Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?
Participant attendance has been poor at the last few weekly meetings. The project manager wants to validate who the participants should be, how often the meetings should occur, and on which day and at what time the meeting should be held. Which of the following is the best place to validate this information?
Which of the following tools is best to use when conducting project meetings across time zones?
A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
Which of the following best describes a benefit of the CI/CD process?
A team member is not completing deliverables on time or responding to emails while the project manager is on vacation. Which of the following actions should the technical lead take?
During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:
Average worked hours
Which of the following describes the result?
After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
Which of the following is a disadvantage of a cloud model?
A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).
Which of the following is a quality assurance tool?
A project scheduler updates the project status with the following information: SPI = 1.25 and CPI = 0.85. Which of the following can the project manager infer about the current project status?
Which of the following best describes the difference between the current state and the desired future state in project management?
A project manager is comparing the documentation attached to invoices from main vendors with the requirements described in the SOW in order to decide if all are correct. Which of the following best describes what is being performed?
A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?
A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?
A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?
A project team is running into challenges because members are unclear about other members' roles. Which of the following charts should the project manager create?
Which of the following best represents the project impact to a company's brand value?
A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
The project manager must create a project charter. Which of the following should be included in the charter?
A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?
Which of the following should a project manager consult when deciding how to send updates regarding deliverables?
A project manager provided details regarding the completion of the following tasks:
Vendor selection took less time than planned.
Equipment procurement took less time than estimated.
Equipment installation went according to schedule.
Which of the following should the project manager update?
A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?
A company is starting a new implementation project The stakeholders are reviewing RFP responses to help make a decision about which project management consulting firm to hire. Given the following information:
Which of the following is the best consulting firm for the company to hire?
Project team members enter their time sheets into a system that also displays incurred project cost. Which of the following systems can perform this task?
A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?
During project initiation, a project manager needs to establish the communication channel that will be used to deliver weekly presentations to stakeholders who are across the country. Which of the following would be the best communication channel to use?
A project manager is assigned to a project that has contracted with vendors. Which of the following actions should the project manager most frequently take? (Select two).
A project team is deciding how to break up a large project into smaller components so the project can be delivered without increasing the duration of the iteration cycles. Which of the following describes the grouping of the smaller components?
A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?
Which of the following software programs would be BEST to use lo store information related to business transactions?
A software development team completed the development and testing of a new accounting software system for a client. Which of the following should the team do next?
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?
A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?
After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?
Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?
A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?
A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?
The goal of a project is to fulfill specific technical features requested by customers. Which of the following actions should the product owner take?
Which of the following items must be protected as Pll? (Select TWO).
Which of the following PRINCE2 processes includes creating the project plan?
Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?
A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?
An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?
After releasing an application into production, a major defect is detected. The project team implements a work-around that fixes the issue for now. Which of the following should the team do next?
A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?
Which of the following is an intended outcome of a stand-up meeting?
A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?
Which of the following can help identify opportunities for future improvement following the successful closure of a project?
Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?
A retail store is rolling out a new point-of-sale solution to several locations where the staff members normally use cash registers. Which of the following activities will best assist staff members with integrating this new solution? (Select two).
A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?
A company is adapting its strategy almost every quarter, and the product might be different at the end of the project. Which of the following is the best methodology for the project manager to use?
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?
A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?
Which of the following would help a project manager identify that project goals have been reached?
A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).
Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?
A project manager needs to pull data from a burndown chart. Which of the following should the project manager analyze to obtain this data in the most efficient way?
A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
As a result of an internal assessment, the steering committee states that the company does not currently have the required skill set or technical tools to develop a particular feature in the project. Which of the following procurement methods would help the company?
Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?
A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?
During a functional validation exercise, two end users request changes to the product that cannot be implemented without altering the already constrained project budget. The project manager convinces the end users to simplify the change request so it can be accomplished. Which of the following conflict resolution techniques did the project manager use?
A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?
Which of the following is a characteristic that defines a project?
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?
A project manager would like to add external engineers to the current team. Engineers will participate in specific tasks only during the testing phase. Which of the following contracts would the project manager most likely use in this situation?
During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?
A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
Which of the following activities would a project manager perform during the closing phase? (Select THREE).
A client continues to present the project team with additional changes. To help with agreeing upon an expected delivery date, the project manager sets up a meeting with stakeholders. Which of the following should this meeting identify?
During the project initiation phase, a project manager needs to assign individual roles and responsibilities to various team members. Which of the following would best enable them to do so?
Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?
During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?
In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?
During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?
Which of the following provides the best justification for undertaking a project?
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
Which of the following pieces of data are examples of Pll?
A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?
Which of the following is a capital expense?
A project manager requests the testing team to figure out if a website allows multiple users to be signed in at the same time. Which of the following testing methods would be best for the testing team to use?
A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?
Which of the following contract types in project procurement has the highest risk for the buyer?
During the project execution, the sponsor would like to have a visual representation indicating the progress of the project The project is being managed using agile methodologies Which of the following tools would best help the sponsor with the request?
Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?
A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?
A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?
A project sponsor is trying to use the ROI to determine if the project should be approved. Which of the following best describes what the project sponsor needs?
Which of the following best describes the results?
A senior PM is working on the development of a tax application and focuses efforts to create an environment to facilitate and motivate teamwork. The team members seem to be in the storming phase. Which of the following best describes the team life cycle?
A project is not progressing as planned following the departure of the project manager. Which of the following would be the best tool to use to document this information?
A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?
Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?
A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?
A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
During the testing phase of a project, an executive raises a concern about a missing requirement in the product. Which of the following is the next step the project manager should take?
Which of the following considers factors such as reliability, scalability, security, and cost-effectiveness within project goals and objectives?
As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
Which of the following best describes the meaning of timeboxing in the context of a project kickoff meeting?
Which of the following is a potential challenge that may arise from language barriers among a project team?
A project manager is concerned about the performance of a developer who is struggling with the new coding language. Which of the following actions should the project manager take?
Which of the following best describes a program in the context of project management?
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?
During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?
A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?
A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?
To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?
A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?
A project misses a deadline. The project manager creates the following diagram:
Execution: The change control process was not followed. The customer added requests for previously unrequested features. The team developed unnecessary features.
Requirements: The customer did not provide all requirements during the initiation phase.
Which of the following is most likely the root cause of the delay?
A project manager is unclear about the budget and timeline prior to the start of a project. Which of the following best describes what type of meeting needs to take place?
During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?
A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?