Summer Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

Adobe AD0-E911 Adobe Workfront Project Manager Certified Professional Exam Practice Test

Demo: 28 questions
Total 95 questions

Adobe Workfront Project Manager Certified Professional Questions and Answers

Question 1

A user wants to add users to a proof based on who requested the project and the additional approvers listed in the request.

Which Workflow should the user choose?

Options:

A.

Automated

B.

Basic

C.

Manual

Question 2

A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a Project report. In the filter, update the actual completion date value to " past year " and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select " month. "

B.

Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select " month of year. "

C.

Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to " past year " and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select " month of year. "

Question 3

A project manager has been asked to create a report showing the planned completion date for all the project manager ' s projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a new report. In the filter, update the project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date and set the default view to “Calendar View.”

B.

Visit the Calendars page and create a new calendar. In the filter, update the date field to Planned Dates and update the Project Owner ID field with the project manager’s name. Set the color to purple.

C.

Visit the Reports page and create a new calendar. In the filter, update the Project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date.

Question 4

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

Options:

A.

The task Duration should be set to 2 days. A predecessor with a Finish-Start Dependency Type should be added to the second task with a lag of 5 days.

B.

Planned Hours should be set to 48 hours. A predecessor with a Finish-Start Dependency Type should be added to the first task with a lag of 5 days.

C.

The task Duration should be set to 48 hours. A predecessor with a Start-Finish Dependency Type should be added to the second task with a lag of 5 days.

Question 5

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

Options:

A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.

B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

Question 6

A project manager has set up and launched a new project for an annual marketing campaign.

Where can the project team locate their work requests?

Options:

A.

Email, Workfront Home, Project tasks list

B.

Email, Automatic Reminders, Workfront Home

C.

Event Notifications, Approval processes, Email

Question 7

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

Options:

A.

Actual Completion Date

B.

Progress Status

C.

Status

Question 8

Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?

Options:

A.

Update the project status.

B.

Recalculate the project timeline.

C.

Update the project baseline.

Question 9

A marketing team determines that in the future, their projects must be reviewed by the Project Sponsor before the project is closed. What is the best practice to ensure that each project is properly reviewed and approved?

Options:

A.

Create a new approval process in the global setup area that will ensure that an approval process is attached to all Marketing Projects.

B.

Create a single-use approval process on each project that routes to the Project Sponsor for approval once the project status is set to Complete.

C.

In the project template, add an approval process routing to the Project Sponsor for approval once the project status is set to Complete.

Question 10

The vice president of operations asks one of their project managers to create a Workfront report that automatically sums columns so that it is similar to a Microsoft Excel file. The project manager decides to use a matrix grouping to show the data, but one of the columns isn’t showing in the report.

What did the project manager forget to do?

Options:

A.

Summarize the columns.

B.

Update the grouping using text mode.

C.

Update the conditional formatting of the column.

Question 11

Which field is used to create a milestone step on a milestone path in the Setup area?

Options:

A.

Status

B.

Description

C.

Key

Question 12

A video designer is spending an excessive number of hours on a project that involves editing a TV commercial. The tasks are keeping the designer from completing other assigned work. After discussing the matter with the designer, the project manager determines that the additional hours for this project are necessary and suspects that the number of hours budgeted for the video designer ' s time on this project was too low in comparison to the actual need. The project manager will need data to illustrate the problem and potentially request more resources for this project so that the designer can still meet commitments on other assigned work.

Which native Project tool is designed to illustrate data on how the Planned Hours for the video designer on this project vary from the Actual Hours spent on the project?

Options:

A.

Utilization

B.

Workload Balancer

C.

Hours

Question 13

What do the green symbols in the report below signify?

Options:

A.

On Time

B.

At Risk

C.

Late

Question 14

The art director is reviewing and approving a proof and has requested that they only get email notifications for a new proof or version. What Email alert option should be assigned to them on the workflow?

Options:

A.

Decisions and Notify recipients about this proof is selected

B.

Disabled and Notify recipients about this proof is selected

C.

Decisions and Notify recipients about this proof is not selected

D.

Disabled and Notify recipients about this proof is not selected

Question 15

A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?

Options:

A.

Set the task condition to At Risk.

B.

Update the Commit Date on the task.

C.

Work on the task and complete it in the given duration.

Question 16

What are two characteristics of a Group in Workfront? (Choose two.)

Options:

A.

A Group can be tagged in an Update thread communication.

B.

A Group assignment is not required for a user.

C.

A Group can be associated with a Company or a Project.

D.

A user can be assigned as Group Administrator of a Group.

Question 17

A resource manager wants to review how resources are utilized across multiple projects to make staffing decisions.

Which Workfront tool should the resource manager use?

Options:

A.

Scenario Planner

B.

Timesheets

C.

Workload Balancer

Question 18

What do the connector lines between tasks in a Gantt chart represent?

Options:

A.

Critical path

B.

Multiple assignments

C.

Predecessor relationship

Question 19

The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions.

Which report grants the executive team this visibility?

Options:

A.

A project report showing active projects grouped by portfolio showing project condition, project priority, and custom data aligning the project initiative to business goals.

B.

A portfolio report showing all projects grouped by team showing project condition, the alignment score, and custom data aligning the project initiative to business goals.

C.

A program report showing active projects grouped by department showing program health, project urgency, and custom data aligning the project initiative to business goals.

Question 20

A task won’t close when trying to select “Complete.”

Which two reasons block someone from being able to close a task? (Choose two.)

Options:

A.

A predecessor task is “In Progress.”

B.

The subtasks are not “Complete.”

C.

The task is a predecessor to another task.

D.

The task is assigned to a job role and not an individual user.

E.

The project is “Active.”

Question 21

What are two ways to associate milestone steps to tasks? (Choose two.)

Options:

A.

In-line editing a task list on a project

B.

From the Milestone View in the Projects area

C.

Through bulk-editing multiple tasks

D.

In the settings area of a task

Question 22

A project manager has been asked to work on a cross-departmental company-wide initiative. There will be many individuals assigned to each task.

What should the project manager ask users to do when it comes to completing tasks?

Options:

A.

Users do not need to complete tasks when multiple users are assigned.

B.

Mark the task as " Done with my part. "

C.

Make an update and tag the project manager.

Question 23

The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.

Which task settings need to be configured to meet these requirements?

Options:

A.

The Task Constraint should be set to Must Start On with Planned Time set to 2 weeks and Duration set to 10 hours.

B.

The Task Constraint should be set to Must Start On with Planned Hours set to 10 hours and Duration set to 2 weeks.

C.

The Task Constraint should be set to Start Date of September 23 with Planned Hours set to 10 hours and Issue Duration set to 2 weeks.

Question 24

Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?

Options:

A.

Critical Path

B.

Baselines

C.

Milestones

Question 25

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?

Options:

A.

Change the Task Duration Type to Effort Driven

B.

Change the Task Duration Type to Calculated Work

C.

Change the Task Constraint to Fixed Dates

D.

Change the Task Constraint to As Soon As Possible

Question 26

A system administrator has created a Marketing Request Queue that routes to the marketing team. This team needs to manage various incoming requests from the organization through emails, instant messaging, and conversations. Team members receive request notifications in their emails but are still having difficulties monitoring and prioritizing incoming requests.

Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?

Options:

A.

Four reports showing the entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, a third report that shows recently completed requests, and a fourth report that shows the schedule assigned to each team member.

B.

Two reports showing the priority and actual completion date of each request, i.e., one that shows active requests and another that shows recently completed requests.

C.

Three reports showing the priority and entry date of each request, i.e., one that shows requests in a New status, one that shows requests in an In Progress status, and one that shows recently completed requests.

Question 27

A statement of work is uploaded to the document section of a project as reference material. How should the file be uploaded into Workfront?

Options:

A.

Document

B.

Proof

C.

Approval

Question 28

A project manager needs to see specific tasks and issues across all of their projects in a single view. The project manager only needs to see tasks and issues that are currently pending approval, and the results should be grouped by project. What steps should the project manager take to create this view?

Options:

A.

Visit the Project page and create a new filter. Update the " Pending Approval " filter to " true " and update the Project Owner ID field to the project manager’s name. In the grouping tab, add a grouping for project name.

B.

Visit the Reports page and create a task report and an issue report. In the filter tab for each report, update the " Pending Approval " filter to " true, " and update the Project Owner ID field with the project manager’s name. In the grouping tab for each report, add a grouping for project name. Add both reports to a new dashboard.

C.

Visit the Reports page and create a Pending Approvals report. In the filter tab, update the Project Owner ID field with the project manager’s name and update the Object ID field to " tasks " and " issues. " In the grouping tab, add a grouping for project name.

Demo: 28 questions
Total 95 questions