Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

CIDQ IDPX Interior Design Professional Exam Exam Practice Test

Demo: 52 questions
Total 175 questions

Interior Design Professional Exam Questions and Answers

Question 1

What is the MOST critical aspect of an existing building to check before locating library shelving and densely packed filing cabinets?

Options:

A.

Location of sprinkler lines and heads

B.

Location of columns and bearing walls

C.

Load-bearing capacity of the building’s floor system

D.

Access route from loading dock to the final location

Question 2

In which type of space would occupant load be calculated using net square footage?

Options:

A.

exercise room

B.

airport terminal

C.

museum exhibit

Question 3

Which of the following should be installed at regular intervals to avoid cracking of a GWB ceiling from building structural movement?

Options:

A.

J mold

B.

U channel

C.

Control joint

D.

Elastic sealant

Question 4

When completing an analysis of the existing conditions for a two-story commercial building, what are some CRITICAL accessibility items to review?

Options:

A.

entrances, exit signs, and location of accessible parking

B.

exit signs, interior path of travel, and location of accessible parking

C.

entrances, restroom (washroom) facilities, and vertical transportation

D.

interior path of travel, fire protection system, and vertical transportation

Question 5

What rating is used to determine a material’s sound absorption?

Options:

A.

CAC

B.

STC

C.

NRC

D.

UL (CSA)

Question 6

Which wall assembly would produce the highest STC rating?

Options:

A.

2x4 studs at 16" [406 mm] OC, 2 layers of 5/8" [15 mm] gypsum board on each side, full batt insulation

B.

2-1/2" [64 mm] metal studs at 16" [406 mm] OC, 1/2" [13 mm] gypsum board on each side, full batt insulation

C.

3-1/2" [89 mm] metal studs at 16" [406 mm] OC, 5/8" [15 mm] gypsum board on each side, full batt insulation

Question 7

What is the PRIMARY benefit for incorporating a design firm?

Options:

A.

Limit liability of the principals

B.

Shelter company’s profits from taxes

C.

Enhance company availability to credit

D.

Protect company from negligence suits

Question 8

What is the MINIMUM fire rating for a door in a 2-hour fire separation wall?

Options:

A.

3/4-hour

B.

1-hour

C.

1 1/2-hours

D.

2-hours

Question 9

A building owner hires a design firm to renovate an existing office suite into a live-work space. What is the FIRST step the designer should take?

Options:

A.

Perform a site visit

B.

Confirm zoning ordinance

C.

Document the project drivers

D.

Verify the building construction type

Question 10

During an office renovation, a financial firm wants to continue occupying the space while maintaining daily functions. What is the BEST method for the designer to follow?

Options:

A.

Utilize fast-track scheduling for completion of the space as a whole

B.

Create separate permits for each area to be completed independently

C.

Designate one portion of the space to be completed prior to another beginning

Question 11

Earthquakes and the loads caused by winds are examples of

Options:

A.

Live loads

B.

Dead loads

C.

Static loads

D.

Dynamic loads

Question 12

The ground floor of a building contains a mixed occupancy with a retail store (9,500 sf [884 m²]) with an adjacent storage space (2,000 sf [186 m²]), a daycare (5,000 sf [465 m²]), and an office (6,000 sf [557 m²]). Based on the chart below, what is the occupant load for this floor?

Occupancy Type

Occupant Load Factor (sf/person)

Retail (Mercantile)

60

Storage

300

Daycare

35

Office (Business)

150

Options:

A.

305

B.

368

C.

524

D.

527

Question 13

Changes made to the contract documents during the bid (tender) process are documented in a(n)

Options:

A.

Bulletin

B.

Addendum

C.

Change order

Question 14

Why is corrective work completed post-occupancy often MORE costly for the contractor?

Options:

A.

The warranty has expired

B.

Progress payments are not included

C.

The work must be performed after hours

D.

Revisions are billed on a cost-plus basis

Question 15

Which elements are MOST important when preparing resilient sheet flooring estimates?

Options:

A.

Seaming diagram, roll width, and door thresholds

B.

Roll width, room dimensions, and seaming diagram

C.

Room dimensions, roll width, and location of columns

D.

Door thresholds, room dimensions, and location of columns

Question 16

Which wall section provides for a two-hour fire-rated wall?

Options:

A.

1 5/8" [41 mm] metal studs, 1/2" [13 mm] regular gypsum board applied to each side, 3/8" [9 mm] regular gypsum board applied to each side

B.

Two layers 1/2" [13 mm] metal studs, regular gypsum board applied to each side

C.

1 5/8" [41 mm] metal studs, 1/2" [13 mm] type X gypsum board applied to each side, 1/4" [6 mm] regular gypsum board applied to each side, 2" [50 mm] glass fiber insulation

D.

1 5/8" [41 mm] metal studs, two layers 1/2" [13 mm] type X gypsum board applied to each side, glass fiber insulation

Question 17

A project is considered substantial and complete when

Options:

A.

Partial occupancy has been issued

B.

Deficiencies have been documented

C.

Progress payments have been administered

D.

The owner can use it for its intended purpose

Question 18

Contract documents serve as the legal contract between

Options:

A.

the client and the designer

B.

the client and the contractor

C.

the designer and the contractor

D.

the contractor and the suppliers

Question 19

To reduce radon levels in a home, it is recommended that the

Options:

A.

crawl space is ventilated

B.

building is depressurized

C.

basement windows are sealed

D.

expansion joints are installed at slabs-on-grade

Question 20

A university is renovating the restrooms (washrooms) of a dormitory built in 1963 and is required to reduce the water usage by 20%. What is MOST important when specifying plumbing fixtures?

Options:

A.

durability & Green Seal fixtures

B.

cleanability & Energy Star fixtures

C.

accessibility & WaterSense fixtures

D.

sustainability & International Plumbing Code compliant fixtures

Question 21

How do project managers guide a project if they or the design team lacks expertise in a certain area?

Options:

A.

Find appropriate consultants and include them in the design team

B.

Use an appropriate consultant if a problem arises during the project

C.

Require project team members to research information on the design criteria

D.

Select one member of the design team to receive training in the expertise required

Question 22

What is the rentable square footage [m²] of a building?

Options:

A.

the tenant suite not including any common and shared areas of a building

B.

the tenant suite including all of common areas of a building such as lobbies, corridors, hallways and restrooms (washrooms)

C.

the tenant suite including a percentage of common areas of a building such as lobbies, corridors, vertical penetrations, hallways and restrooms (washrooms)

D.

the common and shared areas of a building such as lobbies, corridors, stairwells, meeting rooms, hallways and restrooms (washrooms) used by all building tenants

Question 23

The role of the project manager includes

Options:

A.

selecting a project team, establishing and overseeing the budget, and coordinating withconsultants

B.

preparing preliminary designs, coordinating with consultants, and developing proposals and contracts

C.

serving as the primary client contact, developing proposals and contracts, and producing project specifications

D.

establishing and overseeing the budget, producing schematic designs, and serving as the primary client contact

Question 24

What is one way to reduce indoor air pollutants?

Options:

A.

increase humidity levels

B.

install operable windows

C.

use materials with high VOCs

D.

decrease building temperature

Question 25

What is the BEST way for a designer to determine whether the payment application of a contractor is consistent with the work completed to date?

Options:

A.

Request a breakdown of the pricing in the payment application to be reviewed by the consultants

B.

Participate in periodic site visits to compare progress onsite to progress claimed in the payment application

C.

Review the project schedule to determine what should be completed by the date of the payment application

D.

Call the subcontractors individually to verify that the work noted on the payment application is indeed complete

Question 26

Which of the following is MOST likely to require a louvered door?

Options:

A.

IT closet

B.

Hotel room

C.

Executive office

D.

Dental exam room

Question 27

With regard to electrical systems, one responsibility of an interior designer is to provide the

Options:

A.

Quantity of junction boxes for light fixtures

B.

Quantity of conduit for wiring under carpet

C.

Location of electrical panel and circuit breakers

D.

Location of power required for built-in equipment

Question 28

What is required prior to occupancy to improve indoor air quality?

Options:

A.

clean the air intake vents

B.

run the mechanical system

C.

test carbon monoxide detectors

Question 29

Which party is responsible for requesting inspections during construction of a project?

Options:

A.

owner

B.

designer

C.

sub-contractor

D.

general contractor

Question 30

Upon review of all consultants’ drawings, the designer notices that the placement of a water closet is not consistent with the contract documents. What should the designer do?

Options:

A.

Provide the dimensions of the water closet along with a notation on the interior design documents of the water closet’s new location

B.

Coordinate the proper location with all parties through a change order

C.

Coordinate with the mechanical engineer and have the water closet relocated on the engineer’s drawings

D.

No action is necessary because the contractor is obliged to follow the interior design documents

Question 31

A lien has been placed on a building. What may be a probable cause for this action?

Options:

A.

A subcontractor has not been paid by the general contractor

B.

The certificate of substantial completion has not been issued

C.

The client requires more financing

D.

Contract documents do not comply with building code

Question 32

During early planning stages of a sustainable project, which of the following elements are the MOST important to develop?

Options:

A.

LED lighting and locally sourced materials

B.

Wind power and recycled content materials

C.

Composting toilets and renewable power sources

Question 33

What floor finish would BEST support a passive solar design strategy in a hot arid climate?

Options:

A.

vinyl

B.

wood

C.

carpet

D.

concrete

Question 34

The client has approved a selection for lounge seating and has selected a COM fabric for its reception area. What should the designer do NEXT?

Options:

A.

Send the COM information to the furniture vendor for approval of the fabric application

B.

Produce a purchase order for the COM fabric, and send the fabric and the order to the manufacturer

C.

Prepare the specifications for the furniture and list the chairs, COM information, and quantity needed

D.

Reselect a fabric that closely resembles the selected COM fabric and is offered by the furniture vendor

Question 35

What is the term for a continuous path of travel from any point in a building or structure to the open air outside at ground level?

Options:

A.

Area of refuge

B.

Exit discharge

C.

Horizontal exit

D.

Means of egress

Question 36

Which are overhead expenses in a design business?

Options:

A.

Rent, taxes and licenses, insurance, advertising, and non-billable support staff

B.

Advertising, accounts payable, marketing, loan payments, utilities, and rent

C.

Utilities, accounts receivable, taxes and licenses, insurance, and rent

D.

Billable support staff, rent, advertising, loan payments, utilities, and insurance

Question 37

What is the MOST efficient lighting control system a designer can incorporate in a fifth floor, south-facing office suite?

Options:

A.

roller shades

B.

automatic timers

C.

daylighting sensors

D.

occupancy sensors

Question 38

On a multi-tenant floor, what is the usable area when calculating square footage according to Building Owners and Managers Association (BOMA) standards?

Options:

A.

Tenant 1 and Tenant 2

B.

Tenant 1, Tenant 2, and Elevator Lobby 3

C.

Tenant 1, Tenant 2, and Electrical/Telephone 5

D.

Tenant 1, Tenant 2, Electrical/Telephone 5, and Elevator Lobby 3

Question 39

Upon completion of a project, what documents would the designer retain for their files?

Options:

A.

Record (as-built) drawings and specifications

B.

Post-occupancy evaluation and specifications

C.

Record (as-built) drawings and inspection report

D.

Post-occupancy evaluation and inspection report

Question 40

In a project that includes a home renovation and procurement of new furniture, what is the BEST fee structure?

Options:

A.

Hourly fee method and cost-plus method

B.

Square foot method and fixed fee method

C.

Fixed fee method and square foot method

D.

Value-oriented method and hourly fee method

Question 41

During construction, the general contractor notices conflicting information between the construction drawings and the specifications. The FIRST step the contractor should take is to

Options:

A.

issue a change order

B.

make an interpretation

C.

notify the owner of the discrepancy

D.

notify the designer of the discrepancy

Question 42

Which scheduling method BEST shows the interrelationships of tasks?

Options:

A.

work plan

B.

Gantt chart

C.

critical path

D.

milestone chart

Question 43

Which type of mechanical heating system uses pipes or tubing embedded within the ceiling, floor, or wall construction?

Options:

A.

electric

B.

radiant

C.

hot-water

D.

forced-air

Question 44

During which phase is it BEST to consider integrating a security system in a project?

Options:

A.

permit review

B.

post-occupancy

C.

schematic design

D.

construction documents

Question 45

The designer attends the weekly progress meetings and is responsible for the meeting minutes. How does the designer ensure that the minutes prepared are accurate?

Options:

A.

Issue a clause in the minutes indicating that minutes are approved and accepted as written

B.

Issue minutes including a clause stipulating minutes will be approved within 24 hours of issue

C.

Issue minutes including a clause enabling attendees to submit revisions within a specified time frame

D.

Issue draft minutes within 24 hours of the meeting, followed by final minutes within 72 hours of meeting completion

Question 46

When developing a design, which BEST unifies the project and provides specific direction for the design?

Options:

A.

Feasibility studies

B.

Concept statement

C.

Space allocation studies

D.

Programming and research

Question 47

If the net square footage [m²] is 50,000 square feet [4,645 m²] and usable square footage [m²] is 77,000 square feet [7,154 m²], what is the circulation factor?

Options:

A.

20%

B.

35%

C.

25%

D.

40%

Question 48

A contractor defaults on payments to a mechanical subcontractor. The subcontractor is protected and guaranteed payment by a

Options:

A.

payment bond

B.

mechanic’s lien

C.

performance bond

D.

builder’s risk insurance

Question 49

What do written specifications define?

Options:

A.

quantity

B.

form

C.

quality

D.

relationship

Question 50

What is the MINIMUM illumination level at the walking surface for a means of egress?

Options:

A.

1 footcandle [10.76 lux]

B.

2 footcandles [21.53 lux]

C.

5 footcandles [53.82 lux]

D.

9 footcandles [96.88 lux]

Question 51

A new hospital includes a cafeteria and a 60-person conference room. Which occupancy classifications would apply?

Options:

A.

assembly and business

B.

assembly and industrial

C.

institutional and business

D.

institutional and assembly

Question 52

A post-occupancy evaluation indicates that occupants are cold during winter months due to the building’s HVAC system not performing according to design. What would have prevented this situation?

Options:

A.

commissioning

B.

additional diffusers

C.

a punch (deficiency) list

D.

an underfloor distribution system

Demo: 52 questions
Total 175 questions