Question 1

The BIM manager oversees both design coordination and post-handover data requirements and is asked to ensure the digital deliverables align with the owner’s long-term asset-management system.

To minimize information gaps, inconsistencies in file formats, and unclear responsibilities throughout delivery, which tool should the BIM manager rely on to define who provides what information, when, and in what format, from design through facilities handover?

Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.

Options:

A.

The file-naming protocol and model-authoring standards.

B.

The Quantity Takeoff Checklist and/or the BIM Execution Plan.

C.

The Model Element Table and Level of Development (LOD) matrix.

D.

The Master Information Delivery Plan (MIDP) and/or the BIM Execution Plan.

Question 2

During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash results. Many are low-priority issues, such as wall-grid overlaps and minor duct-ceiling intersections. The project’s clash matrix outlines only high-impact clashes between structural, MEP, and architecture in specific zones.

For the BIM manager, what is the most appropriate next step to align clash reporting with the project’s coordination strategy?

Options:

A.

Share the full clash report with all project teams and instruct them to determine and resolve the issues they consider most important.

B.

Export the entire clash list into spreadsheet format so project managers can manually sort, review, and prioritize the items by trade.

C.

Disable or relax selected non-critical clash rules within the detection software to temporarily reduce the total number of reported issues.

D.

Apply the clash matrix to filter out low-priority clashes, adjust detection tolerances where appropriate, and produce reports for each discipline’s scope.

Question 3

A Revit model in Autodesk Forma that does not have any consultant links is opening for all team members except one. The project BIM manager has already audited and compacted the model.

What should the BIM manager do so that the team member can open the model?

Options:

A.

Clear the user’s collaboration cache files and retry again.

B.

Agree to a user request for a hardware upgrade.

C.

Roll back the model to a previous version.

D.

Publish the model to Autodesk Forma and ask the user to retry again.

Question 4

A multidisciplinary healthcare project has multiple firms contributing to a federated model. Early coordination reviews reveal data inconsistencies, unauthorized edits, and missed communication between design teams.

What is the most appropriate first step to establish effective coordination and risk mitigation across the delivery team?

Options:

A.

Assign responsibility for each firm to review and maintain its own models, document identified issues, and present findings during scheduled coordination meetings.

B.

Implement tighter access controls within the Common Data Environment by defining permissions, monitoring edits, and restricting changes to authorized team members.

C.

Develop and communicate protocols that clarify model ownership, editing rights, quality-control procedures, and expected communication channels.

D.

Require each discipline to submit a detailed modelling strategy, document its assumptions, and use this information to identify and resolve potential design conflicts.

Question 5

Refer to the exhibit.

A client has provided the design team with a title block family and a Shared Parameters file that must be used as part of their standards. Those provided parameters must be applied both in the Project Information area as well as the title block.

When the design team is in the project model and attempts to fill in information into the title block parameters, a question mark appears. What is the likely cause of this?

Options:

A.

The shared parameters were included in the title block family but were not loaded into the project file.

B.

The parameters were not included in the Shared Parameters file provided by the client.

C.

The Shared Parameters file was not added to the title block family and was using text instead of a label.

D.

The Sheet and Project Information fields were overwritten in the title block.

Question 6

The BIM manager receives an external lighting CAD file to link into the Architectural model and realizes the link is not vertically or horizontally aligned.

What fix needs to happen to resolve this misalignment?

Options:

A.

The BIM manager needs to go to a 3D view and move the model to align with the architectural geometry.

B.

The Lighting team needs to fix its shared coordinates to match those of the Architectural model and reissue the file.

C.

The BIM manager needs to acquire the shared coordinates of the CAD file.

D.

The Lighting team needs to add gridlines so the BIM manager can align its CAD file to the architectural gridlines.

Question 7

During a project onboarding meeting, the client provides their current BIM standards and templates to the BIM manager. The project will involve multiple consultants across different regions and is being delivered under a fast-track schedule with a high volume of design iterations. The client has also indicated that they plan to use a new collaboration platform not previously piloted on similar project types.

The BIM manager must evaluate whether the client’s materials are sufficient and aligned with digital-delivery expectations, collaboration goals, and coordination requirements.

Given these factors, which two of the client’s BIM resources must be prioritized for review to evaluate their ability to support digital delivery and coordination across regions, teams, and time constraints? (Select two.)

Options:

A.

Confirm that shared-parameter files and naming conventions are consistent across provided templates and documentation to support data consistency.

B.

Review the provided project templates to confirm whether units, naming conventions, and view organization are consistent and support coordination.

C.

Prioritize identifying which users from the client’s team will need Revit training or software access before the project begins.

D.

Review previous projects’ sample sheets and title blocks to assess the visual style preferred by the client.

E.

Confirm whether the templates allow full customization by each discipline so teams can adapt the setup to their own preferences.

Question 8

A BIM manager is creating a firm-wide template for mobilization plans to outline the key steps, resources, and strategies required to set up and launch BIM operations at the beginning of projects.

Which two components should the template include to accomplish the goal? (Select two.)

Options:

A.

Common Data Environment.

B.

Contract template.

C.

Roles and responsibilities.

D.

Specifications.

E.

Project milestone dates.

Question 9

A designer needs to add Area Lines in an Area Plan, but upon adding them, they receive a message stating that none of the created elements are visible.

Where can they check to resolve the issue?

Options:

A.

Plan Region

B.

Detail Level

C.

Area Scheme

D.

Visibility/Graphics

Question 10

An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client’s preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model’s compatibility with internal systems.

As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)

Options:

A.

Any add-ins required.

B.

Project units.

C.

Software version and build.

D.

Shared Coordinates.

E.

Graphic standards.

Question 11

What setting should be defined in the Family Template for Mechanical Equipment families intended for use in projects in specific countries?

Options:

A.

Object Styles set to the country’s official language.

B.

All parameters set to Instance.

C.

Project Location set to the intended country.

D.

Units set to the intended country’s standard format.

Question 12

The BIM manager has finalized the BIM Execution Plan (BEP) for a multi-discipline educational facility project. Some consultants have already begun modelling, while others are onboarding late. A few external stakeholders are not listed in the original BEP distribution but will need access to coordinated models during design and preconstruction.

What two actions could be taken in order to manage distribution of updates? (Select two.)

Options:

A.

Update and reissue the BEP only to the consultants who have not yet started modelling to ensure they catch up to project standards.

B.

Formally distribute the BEP to all relevant parties as an addendum to the contract.

C.

Formally distribute the BEP to all relevant parties and confirm receipt to ensure alignment on roles, responsibilities, and agreed BIM processes.

D.

Upload the BEP in a shared Autodesk Forma Data Management folder to ensure version tracking and verify access to stakeholders.

E.

Wait until construction coordination begins before sharing the BEP with external stakeholders.

Question 13

Refer to the exhibits.

A BIM manager is preparing a site model that includes three separate buildings. Which exhibit shows the correct way to assemble and position the individual building models on the site while maintaining proper coordinates and orientation?

Options:

A.

Exhibit 4

B.

Exhibit 3

C.

Exhibit 2

D.

Exhibit 1

Question 14

For a project that is well into its Design Development phase, it is discovered that there is an easement on the property that increases the setback by 1 ft 6 in. (450 mm).

Which method for updating the geolocation of the project would be least disruptive to the extended design team?

Options:

A.

Specify coordinates at a point along the setback edge using the new data.

B.

Reposition the civil site property-boundary resource file, then publish the new position coordinates to the civil file.

C.

Select all model elements in a 3D view and move them away from the increased setback boundary.

D.

Reset coordinates, reposition the site property-boundary resource file, then acquire coordinates from the repositioned civil file.

Question 15

Refer to the exhibits.

The firm’s technical group would like to show demolished elements as dashed red in all future projects. The BIM manager is updating the Revit template to meet this new standard.

Which Phase Graphic Override will accomplish this?

Options:

A.

Exhibit 4

B.

Exhibit 2

C.

Exhibit 1

D.

Exhibit 3

Question 16

The BIM manager is working on a mixed-use project in which consultants are on different platforms and delivery timelines. The client requires COBie-compliant data handover and weekly coordination uploads.

What is the best approach to ensure project-specific BIM processes are effectively implemented from the outset?

Options:

A.

Facilitate a project-specific BIM kickoff session to align all contributors on workflows, deliverables, and data-handover protocols.

B.

Accept each firm’s standard BIM workflows and distribute them to the team to promote consistency across consultants.

C.

Focus on setting the Common Data Environment permissions first and allow teams to organize their workflows independently.

D.

Establish a baseline BIM Execution Plan, then adjust it incrementally based on coordination issues as they arise.

Question 17

A firm-wide Revit template has an advanced setup of views preset on sheets. A renovation project has a linked as-built model with levels that do not align with levels from the model template.

What method should a BIM manager use to update the levels and create grids in sync with the resource model, without requiring extensive reworking of the preset sheets?

Options:

A.

Align model levels to the linked levels and use Copy/Monitor to duplicate the linked grids.

B.

Create a Scope Box around the linked model and assign it to the template levels and grids.

C.

Delete the template’s levels and use Copy/Monitor to duplicate the linked levels and grids.

D.

Customize a View Template to hide the template levels and only show the linked levels.