Labour Day Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

CIPS L4M3 Commercial Contracting Exam Practice Test

Demo: 28 questions
Total 190 questions

Commercial Contracting Questions and Answers

Question 1

A company is considering entering a new market. Which of the following are the external factors that influence the difference between cost and price of this company? Select THREE that apply

Options:

A.

Procurement policy

B.

Process efficiency

C.

Business strategy

D.

Threat of substitution

E.

Competitiveness of the market

F.

Relative bargaining power of supplier and purchaser

Question 2

ABC Ltd is a UK based company. It plans to enter into a contract with XYZ Ltd which is based in Singapore. Which of the following are the mandatory elements for the contract between ABC Ltd and XYZ Ltd to be legally binding? Select THREE that apply.

Options:

A.

All parties must have capacity to contract

B.

The two parties must have intention to be bound

C.

The invitation to tender must be sent by the agreed deadline

D.

There must be an offer and an acceptance

E.

An amount of money must be paid upfront

F.

There must be an invitation to treat

Question 3

A construction company is undertaking a housing development project. They need lots of bricks and other building materials, but the construction site doesn't have large area for storage of materials. Therefore, the company's suppliers must deliver the building materials with fixed quantity and at fixed time intervals. What type of contract is used between the construction company and its suppliers?

Options:

A.

Framework agreement

B.

Spot transaction

C.

One off contract

D.

Call off contract

Question 4

In a sale contract, a clause requires the seller to "defend, reimburse, and hold harmless" the buyer and its personnel from and against any and all damages arising in connection with some specific circumstances. This clause is an example of...?

Options:

A.

Insurance

B.

Liquidated damages

C.

Indemnity

D.

Force Majeure

Question 5

Which of the following should include in the service level agreement that is an appendix of a contract?

1. How often the service is measured

2. Minimum qualification of supplier staffs

3. Remedies to resolve dispute

4. On time service delivery

Options:

A.

1, 3 and 4 only

B.

1, 2 and 3 only

C.

2, 3 and 4 only

D.

1, 2 and 4 only

Question 6

Which of the following documents are likely to have legal standing? Select TWO that apply:

Options:

A.

Quotation

B.

Request for information

C.

Tender

D.

Requisition

E.

Estimate

Question 7

Which of the following is the set of principles that enables courts to determine exactly what the written contract says and what that must mean, then the court will uphold that?

Options:

A.

Order of precedence

B.

Rules of interpretation

C.

Unfair Contract Act 1977

D.

Rules of contract formation

Question 8

To check whether supplier actually complies with the labour standards set out in the contract, the purchaser should have...?

Options:

A.

Right to penalise the supplier

B.

Right to terminate the contract

C.

Right of audit

D.

Right to rescind the contract

Question 9

When a contract has been agreed on the basis of a fraudulent misrepresentation, which of the following remedies are available?

Options:

A.

Damages only

B.

Rescission only

C.

An injunction only

D.

Both damages and rescission

Question 10

Which of the following are most likely to be substantive elements of the specification of a truck? Select TWO that apply:

Options:

A.

Guarantee

B.

Foreword

C.

Expected lifespan

D.

Ethics

E.

Abbreviation

Question 11

Which of the following can be considered as implied terms in a contract?

1. Case law

2. Statute

3. Trade custom

4. A term can never be implied, it must always be expressed by the parties

Options:

A.

1,3 and 4 only

B.

1, 2 and 3 only

C.

1, 2 and 4 only

D.

2, 3 and 4 only

Question 12

Which of the following should be used in a contract for window cleaning during the next three months?

Options:

A.

Variable pricing arrangement

B.

Fixed pricing arrangement

C.

Standard schedule of rates

D.

Cost-plus arrangement

Question 13

Danielle buys a car from Aaron. Not long after, she receives an proposal from Brian, who is interested in buying the car but his budget is very constraint. Then, Brian decides to sign a hire purchase agreement with Danielle which lasts 4 years. Brian lives very far from Danielle, so he hires Charlie to deliver the car to his place. During the transport, Charlie has an accident and the car is written off. At the time of accident, who has the title of the car?

Options:

A.

Charlie

B.

Aaron

C.

Brian

D.

Danielle

Question 14

Under a framework agreement, which of the following are supplier selection mechanisms? Select TWO that apply:

Options:

A.

Rescission of contract

B.

Mini competition

C.

Contract for lease

D.

Direct call-off

E.

Call off contract

Question 15

XYZ Ltd is negotiating a long-term supply contract of important parts with a supplier. Dave, procurement manager teams up with Alla, legal manager to construct a service level agreement. Dave is concerned that poor performance of supplier may cause damages to the operations of the organisation. Which of the following can be used in conjunction with SLA to compensate the buying organisation in case of supplier's poor performance?

1. Warranties

2. Force majeure clauses

3. Penalty clauses

4. Service credits

Options:

A.

1 and 3 only

B.

3 and 4 only

C.

1 and 2 only

D.

4 and 2 only

Question 16

Southwark is negotiating a contract with Orchard to provide software and IT services. Orchard will manufacture and install the products which are contractually supplied by IBM. Southwark’s procurement manager is worried that during the contract there would be some problems that they would not able to claim for damages from Orchard. Which of the following should be included in the head contract so that Southward can sue IBM, should the need arise?

Options:

A.

Negligence

B.

Indemnity

C.

Collateral warranty deed

D.

Insurance

Question 17

What does quantum meruit mean?

Options:

A.

As much as is earned

B.

A non-graduations promise

C.

As much as is paid

D.

An implied promise

Question 18

What does quantum meruit mean?

Options:

A.

As much as is earned

B.

A non-graduations promise

C.

As much as is paid

D.

An implied promise

Question 19

A company needs to source a product from oversea. It wants to overcome technical barrier to cross-border trade by using standards in the specification. Which of the following is most likely to be incorporated into that specification?

Options:

A.

National standards

B.

Company standards

C.

Brands

D.

International standards

Question 20

SFO procurement manager sent a request for quotation to Vogon International in which he determined the contract terms and specification. In SFO's standard terms and conditions, it is stated that 'Goods shall be delivered and Services performed by the applicable Delivery Date. Supplier must notify Buyer 3 days prior to the Delivery Date if Supplier is likely to be unable to meet a Delivery Date.'

Vogon replied with a quotation without any amendment to SFO's terms & conditions. The SFO procurement manager found the prices were reasonable and submitted to senior management. Senior management team accepted that quotation and sent a notification to Vogon. On the Delivery Date, Vogon said they had no capacity to supply the product as the quotation due to a workers' strike. Did Vogon breach any agreement with SFO?

Options:

A.

No, because Vogon had no intention to be bound by the quotation, therefore, it didn’t constitute a contract

B.

No, because the strike is a force majeur event, so Vogon did not breach any contract with SFO

C.

Yes, because the contract was formed since Vogon had sent the quotation as an acceptance to SFO’s offer

D.

Yes, because the contract had been formed between SFO and Vogon with the quotation as an offer and the notification as an acceptance

Question 21

In which of the following section of a specification, requirements for training to use the equipment will be set out?

Options:

A.

Performance

B.

Consultation requirements

C.

Implementation

D.

Issue reference

Question 22

Which of the following shall help the purchaser control the selection of tier 2 suppliers?

Options:

A.

Subcontracting clause

B.

Warranty clause

C.

Guarantee clause

D.

Insurance clause

Question 23

Which of the following will be included in a conformance specification?

1. Brand names

2. Description of the operating environments

3. Chemical formulae

4. Required safety level

Options:

A.

1 and 2 only

B.

1 and 3 only

C.

1 and 4 only

D.

2 and 3 only

Question 24

Which of the following are reasons why a buying organisation adopts a model contract?

1. Extremely advantageous terms for buyer

2. Correct legal terminology

3. Supplier cannot make variation to the model form

4. Specific to industry

Options:

A.

1 and 2 only

B.

2 and 4 only

C.

2 and 3 only

D.

1 and 4 only

Question 25

Since services are intangible, so KPIs for services must be qualitative in all circumstances. Is this statement correct?

Options:

A.

No, KPIs for services must always be quantitative so that they can be measured easily

B.

No, some KPIs for services are measurable by means of outcome, time and space performed

C.

Yes, quantitative KPIs are limited to timeliness of supply of goods, defective rates and in-full quantities, which are applied to monitor supplier of physical goods

D.

Yes, the only measure mattered to supply of services is end-users' satisfaction

Question 26

A senior procurement specialist in UK is preparing a specification in which ISO standards are used to send to global suppliers. Is this action appropriate?

Options:

A.

No, the procurement specialist must use BSI standards instead

B.

Yes, evert specification must have ISO standards

C.

Yes, ISO standards are globally recognisable

D.

No, ISO standards are unfamiliar to global suppliers

Question 27

Which of the following are features of performance specification?

1. Method of achieving the buyer's desired result

2. What needs to be achieved when using the product

3. Purposes of the product

4. Technical and physical characteristics of the product

Options:

A.

2 and 4 only

B.

1 and 2 only

C.

1 and 4 only

D.

2 and 3 only

Question 28

Which of the following is the set of principles that enables courts to determine exactly what the written contract says and what that must mean, then the court will uphold that?

Options:

A.

Order of precedence

B.

Rules of interpretation

C.

Unfair Contract Act 1977

D.

Rules of contract formation

Demo: 28 questions
Total 190 questions