planning and scheduling, lead time is critical because:
It affects when submittals must be prepared, reviewed, and approved.
It determines when purchase orders must be issued to avoid delays.
Long-lead items (such as custom equipment, certain mechanical/electrical components, curtain wall systems, etc.) must be identified early so the project schedule can accommodate them.
Among the options:
Lead time (Option C) is the established term for this procurement interval.
Why the other options are incorrect:
A. Estimated time of arrival“Estimated time of arrival” (ETA) may be used informally in logistics, but CSI’s scheduling and procurement discussions specifically use “lead time” for the planning parameter from order to arrival.
B. Procurement time“Procurement time” is a generic phrase, not a defined CSI term. In practice, procurement may include internal approvals, budgeting, and other steps beyond the order-to-arrival period.
D. Manufacturing timeManufacturing time is only one component of lead time (which might also include design, submittal, shipping, customs, etc.). It does not necessarily cover the full period until the item is on site.
Key CSI Reference Titles (no links):
CSI Project Delivery Practice Guide – chapters on Construction Phase scheduling and procurement/lead times.
CSI Construction Specifications Practice Guide – Division 01 scheduling and submittals, including handling of long-lead items.
CSI CDT Body of Knowledge – “Construction Phase: Schedule, Submittals, and Procurement.”
When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?
The architect/engineer/owner team can consider bid listing and bid depository provisions.
Require bidders to provide a list of their intended subcontractors along with their bid.
The subcontractor can withhold their prices from the bidder until the final moments before the deadline.
The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.
Within the CSI / CDT framework, bid shopping is the practice of a prime bidder (typically a general contractor) using one subcontractor’s price to pressure that subcontractor or competitors into lowering their price after bids have been received. CSI treats this as an unethical and undesirable practice that increases risk and undermines fair competition in the procurement process.
Practices that help minimize bid shopping include:
Bid listing and bid depository provisions (Option A):Some public agencies require that the general contractor list major subcontractors with the bid or use a bid depository system. These mechanisms are intended specifically to discourage bid shopping by locking in the subcontractors named at bid time and making the process more transparent.
Requiring bidders to provide a list of intended subcontractors with their bid (Option B):This is another form of sub-bid listing. By compelling the prime bidder to identify subcontractors at bid submission, it restricts their ability to shop sub-bids afterward, thereby minimizing the risk of bid shopping.
Subcontractors withholding their prices until close to bid time (Option C):While not ideal from a coordination standpoint, this is a common subcontractor strategy in a competitive environment to reduce the time window during which a prime contractor can use their number to shop for a lower price. This can mitigate bid shopping risk from the subcontractor’s perspective.
By contrast:
D. The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.This is essentially a description of bid shopping behavior. Asking a subcontractor to “re-evaluate” to get a lower price after their number has been used to compile the bid (especially when using other subs’ prices as leverage) is exactly what public procurement provisions try to prevent. This does not minimize the risk of bid shopping; it is bid shopping.
Therefore, the only option that clearly does not reduce or prevent bid shopping is D.
Relevant CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – Procurement and Bidding chapters (discussion of competitive bidding ethics and bid shopping).
CSI CDT Body of Knowledge – Procurement and bidding procedures and ethical practices in public work.
Which entity maintains project record documents?
Architect/engineer (A/E)
Contractor
Owner
Owner or A/E
CSI distinguishes between “project record documents” (kept during construction) and record drawings or as-built drawings (often prepared later by the A/E using the contractor’s markups).
In CSI’s terminology (paraphrased from the Construction Specifications Practice Guide and CDT study materials):
Project record documents consist of the marked-up drawings, specifications, addenda, change orders, and shop drawings kept current during construction, indicating actual conditions and changes in the work.
These record documents are a responsibility of the contractor, who must maintain them on the job site and update them as work progresses.
At project closeout, the contractor turns the updated record documents over to the owner (often via the A/E). The A/E may then prepare record drawings based on those markups, if required by the contract.
Therefore, the entity that maintains project record documents during construction is the Contractor, making Option B correct.
Why the other options are not correct:
A. Architect/engineer (A/E) – The A/E reviews the work and may use the contractor’s record documents to prepare record drawings, but does not maintain the working set of record documents during construction.
C. Owner – The owner ultimately receives and keeps the record documents at the end of the project but does not maintain them as the work progresses.
D. Owner or A/E – This option is inconsistent with CSI’s defined responsibility: maintenance of project record documents is specifically assigned to the contractor in standard specifications and conditions of the contract.
CSI References (no links):
CSI Construction Specifications Practice Guide – sections on project record documents, as-built/record drawings, and contractor responsibilities.
CSI CDT Body of Knowledge – topic on document control and record documents during the construction phase.
Which of the following is a component of project design team coordination during the construction documents phase?
Duplication of important information by each discipline
Ensuring drawing note terminology is differentiated from specification terminology
Requiring the owner to hire a third-party to write the Division 01 specifications independently
Quality assurance tasks shared between design and consulting teams
During the construction documents phase, CSI’s guidance emphasizes that coordination between the architect/engineer (A/E) and the various consulting disciplines (structural, mechanical, electrical, etc.) is essential to produce consistent, coordinated, and complete contract documents (drawings, specifications, and project manual). Part of that coordination is a shared quality assurance (QA) effort among the design team members.
In CSI’s practice guides and CDT body of knowledge, the following principles are stressed (paraphrased to respect copyright):
The prime design professional is responsible for overall coordination of the construction documents, but each consultant is responsible for the technical accuracy and coordination of their own portions.
Coordination includes review of cross-references, matching terminology, alignment of requirements between drawings and specifications, and resolving conflicts before bid/issue.
Quality assurance during this phase is not done in isolation; it is a team activity. Consultants and the lead design firm review each other’s work where it interfaces (e.g., architectural and mechanical coordination of ceilings and diffusers; structural and architectural coordination of openings, etc.).
Therefore, “Quality assurance tasks shared between design and consulting teams” (Option D) correctly describes a standard component of project design team coordination during the construction documents phase.
Why the other options are incorrect:
A. Duplication of important information by each disciplineCSI stresses “say it once, in the right place” as a fundamental principle. Information should not be unnecessarily duplicated because duplication increases the risk of conflict and inconsistency (for example, a requirement shown in both drawings and multiple spec sections but updated in only one location). Coordination aims to avoid duplication, not to promote it.
B. Ensuring drawing note terminology is differentiated from specification terminologyCSI emphasizes consistent terminology across drawings, specifications, and other documents. The same items (e.g., “gypsum board,” “reinforcing steel,” “membrane roofing”) should be described using the same terms in both drawings and specifications to reduce ambiguity. Coordination meetings often include checking that terminology is aligned, not intentionally differentiated.
C. Requiring the owner to hire a third-party to write the Division 01 specifications independentlyDivision 01 – General Requirements – is typically prepared or controlled by the lead design professional or specifier, in coordination with the owner. CSI materials do not identify it as a standard or required coordination practice for the owner to hire an independent third party to write Division 01 separately from the design team. That may occur on some projects, but it is not a defined component of team coordination in CSI’s CDT framework.
In summary, CSI-based construction documentation practice defines coordination during the construction documents phase as a shared responsibility among the architect/engineer and all consultants, including joint quality assurance reviews, consistency checks, and cross-discipline coordination. This aligns directly with Option D.
Key CSI References (no links):
CSI Project Delivery Practice Guide – chapters on Design Phase and Construction Documents coordination.
CSI Construction Specifications Practice Guide – sections on coordination between drawings and specifications and the role of Division 01.
CSI CDT Body of Knowledge – topics on roles and responsibilities of the design team and coordination of construction documents.
An electrical engineer completes a set of electrical drawings and specifications for a project, except for the site electrical work which is indicated on the civil drawings. Which of the following is the intent of the contract documents?
The civil contractor is to place the concrete bases and the electrical contractor is to install the site lighting.
The civil contractor is to place the concrete bases and the site lighting, with the electrical contractor making the final connections.
The general contractor needs to coordinate the work and verify that the electrical subcontractor bids the site electrical.
The electrical engineer does not need to control how the work is to be assigned to subcontractors.
CSI’s core principle is that contract documents describe the work results required, not the internal means, methods, or subcontracting arrangements of the contractor. The contractor (or construction manager) is responsible for:
Determining how the work will be divided among trades and subcontractors.
Coordinating different trades to achieve the required results shown on the drawings and described in the specifications.
Design professionals (architects and engineers):
Organize the documents by disciplines and work results (e.g., civil, architectural, electrical), not by subcontractor or trade contract structure.
Are not responsible for dictating which subcontractor performs which portion of the work; that is the contractor’s role.
Given that:
Site electrical work appears on civil drawings, but the electrical engineer has also prepared electrical documents for the building systems.
The intent of the contract documents is still to describe what must be installed and how it must perform, not which subcontractor does it.
The only option that aligns with CSI’s stated roles and responsibilities is:
D. The electrical engineer does not need to control how the work is to be assigned to subcontractors.
Why the other options are not the “intent” of the documents:
A. The civil contractor is to place the concrete bases and the electrical contractor is to install the site lighting.This presumes a specific trade split based on drawing origin. CSI emphasizes that the contractor determines trade assignments, not the drawings themselves.
B. The civil contractor is to place the concrete bases and the site lighting, with the electrical contractor making the final connections.Again, this dictates trade assignments. The documents may show coordination between civil and electrical work, but do not prescribe how contractors must divide their subcontracts.
C. The general contractor needs to coordinate the work and verify that the electrical subcontractor bids the site electrical.While coordination of work is indeed a contractor responsibility, the phrasing here implies that the documents intend to direct which subcontractor must price which work package. CSI’s standpoint is that the contractor is free to structure subcontract bids as they see fit, as long as the required work is provided in accordance with the contract.
Thus, the intent of the contract documents is to define the required end results, not to assign work scopes among subcontractors. Option D correctly reflects that intent and the design professional’s role.
Relevant CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – roles and responsibilities of owner, design professional, and contractor; explanation that contractor controls means, methods, and subcontracting.
CSI Construction Specifications Practice Guide – distinction between describing work results and assigning work trades.
CSI CDT Body of Knowledge – contract document intent vs. contractor’s responsibility for dividing the work.
During the project closeout phase, what is an appropriate task for the facility manager?
To ensure they have received the required spare parts, extra stock materials, and any necessary training needed in order to maintain the facility in the first year
To coordinate with the architect a final clean-up and site restoration
To hire a new security company to ensure maintenance and ground management
To draft the final changes on the as-built documents
CSI describes the facility manager as a key stakeholder during project closeout and turnover. Their role is to receive the information, materials, and training needed to operate the completed facility in accordance with the Owner’s Project Requirements (OPR).
Typical responsibilities for the facility manager at closeout, as outlined in CSI’s Project Delivery Practice Guide, include (paraphrased):
Participating in commissioning and training sessions.
Verifying receipt of operation and maintenance (O&M) manuals, warranties, and record documents.
Confirming that required spare parts, attic stock/excess materials, and special tools have been delivered.
Ensuring staff have sufficient training to operate building systems during the initial occupancy period.
This is captured best by Option A, which aligns closely with CSI’s description of closeout responsibilities for the facility manager.
Why the other options are not correct:
B. Coordinate with the architect a final clean-up and site restoration – Final cleaning and site restoration are responsibilities of the contractor, overseen by the A/E and owner. The facility manager may observe but is not normally the one coordinating this work in the contract documents.
C. Hire a new security company – Selecting or changing service vendors (like security firms) is an owner/facility operations business decision, not specifically identified in CSI’s project closeout procedures. It is not a standard closeout task defined in the construction documents.
D. Draft the final changes on the as-built documents – CSI differentiates between “project record documents” maintained by the contractor during construction and record drawings/specifications produced by the A/E (when required). The facility manager receives these but does not normally draft or edit them.
CSI References (no links):
CSI Project Delivery Practice Guide – chapters on Construction Phase and Facility Management/Closeout.
CSI Construction Specifications Practice Guide – sections on project closeout, O&M data, and attic stock.
What could a reference standard specification be based upon?
Project manual for similar project
Design intent
Trade association standard
Manufacturer's specification section
CSI identifies several types of specifications, including:
Descriptive specifications – describe materials and methods in detail.
Performance specifications – describe required results and performance criteria.
Proprietary specifications – designate specific products or manufacturers.
Reference standard specifications – define requirements by citing recognized industry standards rather than repeating all technical details.
A reference standard specification works by referring to standards issued by organizations such as:
Trade associations (e.g., industry associations),
Standards organizations (e.g., ASTM, ANSI, ISO),
Other recognized bodies that publish consensus technical standards.
The specification then simply states that materials, products, or work must comply with the named standard. This reduces repetition and promotes consistency and clarity.
Therefore, a proper basis for a reference standard specification is a trade association standard, which is Option C.
Why the other options are incorrect:
A. Project manual for similar projectPrevious project manuals may be informal references for the specifier, but they are not recognized standards. A reference standard specification must refer to a published technical standard, not another project’s contract documents.
B. Design intentDesign intent is expressed more directly in performance or descriptive specifications, not in reference standard form. Reference standards rely on external, recognized standards, not internal design intent statements alone.
D. Manufacturer's specification sectionReferring to a specific manufacturer’s literature or section is characteristic of a proprietary specification, not a reference standard specification. Reference standards must be based on independent, consensus-based standards, not one manufacturer’s materials.
Key CSI Reference Titles (no links):
CSI Construction Specifications Practice Guide – Types of specifications, including reference standard specifications and their proper use.
CSI Project Delivery Practice Guide – Relationship of specifications to industry standards.
CDT Body of Knowledge – “Specification Types and Methods of Specifying.”
How does the architect/engineer control the project cost when not enough information is available to make product decisions during the design phases of a project?
Alternates
Unit prices
Contingencies
Allowances
CSI identifies several cost-control tools used in specifications and bidding documents:
Alternates – provide optional changes in scope or quality that can add or deduct cost.
Unit prices – establish prices for specific items or quantities where exact amounts may vary.
Contingencies – funds reserved by the owner (in the project budget) for unexpected conditions.
Allowances – specified amounts included in the contract sum for items whose exact product, quantity, or selection is not yet known at bid time.
When insufficient information is available to make final product decisions during design, CSI’s guidance is that the A/E can maintain control over construction cost by specifying allowances. An allowance:
Is clearly described in the specifications or Division 01.
Provides a defined monetary amount (or quantity and unit cost) for a future selection (for example, certain finishes, fixtures, or equipment).
Allows the project to proceed to bidding and contract award while preserving cost control, because bidders all carry the same allowance values in their bids.
Thus the best answer is D. Allowances.
Why the other options are less appropriate:
A. AlternatesAlternates help manage scope and options, but they do not directly solve the problem of not yet knowing which specific product will be chosen. They are more about “add or deduct” scenarios than uncertain product selection.
B. Unit pricesUnit prices are used when quantities are uncertain, not when product decisions themselves are unknown. They are tied to measurable units (e.g., cubic meters of rock excavation), not to undecided product choices.
C. ContingenciesContingencies are normally an owner’s budgeting tool, not written into the contract in the same way as allowances. They help the owner plan for unknowns but do not provide a structured way in the specifications to carry costs for undecided products.
Key CSI Reference Titles (no links):
CSI Project Delivery Practice Guide – sections on Cost Management and Design Phase cost-control tools.
CSI Construction Specifications Practice Guide – Division 01 provisions for Allowances, Alternates, and Unit Prices.
CSI CDT Body of Knowledge – “Methods of Specifying and Cost Control Provisions in the Project Manual.”
Top of Form
Bottom of Form
Which of the following elements should be included in Supplementary Conditions?
Requirements for a schedule of values
Claims and dispute resolution requirements
Equal employment opportunity requirements
Termination of the work by owner or contractor
CSI organizes the contract documents into a logical hierarchy:
General Conditions – Standard baseline clauses on rights, responsibilities, procedures (e.g., claims, dispute resolution, termination, payments, schedule of values reference).
Supplementary Conditions – Project-specific modifications or additions to the General Conditions, often driven by laws, funding requirements, or owner policies.
Division 01 – General Requirements – Administrative and procedural requirements specific to the project (submittals, schedule of values procedures, temporary facilities, etc.), coordinated with the Conditions of the Contract.
CSI’s guidance (as used for CDT) explains that Supplementary Conditions are the place to add or modify contract conditions to comply with local laws, regulations, and owner requirements that go beyond or differ from the standard General Conditions. Typical items include:
Project-specific insurance requirements and limits,
Local wage requirements,
Equal Employment Opportunity (EEO) and affirmative action provisions,
Special regulatory or funding-agency conditions.
Therefore, Equal Employment Opportunity requirements belong properly in Supplementary Conditions, making Option C the CSI-consistent answer.
Why the others are incorrect in CSI’s structure:
A. Requirements for a schedule of valuesCSI places the detailed procedures and requirements for the schedule of values in Division 01 – General Requirements, not in the Supplementary Conditions. The General Conditions may mention the schedule of values at a high level, but the “how to” (formats, breakdown, submission procedures) belongs in Division 01, not Supplementary Conditions.
B. Claims and dispute resolution requirementsStandard claims and dispute resolution clauses are part of the General Conditions (for example, notice requirements, initial decision-maker roles, mediation/arbitration steps). Supplementary Conditions may modify certain aspects if needed, but the base provisions themselves are not created there; they originate in the General Conditions.
D. Termination of the work by owner or contractorTermination rights (for cause or for convenience) and their procedures are fundamental contract provisions that belong in the General Conditions. Like claims, they can be adjusted in Supplementary Conditions, but the primary termination clauses are part of the standard General Conditions text, not something you “include” first in Supplementary Conditions.
Key CSI-aligned references (no links):
CSI Construction Specifications Practice Guide – chapters on the Conditions of the Contract and the roles of General and Supplementary Conditions.
CSI CDT Body of Knowledge – organization of the Project Manual and correct placement of Division 01, General Conditions, and Supplementary Conditions content.
Which of the following is a component of the contract documents?
Procurement requirements
Resource drawings
Shop drawings
Addenda
CSI defines the contract documents as the documents that form the legally binding contract between the owner and the contractor. These typically include:
Agreement (contract form)
Conditions of the Contract (General and Supplementary)
Drawings
Specifications
Addenda (issued before contract execution, modifying bidding documents)
Modifications (issued after execution — change orders, CCDs, etc.)
Thus, addenda, once issued prior to contract signing, become a binding part of the contract documents.
Why others are incorrect:
A. Procurement requirements – These include instructions to bidders, bid forms, and similar pre-contract information; once the contract is executed, they are not part of the contract documents.
B. Resource drawings – Background reference materials only; not contractually binding.
C. Shop drawings – Prepared by the contractor/subcontractors for review and coordination; not part of the contract documents, even after A/E review.
CSI Reference:
CSI Project Delivery Practice Guide, “Procurement and Contracting”; Construction Specifications Practice Guide, “Definition of Contract Documents.”
Which of the following statements best describes stakeholder and participant interest in a project?
Participants have direct interest in the project while stakeholders have indirect interest
Stakeholders have direct interest in the project while participants have indirect interest
Both stakeholders and participants have direct interest in the project
Both stakeholders and participants have indirect interest in the project
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
In CSI/CDT terminology, there is an important distinction between participants and stakeholders in a project:
Project participants are those who are formally part of the project delivery process, typically through a contractual or professional role. Examples: the owner, architect/engineer, contractor, and sometimes construction manager, commissioning authority, or key consultants. They:
Have direct responsibilities for planning, designing, constructing, administering, or managing the facility.
Are directly affected by project decisions and outcomes under the contracts and agreements.
Stakeholders are a broader group of parties who have an interest in the project, but many of them are not directly involved in performing the work or administering the contract. Examples include:
Users/occupants
Neighbors and surrounding community
Authorities having jurisdiction (from a public-interest standpoint)
Facility management staff, investors, or the general public
Their interest is often indirect—they are affected by the project’s performance, appearance, safety, cost, or impact, but they are not all active participants in day-to-day project execution or contract administration.
Because of this CSI distinction:
Participants → direct interests (active roles)
Stakeholders → often indirect interests (affected by, but not always performing, the work)
That matches Option A: Participants have direct interest in the project while stakeholders have indirect interest.
Key CSI-Related References (titles only, no links):
CSI Project Delivery Practice Guide – discussions of project participants vs. stakeholders and their roles throughout the facility life cycle.
CSI CDT Exam Study Materials – sections defining owner, design professional, contractor as participants, and users/community as stakeholders.
Which member of the project team initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding?
Contractor
Designer
Supplier
Owner
CSI’s description of project roles is very clear about the owner’s role in project delivery:
The owner is the party that:
Identifies the need or opportunity and therefore initiates the project.
Provides the funding for design and construction.
Retains the design and construction teams and selects the project delivery method.
Ultimately assumes the primary financial and project risk, because the owner is the one investing in and depending on the completed facility.
In contrast:
The designer (architect/engineer) is responsible for planning and design, preparing construction documents, and administering the construction contract on the owner’s behalf, but does not typically initiate the project or provide funding.
The contractor is responsible for constructing the project in accordance with the contract documents; the contractor bears construction execution risk, but not the basic project-initiative and funding role.
Suppliers provide materials/equipment and have no overarching control over the project delivery process.
The question lists all of the characteristics that CSI attributes to the owner:
“initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding.”
Thus, the correct answer is Option D – Owner.
CSI references (by name only, no links):
CSI Project Delivery Practice Guide – “Participants in Project Delivery” (owner, designer, constructor, suppliers)
CDT Body of Knowledge – descriptions of owner responsibilities and risk
What is Leadership in Energy and Environmental Design® (LEED®)?
A set of sustainable standards with measurable recognized categories for a project
A formula for determining a sustainable classification
A system of prioritizing sustainable projects
Standardized structure for organizing sustainable information
Leadership in Energy and Environmental Design (LEED) is not just a vague label or a single formula. It is a comprehensive green building certification system with defined categories and measurable credits.
Official and technical descriptions of LEED explain that:
LEED is a green building certification program developed by the U.S. Green Building Council (USGBC).
It “includes a set of rating systems” for the design, construction, operation, and maintenance of buildings, homes, and neighborhoods, with the aim of helping building owners be environmentally responsible and use resources efficiently.
The LEED Rating System is organized into specific categories (e.g., Sustainable Sites, Water Efficiency, Energy and Atmosphere, Materials and Resources, Indoor Environmental Quality, Innovation in Design, Regional Priority), and projects obtain credits in these areas to achieve certification at levels such as Certified, Silver, Gold, or Platinum.
These features match Option A:
A set of sustainable standards with measurable recognized categories for a project
LEED provides:
Standardized criteria and prerequisites
Credit categories and point scoring
Recognized certification levels
Why the other options are incorrect:
B. A formula for determining a sustainable classification – LEED is not a single “formula”; it is a multi-category rating system with many credits and requirements.
C. A system of prioritizing sustainable projects – LEED does not decide which projects to build; instead, it evaluates how sustainably a given project is designed and built, and then certifies it based on points.
D. Standardized structure for organizing sustainable information – That description more closely resembles what MasterFormat/UniFormat do for organizing specification information. LEED is a certification/rating system, not a document-organization standard.
In CSI practice, LEED-related requirements (such as credit strategies, submittals, and performance criteria) are typically addressed in:
Division 01 – General Requirements (e.g., “Sustainable Design Requirements”), and
Appropriate technical sections (material content, VOC limits, energy performance, etc.),
but LEED itself is correctly defined as a structured green building rating system with measurable categories and credits—Option A.
Core CSI-aligned references for this question (no URLs):
USGBC/LEED descriptions: LEED as a green building certification program and set of rating systems.
LEED Rating System explanations: category list and credit/point structure.
CSI Project Delivery and Construction Specifications Practice Guides – sections on specifying sustainable design and referencing LEE
Within the context of the construction industry, what does BIM stand for?
Building Information Modeling
Business Information Manual
Building Interior Maintenance
Building Inspection Manual
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In CSI’s project delivery and documentation discussions, BIM is consistently defined as “Building Information Modeling.”
CSI describes BIM as:
A digital representation of the physical and functional characteristics of a facility.
A shared knowledge resource for information about a facility, forming a reliable basis for decisions during its life cycle.
A tool that supports coordination, clash detection, documentation, quantity takeoff, and communication between design and construction team members.
BIM models are used alongside, and coordinated with, drawings, specifications, and other contract documents, and they support communication and decision-making throughout design, construction, and sometimes operation.
The other options are not recognized industry meanings of BIM:
B. Business Information Manual – not a standard construction-industry term.
C. Building Interior Maintenance – does not match CSI or industry definitions of BIM.
D. Building Inspection Manual – again, not the accepted meaning of BIM in the AEC context.
Therefore, in the construction context, BIM stands for “Building Information Modeling” (Option A).
Key CSI References (titles only):
CSI Project Delivery Practice Guide – chapters addressing BIM and information management.
CSI Construction Specifications Practice Guide – discussions of model-based delivery and coordination with specifications.
CSI CDT Body of Knowledge – terminology and emerging practices including BIM.
Under SectionFormat®, where would the Article "Manufacturers" be found?
Either Part 1 or Part 2
Part 1 only
Part 2 only
Part 3 only
CSI’s SectionFormat® establishes a standard three-part structure for specification sections:
Part 1 – GeneralAdministrative and procedural requirements specific to that section (scope, related work, references, submittals, quality assurance, delivery/storage, warranties, etc.).
Part 2 – ProductsDescriptions of products, materials, and equipment required: manufacturers, materials, components, fabrication, finishes, performance requirements, and similar.
Part 3 – ExecutionField/application/installation requirements: examination, preparation, installation/application procedures, tolerances, field quality control, adjustment, cleaning, protection, etc.
Within this structure, CSI specifically places “Manufacturers” as an article in Part 2 – Products. This is because Part 2 is where the specifier identifies:
Acceptable manufacturers or manufacturer list
Standard products and models
Performance or quality requirements associated with those manufacturers
Product substitutions (if addressed by article structure)
Placing “Manufacturers” in Part 2 maintains consistency across specs and makes it clear that manufacturer-related information is part of the product requirements, not administrative conditions or execution procedures.
Why the other options do not align with SectionFormat®:
A. Either Part 1 or Part 2Although some poorly structured sections in practice may misplace content, CSI’s recommended SectionFormat® is explicit: manufacturers belong in Part 2 – Products. Allowing Part 1 or Part 2 would blur the distinction between administrative requirements and product requirements.
B. Part 1 onlyPart 1 is not intended for listing manufacturers. It covers general/administrative topics, not the specific products or manufacturers.
D. Part 3 onlyPart 3 deals with execution/installation in the field, not who manufactures the products. Manufacturer listing in Part 3 would conflict with CSI’s structure and make the section harder to interpret and coordinate.
Therefore, under SectionFormat®, the correct location for the “Manufacturers” article is Part 2 only (Option C).
Key CSI References (titles only, no links):
CSI SectionFormat® and PageFormat™ (official CSI format document).
CSI Construction Specifications Practice Guide – chapters explaining the three-part section structure and where to place specific articles such as “Manufacturers.”
CSI MasterFormat®/SectionFormat® training materials used for CDT preparation.
What does Divisions 02-49 of the construction project manual address?
Procurement instructions
Distinct work results areas
Temporary facilities and controls
Life cycle activities
In CSI’s MasterFormat® system, the project manual’s specifications are organized into Divisions 00–49:
Division 00 – Procurement and Contracting Requirements (instructions to bidders, bid forms, owner–contractor agreement, etc.)
Division 01 – General Requirements (administrative and procedural requirements applicable to the whole project, including items like temporary facilities and controls, submittals, project meetings, etc.)
Divisions 02–49 – Technical Specifications
CSI defines Divisions 02–49 as the technical divisions, each of which is organized around a specific work results area (sitework, concrete, masonry, metals, finishes, mechanical, electrical, etc.). Within those divisions, each specification section describes the materials, products, and execution requirements for that particular work result.
Therefore:
A. Procurement instructions – belong in Division 00, not Divisions 02–49.
C. Temporary facilities and controls – are addressed under Division 01 – General Requirements, not Divisions 02–49.
D. Life cycle activities – are not how CSI defines the scope of Divisions 02–49.
The only accurate description of Divisions 02–49 is that they address distinct work results areas, which is Option B.
CSI references (by name only, no links):
CSI MasterFormat® – Numbers and Titles (Introduction and Use)
CSI Construction Specifications Practice Guide, chapters explaining organization of the project manual into Divisions 00–49
Who is responsible for job site security?
Owner
Architect/engineer
Contractor
Construction manager
Under CSI’s project delivery framework and the typical General Conditions of the Contract, the contractor has primary responsibility for:
The means, methods, techniques, sequences, and procedures of construction.
Job site safety and security, including protection of workers, the public, and the work itself.
Controlling access to the site, securing materials and equipment, and complying with safety laws and regulations.
CSI’s CDT materials summarize the allocation of responsibilities this way (paraphrased):
The owner is responsible for providing information, funding, and overall project requirements; the owner does not direct day-to-day site operations or security.
The architect/engineer is responsible for design and contract administration functions such as reviewing submittals, certifying payments, and evaluating change requests—not for job site security or safety control.
The contractor (or construction manager acting as contractor, where applicable) is the party who controls the site and is therefore responsible for job site safety and security.
Even when a construction manager is involved (Option D), CSI and standard general conditions distinguish between a CM as advisor (who advises the owner) and a CM as constructor (who is essentially the contractor). For the exam-style question as written, “contractor” is the single correct generic answer for who is responsible for job site security.
Why the other options are not correct:
A. Owner – The owner does not direct means and methods or daily site activities; shifting site security responsibility to the owner would contradict the usual conditions of the contract.
B. Architect/engineer – The A/E does not control the job site and is not responsible for job site safety/security; this is a repeated CDT exam emphasis to avoid misallocating liability.
D. Construction manager – Only in specific project delivery methods where the CM is also the constructor (CM-at-Risk) does this role overlap with the contractor. The question’s general form points to the contractor as the standard answer in CSI’s framework.
Therefore, in accordance with CSI’s explanation of roles and responsibilities under standard conditions of the contract, the contractor is responsible for job site security, making Option C correct.
What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?
Stipulated sum
Unit price
Cost-plus-fee
Cost-plus-fee with guaranteed maximum price
CSI’s treatment of methods of payment / contract pricing (as used in standard owner–contractor agreements and CDT content) includes several common bases of payment:
Stipulated Sum (Lump Sum)
The contractor agrees to provide the work for a single fixed price.
The price does not change except through formal changes to the work (change orders).
This is the classic “fixed-price” contract form.
Unit Price
The contractor is paid based on measured quantities of work completed multiplied by agreed unit rates.
Final cost depends on actual quantities installed, not a single fixed total.
Cost-Plus-Fee
The owner reimburses actual cost of the work (labor, materials, equipment, etc.) plus a fee (fixed or percentage) as contractor’s compensation.
The final cost is not fixed; it varies with actual costs incurred.
Cost-Plus-Fee with Guaranteed Maximum Price (GMP)
A variation of cost-plus where the total reimbursable cost plus fee is capped at a guaranteed maximum.
Still not the same as a straightforward fixed lump sum; the basis is cost reimbursement up to a cap.
The question specifically asks: “for a fixed price.” In CSI and standard contract terminology, “fixed price” = “stipulated sum” (or lump sum). That is:
The owner and contractor negotiate a single dollar amount for the entire scope of work;
The contractor’s compensation is that stipulated sum, adjusted only by approved changes.
Why the other options are not correct:
B. Unit price – The total cost is not fixed at the time of contracting; it depends on actual installed quantities.
C. Cost-plus-fee – Costs are reimbursed; final price is open-ended and therefore not fixed.
D. Cost-plus-fee with guaranteed maximum price – This sets a cap, but the actual final cost is not a single fixed price; it is “actual cost plus fee” up to the GMP.
Therefore, the correct basis of payment for a fixed-price contract is Stipulated sum (Option A), consistent with CSI’s classification of contract types and standard owner–contractor agreements.
Key CSI References (titles only, no links):
CSI Project Delivery Practice Guide – sections on “Basis of Payment” and contract pricing methods (stipulated sum, unit price, cost-plus, GMP).
CSI CDT Body of Knowledge – Contract Types and Methods of Payment.
Standard owner–contractor agreements discussed in CSI materials (e.g., stipulated sum as the fixed-price form).
When does a project reach substantial completion?
When the project is sufficiently complete to allow its intended use
When the project receives final inspections from the authorities having jurisdiction
When the contractor's final application for payment is approved
When all of the close-out documents have been reviewed and approved
Comprehensive and Detailed Explanation (CSI-aligned, paraphrased)
CSI and commonly used general conditions define Substantial Completion as the stage in the progress of the Work when:
The Work, or a designated portion, is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize it for its intended use.
Important implications in CSI/CDT context:
Substantial Completion is a functional milestone, not simply an administrative or paperwork milestone.
At Substantial Completion:
The Owner can begin using the facility for its intended purpose (e.g., occupy offices, treat patients, teach classes).
The warranty periods typically begin, unless otherwise specified.
The responsibility for utilities, security, and insurance often shifts in whole or in part to the Owner.
Final inspections, final payment, and complete closeout documentation generally occur after Substantial Completion.
So the correct definition is:
A. When the project is sufficiently complete to allow its intended use.
Why the other options are not correct:
B. When the project receives final inspections from the authorities having jurisdiction – AHJ inspections (for occupancy permits, etc.) are important and often coincide with or enable Substantial Completion, but they are regulatory milestones, not the contractual definition itself. Substantial Completion is determined under the contract, usually via certification by the A/E.
C. When the contractor’s final application for payment is approved – That is associated with Final Completion, which occurs after all work (including punch list) is done and all closeout requirements are met. Substantial Completion occurs before final payment.
D. When all of the close-out documents have been reviewed and approved – Closeout submittals (O&M manuals, warranties, as-builts) are typically prerequisites for final payment and Final Completion, not for Substantial Completion.
Key CSI-Related Reference Titles (no links):
CSI Project Delivery Practice Guide – sections on Construction Phase, Substantial Completion, and Final Completion.
CSI Construction Specifications Practice Guide – Division 01 “Closeout Procedures” and “Substantial Completion” articles.
CSI CDT Study Materials – definitions of Substantial and Final Completion.
The general principle to which architects and engineers have a duty to clients and society at large to practice is defined as "taking the same course of action as another reasonable and prudent architect or engineer in the same geographic area would have taken under the same circumstances" is known by what term?
Professional standard of care
Due diligence
Performance based requirement
Spearin doctrine
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
In CSI’s project delivery and contract administration guidance, the architect’s/engineer’s fundamental professional obligation is described in terms of the “standard of care.”
In the context of design and construction:
Professional standard of care is the legal and professional benchmark used to judge the A/E’s performance.
It is commonly defined as: what a reasonable and prudent design professional, with similar training and experience, in the same discipline and geographic area, would have done under similar circumstances.
CSI emphasizes that the A/E does not guarantee a perfect result or an error-free project, but must act with the skill and care ordinarily exercised by professionals practicing under comparable conditions.
This language and concept are used throughout CSI’s CDT body of knowledge when explaining A/E responsibilities, liability, and expectations under the Owner–A/E Agreement and within the General Conditions of the Contract.
Therefore, the principle described in the question exactly matches Option A – Professional standard of care.
Why the other options are incorrect in CSI/CDT context:
B. Due diligence“Due diligence” is a general legal/business term meaning a thorough and careful effort to investigate or act before making a decision (e.g., feasibility studies, site investigations, or reviewing existing conditions). While A/Es certainly must exercise due diligence, the formal, recognized term for the duty described in the question (reasonable and prudent professional in same area and conditions) is the “standard of care,” not “due diligence.”
C. Performance based requirementThis relates to performance specifications, where the documents define the required results or performance criteria (e.g., energy use, strength, capacity), and the contractor or supplier selects means and methods or products to meet those criteria. It is not a legal or professional duty of A/Es, but rather a type of specification language.
D. Spearin doctrineThe Spearin doctrine (from a U.S. Supreme Court case) holds that when the owner provides plans and specifications, the owner implicitly warrants their adequacy; if the contractor constructs the work according to those plans/specifications and the result is defective due to errors in them, the contractor may not be responsible for that defect. This doctrine concerns owner–contractor risk allocation, not the A/E’s professional duty described in the question.
Key CSI-Related References (titles only, no links):
CSI Project Delivery Practice Guide – chapters on Design Professionals’ Roles, Standard of Care, and Liability.
CSI Construction Specifications Practice Guide – discussions on A/E responsibilities in preparing specifications and coordinating documents.
CSI CDT Exam Study Materials – sections addressing professional standard of care and legal concepts affecting design professionals.
Modifications to the contract documents after execution of the owner–contractor agreement include which of the following?
Change order, construction change directive, and field order
Field order, construction change directive, and request for information
Addendum, change order, and request for information
Supplemental instructions, work change directive, and addendum
Under CSI’s project delivery and contract administration framework, once the owner–contractor agreement is executed, the contract documents can only be modified through specific instruments defined in the Conditions of the Contract (General and Supplementary Conditions). These recognized formal modifications include:
Change Orders – Written instruments signed by owner, contractor, and usually the architect/engineer (A/E) that change the contract sum, contract time, or both, and possibly scope.
Construction Change Directives (CCD) (sometimes called Work Change Directives) – Written orders issued typically by the owner or A/E directing a change in the work before agreement has been reached on an adjustment in contract sum or time. They are later converted into a change order once costs/time are agreed.
Minor changes in the work – Often issued by the A/E as field orders or supplemental instructions, used for small changes that do not affect contract time or sum.
Different standard forms use different names (“Architect’s Supplemental Instructions,” “Field Order,” “Work Change Directive”), but CSI’s CDT content treats these as the recognized post-execution modification mechanisms to the contract documents.
Now, look at the choices:
Addendum is used to modify the bidding documents before the owner–contractor agreement is signed, not after.
Requests for Information (RFIs) are used to clarify contract documents, not to modify them; an RFI alone does not change the contract.
Option A is the only one that contains the combination of change order and construction change directive, plus a commonly used term (field order) for a minor change in the work. These three together align with the CSI-recognized instruments for modifying the contract documents after execution.
Why the other options are incorrect:
B. Field order, construction change directive, and request for information – Missing a change order, which is the primary and most formal method of modification. An RFI is not a modification instrument.
C. Addendum, change order, and request for information – Addendum is pre-contract; RFI is not a modification instrument; only the change order is correct here.
D. Supplemental instructions, work change directive, and addendum – While “supplemental instructions” and “work change directive” can be instruments of modification, combining them with addendum (pre-contract) means this set does not correctly describe modifications after execution.
Therefore, A. Change order, construction change directive, and field order best matches the CSI-defined post-execution modification tools.
Which of the following participants is involved in the Integrated Project Delivery (IPD) method?
Authority having jurisdiction
Commissioning agent
Contractor
Inspector
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
Integrated Project Delivery (IPD), as described in CSI’s project delivery materials, is a collaborative project delivery method that:
Involves key project participants early in the project,
Uses shared risk and reward, and
Promotes integration of people, systems, business structures, and practices into a process that optimizes project results.
CSI’s discussion of IPD identifies the core IPD team as typically including:
The Owner
The Architect/Engineer (Design Professional)
The Contractor (often a general contractor or construction manager at risk)
In IPD, the contractor is deliberately brought into the project early, often during conceptual or schematic design, to:
Provide constructability input
Contribute cost estimating and scheduling
Help optimize means and methods and coordinate with major trades
Among the choices given, the participant that is clearly recognized as a primary IPD participant in CSI-oriented explanation of IPD is the:
C. Contractor
Why the other options are not the best answer:
A. Authority having jurisdiction (AHJ)The AHJ (e.g., building department, fire marshal) is always involved in permitting and inspections, regardless of delivery method. However, they are not part of the project’s contractual IPD team, nor do they share in IPD contractual risk/reward structures.
B. Commissioning agentA commissioning agent (or authority) may participate in IPD projects, but is not a mandatory or defining core party. Commissioning can be part of many delivery methods (Design-Bid-Build, CM at Risk, Design-Build, IPD). CSI’s general description of IPD focuses on owner–designer–contractor integration.
D. InspectorInspectors (code inspectors, special inspectors) are similar to the AHJ functions—important to the project but external to the project’s contractual structure and not specific to IPD. They serve regulatory and quality verification roles across all delivery methods.
Thus, in the context of CSI’s explanation of Integrated Project Delivery, the clearly correct answer is Option C – Contractor.
Key CSI-Related References (titles only):
CSI Project Delivery Practice Guide – chapters on Project Delivery Methods and Integrated Project Delivery.
CSI CDT Study Materials – comparisons of Design-Bid-Build, CM at Risk, Design-Build, and IPD, including team composition.
CSI presentations and educational modules on collaborative and integrated delivery methods.
In the MasterFormat® specification system, which subgroup contains requirements of MEP, fire protection, and telecom systems?
Site and Infrastructure Subgroup (Divisions 30–39)
Facility Services Subgroup (Divisions 20–29)
Facility Construction Subgroup (Divisions 02–19)
Part 2 – Products
CSI’s MasterFormat® (2004 and later editions) organizes work results into five major groups, several of which are broken into subgroups. In CDT and CSI materials, the key subgroups are described as follows:
Facility Construction Subgroup (Divisions 02–19) – Covers sitework and building construction elements, such as existing conditions, concrete, masonry, metals, wood, finishes, openings, specialties, equipment, furnishings, conveying systems, fire suppression, plumbing, HVAC (in early editions), and electrical (in divisions 26–28 pre–2010 structure; in more recent updates MEP is consolidated differently but still under “facility services”).
Facility Services Subgroup (Divisions 20–29) – Specifically established to organize mechanical, electrical, plumbing, fire suppression, communications, and related systems—collectively termed facility services.
Site and Infrastructure Subgroup (Divisions 30–39) – Covers civil, site, utility, and infrastructure work, such as earthwork, site utilities, transportation, and similar site/infrastructure elements.
In the modern MasterFormat framework, CSI defines “Facility Services” as the subgroup including divisions for:
Mechanical systems
Electrical systems
Plumbing
Fire suppression / fire protection
Communications and telecom, security, and related low-voltage systems
Therefore, the subgroup that contains MEP (mechanical, electrical, plumbing), fire protection, and telecom systems is:
B. Facility Services Subgroup (Divisions 20–29)
Why the other options are incorrect or incomplete:
A. Site and Infrastructure Subgroup (Divisions 30–39)This subgroup addresses site and infrastructure work, not building internal MEP or telecom systems. Items like site utilities and transportation infrastructure belong here, not typical building MEP systems.
C. Facility Construction Subgroup (Divisions 02–19)This subgroup deals primarily with building fabric and architectural/structural elements (sitework, concrete, masonry, metals, finishes, openings, specialties, etc.). While historically some mechanical/electrical content appeared in lower-number divisions before the 2004 reorganization, in the current CSI structure, MEP and related systems are grouped under Facility Services (20–29), not under Facility Construction.
D. Part 2 – Products“Part 2 – Products” is a component of SectionFormat™, not MasterFormat’s division/group structure. SectionFormat defines the three-part structure of individual specification sections (Part 1 – General, Part 2 – Products, Part 3 – Execution). It doesn’t define which subgroup MEP/telecom systems belong to.
Thus, consistent with CSI’s MasterFormat organization, Option B is the correct answer.
The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?
Cash allowance
Quantity allowance
Unit pricing
Alternates
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI describes several techniques in the procurement documents to manage cost uncertainty. When the owner is concerned that the project may exceed the budget when bids are received, the most common tool to allow scope flexibility is the use of alternates.
Alternates (often called “bid alternates”):
Are defined variations in the work (additions or deletions) that bidders price separately from the base bid.
Can be additive (additional scope that can be accepted if the budget allows) or deductive (scope that can be removed to reduce cost if needed).
Give the owner the ability, after seeing the base bids, to accept or reject alternates to bring the project within the available budget without redesigning the entire project.
This fits the scenario in the question exactly: the owner anticipates that the budget may be tight and wants a mechanism to adjust the final contract amount if bids come in high.
Why the other options are not the primary CSI method for this budget-flexibility issue:
A. Cash allowanceAn allowance is a set amount included in the contract sum to cover a defined but not fully specified portion of the work (e.g., artwork, specialty items). It helps manage scope uncertainty, but it doesn’t systematically provide a way to reduce overall cost after bids in the same way alternates do.
B. Quantity allowanceThis is a form of allowance tied to a presumed quantity (e.g., rock excavation). It addresses uncertain quantities, not overall budget flexibility in the bidding process.
C. Unit pricingUnit prices provide fixed prices per unit (e.g., per cubic meter, per square meter) for work items whose final quantities are uncertain. They are useful for adjustments after contract award as quantities change, but they are not the primary tool for adjusting total scope to meet the owner’s budget at bid time.
Therefore, the CSI-aligned answer for allowing flexibility when bids may exceed the budget is:
D. Alternates
Key CSI-Related References (titles only, no links):
CSI Project Delivery Practice Guide – procurement and pricing strategies, including alternates and allowances.
CSI Construction Specifications Practice Guide – Division 01 sections on Alternates, Unit Prices, and Allowances.
CSI CDT Study Materials – explanations of bid alternates and their role in controlling project cost.
Copyright © 2014-2025 Certensure. All Rights Reserved