Question 1

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

Options:

A.

Start-to-start

B.

Start-to-finish

C.

Finish-to-finish

D.

Finish-to-start

Question 2

Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?

Options:

A.

Send out a survey to the potential end users to gather information about the best functional setup for work productivity.

B.

Provide clear instructions based on personal preference and aesthetics for setup of the work areas.

C.

Explain to team members that the placement of the items is not too important, as long as everything is connected and working.

D.

Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

Question 3

During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

Options:

A.

Issue log

B.

Risk register

C.

Defect log

D.

Traceability matrix

Question 4

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

Options:

A.

Synchronous

B.

Informal

C.

Asynchronous

D.

Formal

Question 5

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

Options:

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Question 6

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Options:

A.

Decline because it is not included in the project scope.

B.

Assess the impact of the request and create a change request

C.

Create new functional and non-functional requirements for mobile devices.

D.

Revise the baseline of the project plan by adding the new requirements.

Question 7

A project team member wrote a user guide over the past ten days. Given the following scatter diagram.

Which erf the following can be formally conducted?

Options:

A.

The team member prioritized other tasks over the completion of this task

B.

The learn member had performance issues over time.

C.

There is a negative correlation with 6me and output

D.

This is a display of units of outstanding work to predict completion

Question 8

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

Options:

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Question 9

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options:

A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

Question 10

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

Options:

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Question 11

An IT infrastructure change request needs to be implemented in the production environment. Which of the following elements are the most important prerequisites? (Select two).

Options:

A.

Rollback plans

B.

Project management plan

C.

Deployment plan

D.

Asset management plan

E.

Communication plan

F.

Resource management plan

Question 12

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

Options:

A.

Social engineering

B.

Phishing

C.

Spoofing

D.

Hacking

Question 13

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Which of the following most likely represents the number of items in the backlog?

Options:

A.

23

B.

5

C.

10

D.

15

Question 14

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

Options:

A.

negotiating resources.

B.

assigning resources.

C.

assessing the resource pool.

D.

adding resources to the schedule.

Question 15

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

Options:

A.

Issue log

B.

Scope statement

C.

Risk report

D.

Change log

Question 16

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

Options:

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Question 17

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

Options:

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Question 18

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

Options:

A.

Allocate resources.

B.

Determine the project budget

C.

Develop a communication plan.

D.

Establish baselines.

Question 19

Which of the following would be considered operational security?

Options:

A.

Mobile device compliance

B.

Background screening

C.

Multifactor authentication

D.

Facility access

Question 20

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

Options:

A.

Implement the change.

B.

Approve the test plan.

C.

Notify customers.

D.

Develop a rollback plan.

Question 21

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

Options:

A.

Define the WBS.

B.

Develop a RAM.

C.

Manage the vendors.

D.

Assess the resource pool.

Question 22

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

Options:

A.

Memorandum of understanding

B.

Request for information

C.

Statement of work

D.

Non-disclosure agreement

Question 23

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

Options:

A.

The project utilized all of its available reserve.

B.

The project has scope creep.

C.

The project deviated from the critical path.

D.

The project is trending ahead of schedule.

Question 24

A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

Options:

A.

Removing access

B.

Closing contracts

C.

Project sign-off

D.

Project evaluation

Question 25

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

Options:

A.

Flat

B.

Projectized

C.

Weak matrix

D.

Functional

Question 26

Which of the following PRINCE2 processes includes creating the project plan?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Managing product delivery

D.

Directing a project

Question 27

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

Options:

A.

RFI

B.

RFP

C.

RFQ

D.

RFB

Question 28

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

Options:

A.

Architect

B.

Project sponsor

C.

Scrum master

D.

Product owner

Question 29

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Question 30

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

Options:

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

Question 31

Which of the following best represents the project impact to a company's brand value?

Options:

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.

The project meets the expected milestones and finishes on time and within budget.

Question 32

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

Options:

A.

Application deployment

B.

Rollback plans

C.

Validation checks

D.

Maintenance window schedules

Question 33

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

Options:

A.

Mitigate

B.

Transfer

C.

Accept

D.

Share

Question 34

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Options:

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

Question 35

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

Options:

A.

Smoke test

B.

Stress test

C.

Penetration test

D.

Regression test

Question 36

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Question 37

A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

Options:

A.

Demonstration

B.

Workshop

C.

Brainstorming

D.

Focus group

Question 38

Which of the following activities are important parts of the closing phase? (Select two).

Options:

A.

Releasing resources

B.

Locking risks

C.

Updating stakeholder register

D.

Closing contracts

E.

Completing the work breakdown structure

F.

Negotiating the next project

Question 39

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

Options:

A.

Escalate the finding to the change control board.

B.

Add a risk to the risk register for validation.

C.

Consult the RACI matrix to identify ownership of the risk.

D.

Have a meeting with the project sponsor and main stakeholders.

Question 40

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Question 41

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

Options:

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Question 42

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

Question 43

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?

Options:

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.

Question 44

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

Options:

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Question 45

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

Options:

A.

RFP

B.

WBS

C.

SLA

D.

SOW

Question 46

Which of the following software programs would be best to use to store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Question 47

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

Options:

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter

Question 48

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

Options:

A.

Remove the team member's access.

B.

Release the project resources.

C.

Collect the stakeholders' feedback.

D.

Have the closeout report approved.

Question 49

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

Options:

A.

Development

B.

Production

C.

Testing

D.

QA

Question 50

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

Options:

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

Question 51

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

Options:

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Question 52

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

Options:

A.

Transfer

B.

Mitigate

C.

Avoid

D.

Accept

Question 53

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RF

D.

RFP

Question 54

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

Options:

A.

Dashboard

B.

Gantt chart

C.

Work breakdown structure

D.

Requirements Traceability Matrix

Question 55

A company is creating a new technology. The company is concerned that the project details could be compromised if a cloud service is used, and another company could launch the technology before the current projected delivery. Which of the following can the company do to minimize this risk?

Options:

A.

Use an on-premises project management scheduling tool.

B.

Limit access to members of the project team.

C.

Mandate overtime to get the project completed sooner.

D.

Ensure all team members have signed a non-disclosure agreement.

Question 56

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

Options:

A.

Inform the CCB to stop communication.

B.

Establish a RACI matrix.

C.

Escalate the communication issues.

D.

Revise the communication plan.

Question 57

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Question 58

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

Options:

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Question 59

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Options:

A.

Document the request in the change control log.

B.

Communicate the change deployment.

C.

Conduct an impact assessment.

D.

Implement the change.

Question 60

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Question 61

Given the following network diagram:

Which of the following is the critical path?

Options:

A.

A-C-G-K-M

B.

A-B-D-l-L-M

C.

A-B-E-J-L-M

D.

A-B-F-L-M

Question 62

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

Options:

A.

Remove access.

B.

Complete the project sign-off.

C.

Release the resources.

D.

Outline the lessons learned.

Question 63

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options:

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Question 64

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Options:

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Question 65

Which of the following can a project manager infer from the following velocity chart?

Options:

A.

The project is on schedule.

B.

The project Is ahead of schedule.

C.

The project is behind schedule.

D.

The project is at risk.

Question 66

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

Options:

A.

Assign more resources to complete similar stories in the future.

B.

Break the stories into workable items that can be completed within one sprint.

C.

Extend the sprint duration when required with the approval of the product owner.

D.

Release the current progress into production and carry over the rest of the code for the next sprint.

Question 67

A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

Options:

A.

To move the system to a production environment

B.

To obtain project sign-off

C.

To formalize the end of the contract

D.

To release resources

Question 68

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Options:

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Question 69

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Select the new critical path.

Option A

Option B

Option C

Options:

Question 70

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

Options:

A.

Collate the lessons learned.

B.

Perform a gap analysis.

C.

Review existing artifacts.

D.

Conduct a retrospective.

Question 71

Which of the following can be used to determine whether a sample product is within an acceptable range?

Options:

A.

Scatter diagram

B.

Velocity chart

C.

Control chart

D.

Fishbone diagram