Big Cyber Monday Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

BCS TM3 ISTQB Certified Tester Advanced Level - Test Management v3.0 Exam Practice Test

Demo: 15 questions
Total 51 questions

ISTQB Certified Tester Advanced Level - Test Management v3.0 Questions and Answers

Question 1

You are a test manager managing a test team and working at a government agency. The test team is responsible for performing the system test. Senior management has been provided with the following test objective for a new project:

“The system should be of high quality.”

Using the SMART goal methodology, which of the following statements would be appropriate as a revision to the defined test objective by management?

Options:

A.

All defined requirements shall be implemented and function without problems

B.

At least three weeks of system testing shall be performed and no major defects will be outstanding before going live

C.

The number of user issues reported in the first 3 months after going live shall be less than an average of 1 per week

D.

During component testing a statement coverage of 90% shall be achieved

Question 2

Which of the following characteristics of risk-based techniques is not appropriate to a more heavyweight risk-based technique?

Options:

A.

Defined processes and detailed documentation

B.

Risk likelihood and risk impact on an ordinal scale

C.

Broad group of stakeholders

D.

Mathematical formulas

Question 3

For which type of testing would a test manager be involved with establishing benchmarks?

Options:

A.

Functional Testing

B.

Non-Functional Testing

C.

Testing Black-box

D.

White-box Testing

Question 4

Study the following characteristics:

Avoid re-inventing the wheel

Pool on experiences from earlier projects

They prompt thought in areas that are sometimes forgotten

Often used when compliance to specific standards is relevant

To which risk identification technique do these characteristics relate?

Options:

A.

Risk Workshops

B.

Retrospectives

C.

Brainstorming

D.

Checklists

Question 5

You have been contracted to manage the user acceptance testing of a new reservation system for a travel agency. The reservation system is being developed by a third party. Detailed specifications are available, and an estimate of the total development effort exists. The system will be delivered in four agreed increments.

Which of the following estimation techniques would be most appropriate to use in this context?

Options:

A.

Estimation based on ratios

B.

Extrapolation

C.

Wide-band Delphi

D.

Planning poker

Question 6

When reading books and watching recorded videos are used as a way to acquire skills and knowledge, which approach to competence development is typically being used?

Options:

A.

Training and education

B.

Self-study

C.

Peer learning

D.

Training on-the-job

Question 7

To which category of cost of quality does "fixing a defect found during testing" belong?

Options:

A.

Defect prevention costs

B.

Appraisal costs

C.

Internal failure costs

D.

External failure costs

Question 8

Management is sceptical regarding the budget request (€25,000) for the next testing project. You are asked for a cost-benefit calculation. Based on historical data from several projects, you have the following numbers:

Average prevention cost per defect: €200

Average cost of detection per defect: €400

Average cost of internal failure: €150

Average cost of external failure: €2,500

Expected number of defects to be found in this project during testing: 50

What is the result for the expected cost-benefit calculation for the upcoming project?

Options:

A.

€62,500

B.

€72,500

C.

€87,500

D.

€92,500

Question 9

Assume that you are using traceability to manage test case coverage against test conditions. During test analysis, three test conditions were identified. Test design for system testing has been completed and 10 test cases (TC1 to TC10) have been designed, as described by the following traceability matrix (“C” indicates a critical test case, while “NC” indicates a non-critical test case):

[traceability matrix not visible in the prompt]

The exit criterion for system testing states that each test condition must have all the associated critical test cases successfully executed (passed) AND all associated non-critical test cases at least executed.

The following is the situation after three days of system testing:

TC1, TC2, TC4, TC5, TC7, TC9: passed

TC3, TC10: failed (with an associated open defect report)

TC6, TC8: not run

Management wants to decide whether to release the system. You advise them that the system does not yet meet the defined exit criteria.

Based only on the given information, which test condition does not yet meet the stated exit criterion?

Options:

A.

Test condition 1

B.

Test condition 2

C.

Test condition 3

D.

None, all meet the stated exit criteria

Question 10

Which of the following activities in the test process is considered to deliver a document which can be used as a major input for test process improvement?

Options:

A.

Test Planning

B.

Test Monitoring

C.

Test Execution

D.

Test Completion

Question 11

In multi-team environments with hybrid software development approaches, there are various challenges in the context of defect management, such as:

i. Alignment of defect attributes to be used

ii. Prioritisation of defects

iii. Alignment of the approach for defect fixes

Solutions to the above-mentioned challenges include:

Options:

A.

The product owner should be involved in the defect management meetings

B.

Synchronisation between the defect management tools

C.

Transparency of plans by sharing them between teams via dashboardsWhich solution is related to which challenge?

D.

A = i, B = ii, C = iii

E.

A = i, B = iii, C = ii

F.

A = ii, B = i, C = iii

G.

A = i, B = ii, C = i

Question 12

You are a test consultant involved in setting up and implementing retrospectives in an organisation that is developing software based on an Agile lifecycle. The Agile teams are experiencing problems on product quality, so the retrospectives will be specifically focused on the testing practices and processes.

Which of the following is an example of a good practice for a test retrospective?

Options:

A.

Only testers should be involved in the retrospectives since they perform testing and will know what should be improved

B.

Because an Agile team is empowered, all improvement actions should reside within the team

C.

Brainstorming sessions can be used to generate ideas on how to resolve the root causes of testing issues identified

D.

An action plan for the improvements identified is too much documentation in an Agile context; the team members are already motivated to implement the improvements based on the retrospective

Question 13

Which status would typically be assigned to a false-positive defect report during defect management?

Options:

A.

Rejected

B.

Accepted

C.

Resolved

D.

Deferred

Question 14

You are working as a test manager at a company that develops software applications for the mobile domain. The organisation has recently been assessed against TMMi. This assessment showed that the company is a TMMi level 1 organisation. The projects use the V-model lifecycle and an independent test team exists. The test team consists of both experienced and novice testers. The team has not yet been formally trained in testing, but an ISTQB Foundation course is scheduled to take place in two months.

In your role as a test manager working in the independent test team, you have recently performed a risk assessment for a mobile software application to be developed. You want the features that have been identified as major risks to be tested more thoroughly.

Which test practice would you propose to mitigate the identified major product risks?

Options:

A.

Assign the most experienced testers to test the features with the highest risk levels

B.

Use test design techniques such as equivalence partitioning and decision table testing

C.

Start a test improvement project to achieve TMMi level 2

D.

Create pairs of developers and testers to test the features with the highest risk levels together

Question 15

Which of the following statements about test management activities for an iterative development model is false?

Options:

A.

With testware the focus is on acceptance criteria and definition of done. The level of documentation is minimal.

B.

The test approach is embedded within iterations, with a focus on adaptability and feedback.

C.

Reporting is done at project milestones.

D.

Roles are integrated; facilitator or coach typically replace the traditional test manager.

Demo: 15 questions
Total 51 questions