Who has the MOST control over project scope changes?
Several stakeholders and the project sponsor have indicated that they are not being supplied with project updates. As the project manager, which of the following should be done to address the situation?
Which of the following is the BEST reason to review the historical information from a similar project?
The project manager has the MOST authority in which of the following organizational structures?
A project manager has been engaged to deliver a project in South America and does not speak Spanish. More than 50 percent of the project team will be Spanish speaking. Which of the following would be the project managers BEST option?
Which of the following is an example of risk mitigation?
Which of the following is created as part of the closing phase?
A project manager is managing the delivery of a project awarded under a fixed-cost contract. The project cost was poorly planned and underestimated, but the projects overall scope and deadline cannot change. Failure to deliver the project is not an option. Which of the following will MOST likely be affected by these circumstances?
Work must be overlapped and completed in parallel rather than sequentially within the critical path in order to meet the end date of the project. Which of the following would be utilized?
The schedule estimates for a particular work package that is underway were not properly considered and the timescales are too tight. Which of the following methods should the project manager select to investigate?
Which of the following is the MOST common precedence dependency type?
A project manager must initially address a performance issue with a project team member.
Which of the following communication methods is BEST to use?
Which of the following would be considered a valid strategy in response to an adverse risk?
A project manager notices that status meetings are poorly attended and that one or two team members try to dominate the meetings. Which of the following should the project manager do to make the project status meetings more productive? (Select Two).
When does stakeholder identification initially take place?
Which of the following defines a project? (Select Two).
Which of the following contract types places the LEAST amount of risk on the seller?
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
Final project acceptance criteria are contained in which of the following?
The project has been terminated. Which of the following should be conducted with the project team before they are released?
A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?
All of the following occur during the project closure phase EXCEPT:
Which of the following risk response strategies involves shifting the negative impact of a threat, along with ownership of the response, to a third party?
A SPI of 1.1 means that the project is:
Which of the following techniques can a project manager use to assist with quality planning? (Select Three).
A project manager conducted a risk probability and impact assessment with the project team. In which of the following risk management processes did this occur?
One of the team members assigned to a project is not performing well. The team member is new and is not experienced in the type of work involved with this project. Which of the following is the BEST response to this situation?
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
A project manager has decided to increase the number of resources working on critical path activities. This is an example of:
The purpose of a WBS dictionary is to provide:
The amount of time ahead or behind schedule on a project is called the:
Which of the following would require that the project risk register be updated?
A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?
There are three teams assigned to the same project. Two of the project teams are ahead of schedule; however, the product does not meet the needed quality standards. The third project team is behind schedule, but their product meets the quality standards. Which of the following should be the NEXT step for the project manager?
Which of the following would be the MOST important objective of a kick-off meeting? (Select Two).
The project manager needs to determine the relationship between two variables. Which of the following tools will the project manager use?
A key stakeholder on a project advises the project manager that there is a component of the project that has yet to be decided. They are concerned that their needs regarding this component will not be addressed. In which of the following documents should the project manager record this information?
A project manager is receiving many requests for changes to a project. Which of the following did the project manager fail to complete?
The purpose of the WBS is to:
A project manager creates a detailed list of costs for each activity involved in the project and then uses the sum of the individual activities to create the budget. Which of the following cost estimating techniques was used?
A stakeholder wants information on how frequently the project manager will provide a status report. Which of the following documents would be the BEST place to find this information?
Which of the following is a benefit of a work breakdown structure (WBS)?
Refer to the attached Exhibit.
Which of the following is the duration of the critical path in the diagram?
Which of the following sequences represents the correct order for implementing a change request?
A project manager has determined the probability and impact of identified project risks. A meeting with the project team will be held to determine how to mitigate risks above the project threshold. Which of the following will be created during this meeting?
The communication plan for a project is a subset of which of the following documents?
A project manager learns that a team member has falsified work experience, and does not have the knowledge required to complete the task. Which of the following should the project manager do?
A quality control technician is diagramming test results on a run chart. The chart consists of twenty-five points, with twelve consecutive points below the median line; however, the other thirteen points alternate above and below the median line. The twelve consecutive points represent which of the following?
In order to validate a project, which of the following is required to complete a stakeholder analysis?
Which of the following is an input to a work breakdown structure (WBS)?
Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the EV of this project?
A project sponsor has requested that weekly status updates are to be sent by email, detailing the schedule performance index (SPI) and schedule variance (SV) of the project. In which of the following documents should these requirements be included?
If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?
Which of the following are characteristics of an approved project charter? (Select Two).
Which of the following would require that the project risk register be updated?
The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?
In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?
During the execution of an assigned task the developer informs the project manager of a missing component. Which of the following should the project manager do next?
Quality assurance is performed during which phase of a project?