Big Cyber Monday Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

Construction Specifications Institute CDT Construction Documents Technologist Exam Practice Test

Demo: 36 questions
Total 120 questions

Construction Documents Technologist Questions and Answers

Question 1

When preparing their bid, a contractor organizes their costs into different categories. The following items are examples of which type of cost?

    Permits and inspections

    Mobilization and startup

    Jobsite safety and security procedures, including personnel

    Administrative costs attributable to the work

Options:

A.

Construction

B.

Contingency

C.

Overhead

D.

Insurance

Question 2

The emphasis shifts from overall relationships and functions to more technical issues during which design phase?

Options:

A.

Preliminary design

B.

Schematic design

C.

Design development

D.

Construction documents

Question 3

Which team member is actively involved and interested in all phases of the project?

Options:

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

Question 4

Which of the following establishes a baseline from which deviations are identified?

Options:

A.

General requirements

B.

Supplementary conditions

C.

Project manual

D.

General conditions

Question 5

The architect/engineer reviews submittals for which of the following reasons?

Options:

A.

To correct or change the design

B.

To monitor design conformance

C.

To review installation procedures

D.

To review substitution requests

Question 6

How do private bidding practices compare or contrast with public bidding practices?

Options:

A.

A private owner may waive any informality in the bidding, except for the performance bond.

B.

Private bids may be opened in private, but the results must be published in a reasonable time.

C.

The laws and regulations for private bidding are the same as for public bidding.

D.

The private owner may award a contract to a responsive and responsible bidder other than the lowest.

Question 7

In the AIA A201 General Conditions of the Contract for Construction, whom is responsible for property insurance for a project?

Options:

A.

Surety, on contractor's behalf.

B.

Owner, unless assigned to contractor.

C.

Owner and contractor, jointly.

D.

Contractor, unless assigned to owner.

Question 8

Lump sum, unit price, and cost-plus-fee are examples of what?

Options:

A.

Delivery method

B.

Bonding system

C.

Basis of payment

D.

Cost estimate

Question 9

Which of the following is an example of preconstruction submittals?

Options:

A.

Product data

B.

Shop drawings

C.

Schedule of values

D.

Warranty documentations

Question 10

How long after bid opening is a bidder required to honor their bid price for a project?

Options:

A.

It should be no less than the time period acknowledged on the bid form.

B.

The time period is thirty days for a private project and indefinitely for a public project.

C.

The time period should conform to requirements set by the Associated General Contractors of America.

D.

The time period as established by the contract for construction.

Question 11

What can value analysis be used for?

Options:

A.

To provide the owner with the lowest construction cost.

B.

To enhance project value or reduce initial or long-term cost.

C.

A phase for future work to allow higher quality items up front.

D.

To change the perceived value by owner and stakeholder.

Question 12

Which meeting is held for the purposes of introducing the design and construction teams, establishing the ground rules for communication, and explaining the administrative process?

Options:

A.

Mobilization meeting

B.

Preconstruction meeting

C.

Prebid meeting

D.

Coordination meeting

Question 13

What is the term used to describe the time it takes to procure an item on site?

Options:

A.

Estimated time of arrival

B.

Procurement time

C.

Lead time

D.

Manufacturing time

Question 14

When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?

Options:

A.

The architect/engineer/owner team can consider bid listing and bid depository provisions.

B.

Require bidders to provide a list of their intended subcontractors along with their bid.

C.

The subcontractor can withhold their prices from the bidder until the final moments before the deadline.

D.

The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.

Question 15

Which entity maintains project record documents?

Options:

A.

Architect/engineer (A/E)

B.

Contractor

C.

Owner

D.

Owner or A/E

Question 16

Which of the following is a component of project design team coordination during the construction documents phase?

Options:

A.

Duplication of important information by each discipline

B.

Ensuring drawing note terminology is differentiated from specification terminology

C.

Requiring the owner to hire a third-party to write the Division 01 specifications independently

D.

Quality assurance tasks shared between design and consulting teams

Question 17

An electrical engineer completes a set of electrical drawings and specifications for a project, except for the site electrical work which is indicated on the civil drawings. Which of the following is the intent of the contract documents?

Options:

A.

The civil contractor is to place the concrete bases and the electrical contractor is to install the site lighting.

B.

The civil contractor is to place the concrete bases and the site lighting, with the electrical contractor making the final connections.

C.

The general contractor needs to coordinate the work and verify that the electrical subcontractor bids the site electrical.

D.

The electrical engineer does not need to control how the work is to be assigned to subcontractors.

Question 18

During the project closeout phase, what is an appropriate task for the facility manager?

Options:

A.

To ensure they have received the required spare parts, extra stock materials, and any necessary training needed in order to maintain the facility in the first year

B.

To coordinate with the architect a final clean-up and site restoration

C.

To hire a new security company to ensure maintenance and ground management

D.

To draft the final changes on the as-built documents

Question 19

What could a reference standard specification be based upon?

Options:

A.

Project manual for similar project

B.

Design intent

C.

Trade association standard

D.

Manufacturer's specification section

Question 20

How does the architect/engineer control the project cost when not enough information is available to make product decisions during the design phases of a project?

Options:

A.

Alternates

B.

Unit prices

C.

Contingencies

D.

Allowances

Question 21

Which of the following elements should be included in Supplementary Conditions?

Options:

A.

Requirements for a schedule of values

B.

Claims and dispute resolution requirements

C.

Equal employment opportunity requirements

D.

Termination of the work by owner or contractor

Question 22

Which of the following is a component of the contract documents?

Options:

A.

Procurement requirements

B.

Resource drawings

C.

Shop drawings

D.

Addenda

Question 23

Which of the following statements best describes stakeholder and participant interest in a project?

Options:

A.

Participants have direct interest in the project while stakeholders have indirect interest

B.

Stakeholders have direct interest in the project while participants have indirect interest

C.

Both stakeholders and participants have direct interest in the project

D.

Both stakeholders and participants have indirect interest in the project

Question 24

Which member of the project team initiates the project, assumes the risk, controls and manages the design and construction process, and provides the funding?

Options:

A.

Contractor

B.

Designer

C.

Supplier

D.

Owner

Question 25

What is Leadership in Energy and Environmental Design® (LEED®)?

Options:

A.

A set of sustainable standards with measurable recognized categories for a project

B.

A formula for determining a sustainable classification

C.

A system of prioritizing sustainable projects

D.

Standardized structure for organizing sustainable information

Question 26

Within the context of the construction industry, what does BIM stand for?

Options:

A.

Building Information Modeling

B.

Business Information Manual

C.

Building Interior Maintenance

D.

Building Inspection Manual

Question 27

Under SectionFormat®, where would the Article "Manufacturers" be found?

Options:

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Question 28

What does Divisions 02-49 of the construction project manual address?

Options:

A.

Procurement instructions

B.

Distinct work results areas

C.

Temporary facilities and controls

D.

Life cycle activities

Question 29

Who is responsible for job site security?

Options:

A.

Owner

B.

Architect/engineer

C.

Contractor

D.

Construction manager

Question 30

What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?

Options:

A.

Stipulated sum

B.

Unit price

C.

Cost-plus-fee

D.

Cost-plus-fee with guaranteed maximum price

Question 31

When does a project reach substantial completion?

Options:

A.

When the project is sufficiently complete to allow its intended use

B.

When the project receives final inspections from the authorities having jurisdiction

C.

When the contractor's final application for payment is approved

D.

When all of the close-out documents have been reviewed and approved

Question 32

The general principle to which architects and engineers have a duty to clients and society at large to practice is defined as "taking the same course of action as another reasonable and prudent architect or engineer in the same geographic area would have taken under the same circumstances" is known by what term?

Options:

A.

Professional standard of care

B.

Due diligence

C.

Performance based requirement

D.

Spearin doctrine

Question 33

Modifications to the contract documents after execution of the owner–contractor agreement include which of the following?

Options:

A.

Change order, construction change directive, and field order

B.

Field order, construction change directive, and request for information

C.

Addendum, change order, and request for information

D.

Supplemental instructions, work change directive, and addendum

Question 34

Which of the following participants is involved in the Integrated Project Delivery (IPD) method?

Options:

A.

Authority having jurisdiction

B.

Commissioning agent

C.

Contractor

D.

Inspector

Question 35

In the MasterFormat® specification system, which subgroup contains requirements of MEP, fire protection, and telecom systems?

Options:

A.

Site and Infrastructure Subgroup (Divisions 30–39)

B.

Facility Services Subgroup (Divisions 20–29)

C.

Facility Construction Subgroup (Divisions 02–19)

D.

Part 2 – Products

Question 36

The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?

Options:

A.

Cash allowance

B.

Quantity allowance

C.

Unit pricing

D.

Alternates

Demo: 36 questions
Total 120 questions