11.11 Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70percent

SAP C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Exam Practice Test

Demo: 24 questions
Total 165 questions

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Questions and Answers

Question 1

Which type of down-payment chain allows you to monitor receivables to customers and to gain information on past and future incoming payments?

Please choose the correct answer.

Response:

Options:

A.

Credit-side down payment

B.

Debit-side down payment

C.

Credit memo

D.

Debit memo

Question 2

What is copied when transferring a simulation version back to an operative project?

There are 3 correct answers to this question.

Response:

Options:

A.

Plan costs

B.

WBS elements

C.

Actual work

D.

Maintenance orders assigned to the project

E.

Network activities

Question 3

Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.

What is the status that must be set before you can enter actual start and actual end dates?

There are 2 correct answers to this question.

Response:

Options:

A.

Partially released

B.

Released

C.

Partially set

D.

Partially finished

Question 4

Which types of networks store all the activity and material component costs at the network header level and behave in the same way as all other order categories?

Please choose the correct answer.

Response:

Options:

A.

Order header networks

B.

Order category networks

C.

Assignment networks

D.

Header assigned networks

Question 5

How can you update the degree of processing for an activity?

Options:

A.

By charging the activity

B.

By confirming the activity

C.

By using results analysis

D.

By scheduling the activity

Question 6

For which objects can billing plans be created? (2)

Options:

A.

Activities

B.

Sales order items

C.

WBS elements

D.

Milestones

E.

Project definition

Question 7

Which indicator determines whether summarization is executed on the basis of classification or master data characteristics; in a network profile?

Please choose the correct answer.

Response:

Options:

A.

Proj.summ.master data indicator

B.

Project summarization indicator

C.

Capacity requirement indicator

D.

Version profile indicator

Question 8

Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning?

Please choose the correct answer.

Response:

Options:

A.

Scheduled orders

B.

Procurement orders

C.

Planned orders

D.

Stock orders

Question 9

Which of the following types of reports are avaialable for financial reporting? (2)

Options:

A.

Profitability Analysis reports

B.

Cost element reports

C.

Profit Center Accounting reports

D.

Hierarchy repost

Question 10

Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?

Please choose the correct answer.

Response:

Options:

A.

Trend technique

B.

Project technique

C.

Milestone technique

D.

Period indicator technique

Question 11

Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?

There are 3 correct answers to this question.

Response:

Options:

A.

Scheduling must have been carried

B.

A distribution key must be maintained in the work center

C.

A work center must be maintained in the activity

D.

The capacity requirements indicator must not be set in the network header

Question 12

In resource-related billing if you do not want to bill a customer for a dynamic item, where do you enter this information?

Please choose the correct answer.

Response:

Options:

A.

You can enter in an apportionment reason

B.

You can enter in reason code

C.

You can enter in reference code

D.

You can enter in reason for rejection

Question 13

Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element?

Please choose the correct answer.

Response:

Options:

A.

Manual planning in billing elements in the project structure

B.

Sales order planning

C.

Billing plan in project billing elements

D.

Hierarchical billing plan

Question 14

What is the starting point for milestone billing?

Please choose the correct answer.

Response:

Options:

A.

Purchase requisition

B.

Purchase order

C.

Goods receipt

D.

Sales order item with a billing plan

Question 15

When using budgeting and active availability control, which business transactions affect the current budget?

There are 3 correct answers to this question.

Response:

Options:

A.

Cost element planning

B.

Original budget

C.

Revenues

D.

Transfers

E.

Supplements

Question 16

Items procured through which of the following methods are not assigned to a stock segment and do not pass through a warehouse?

Please choose the correct answer.

Response:

Options:

A.

Indirectly

B.

Vendors

C.

Directly

D.

Non project stock items

Question 17

What are the components on which reporting is based upon, in profit center accounting?

There are 2 correct answers to this question.

Response:

Options:

A.

Cost centers

B.

Cost elements

C.

Profit centers

D.

Profit center hierarchy

Question 18

Which account assignment category is important for non-valuated project stock with WBS and sales order item?

Please choose the correct answer.

Response:

Options:

A.

E = quantities and values managed in the sales order item

B.

D = quantities managed using sales order item and values managed in projects

C.

G = plant stock, values managed using projects

D.

Q = quantities and values managed in projects

Question 19

All the currency-dependent data in the Project System is managed in three different currencies in parallel. These are;

There are 3 correct answers to this question.

Response:

Options:

A.

Business Area Currency

B.

Controlling area currency

C.

Object Currency

D.

Transaction currency

Question 20

In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account assignment elements. What is the use of this assignment?

There are 3 correct answers to this question.

Response:

Options:

A.

This assignment can then be used to display the planned costs of the orders of the project

B.

This assignment can then be used to display the unit costs of the orders of the project

C.

It can be copied to a new project

D.

Cost planning can be moved automatically along with the activities

Question 21

Which of the following cost planning transactions are related to Account assignment?

There are 3 correct answers to this question.

Response:

Options:

A.

Invoice posting

B.

Goods movement

C.

Confirmations

D.

Purchase requisitions

Question 22

In which of the following levels can you execute BOM transfer in the order browser?

There are 3 correct answers to this question.

Response:

Options:

A.

For multiple assemblies

B.

For the whole multi-level BOM for a sales order item

C.

For a sub-tree

D.

For an individual assembly

Question 23

Which costing supplies strategic information that can be used to reduce overheads and increase profitability by highlighting unprofitable products or customers?

Please choose the correct answer.

Response:

Options:

A.

Overheads costing

B.

Planned costing

C.

Profitability costing

D.

Activity based costing

Question 24

What does ā€˜Eā€™ determine in account assignment while using consumption posting indicator to determine the controlling object for the sales item?

Please choose the correct answer.

Response:

Options:

A.

E determines that the sales order is a controlling object

B.

E determines that the sales order is a project is a controlling object

C.

E determines that the sales order items are relevant for delivery through sales and distribution

D.

E determines that the sales order is a cost object

Demo: 24 questions
Total 165 questions